Completed No litigation declared Others project

Grishma Heights

By RIGHT CHANNEL CONSTRUCTION PVT LTD

RG-MH-47336 · RERA P51800012108 · Last updated on MahaRERA portal: 4 Jan 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

Grishma Heights is a Others project by RIGHT CHANNEL CONSTRUCTION PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012108 on 1 Sep 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameGrishma Heights
  • TypeOthers
  • Location
    • mg road
    • kandivali west
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012108
  • ReraGenie IDRG-MH-47336

Builder

  • NameRIGHT CHANNEL CONSTRUCTION PVT LTD
  • Entity typeCompany
  • CINU45202MH2008PTC188854
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredSep 2017First promiseDec 2018Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Grishma HeightsNA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Grishma Heights: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 4 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed142

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots142
Closed/Covered142

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,868 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8250.1
Proposed, not sanctioned8,250 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPranik Gardens, Pranik Arcade Shop No 8/9/10/11, Mahavir Nagar, Kandivali West, Mumbai - 400 067

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectD.P Associates
EngineerHiren Tanna
PartnerRole in project
RIGHT CHANNEL CONSTRUCTION PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010691Dec 2018 → Dec 2021

Reason as filed by the promoterWe would like to state that our proposed date of completion of our project Grishma Heights (comprising of ground + 2 Podiums + 18 habitable floors) initially was 30th October, 2020 which later vide Maharera order no.: 13/2020 dated 02nd April, 2020 extended for 3 months and vide order no.: 14/2020 dated 18th May, 2020 further extended for another 3 months resulting into the new proposed date of completion to be 30th April, 2021. Due to the sudden outbreak, rapid spread of novel coronavirus (Covid-19) and to stop the virus from spreading, the whole of country was under lockdown. During this loc

EXT51800001005Dec 2018 → Apr 2020

Reason as filed by the promoterDelay in permissions as per new DCR 2034 which had come into existence from this December. Request Extension upto 31st March 2019.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Oct 2023

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexture F Form 5 - Grishma Heights.pdf4 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GH - Full OC.pdf15 Oct 2023
Certificates of CA (Form 3)File: GH Form 3 Q3.pdf16 May 2023
Certificates of CA (Form 3)File: GH Form 3 Q4.pdf16 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf21 Feb 2023
Certificates of CA (Form 3)File: Grishma Heights Form 3 (Mar 2022).pdf8 Feb 2023
Certificates of CA (Form 3)File: Grishma Heights Form 3 (Jun 2022).pdf8 Feb 2023
Certificates of CA (Form 3)File: Grishma Heights Form 3 (Sept 2022).pdf8 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf29 Apr 2022
CERSAI detailsFile: GH - Credai (MCHI) Membership Certificate.pdf31 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf31 Dec 2021
Certificates of CA (Form 3)File: GH_Form_3.pdf18 Oct 2021
Declaration about Commencement CertificateFile: Declaration of Commence Certificate (Compressed).pdf11 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QA Certificate - Mar-20.pdf11 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA Certificate - Mar-21.pdf11 Sep 2021
Disclosure of sold/ booked inventoryFile: Declaration of Sold Inventory (Compressed).pdf11 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Aug 2021
Certificates of CA (Form 3)File: Form 3.pdf23 Aug 2021
Certificates of CA (Form 3)File: Form 3.pdf23 Aug 2021
Certificates of CA (Form 3)File: Form_3.pdf5 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2255780_OC_signed.pdf17 Apr 2021
OtherFile: Grishma_Heights-Part_OC.pdf19 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf21 Jan 2021
Certificates of CA (Form 3)File: Form_3.pdf28 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5.pdf19 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf19 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf20 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf20 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf20 Sep 2019
Certificates of CA (Form 3)File: Form 3.pdf20 Sep 2019
Certificates of CA (Form 3)File: Form 3.pdf20 Sep 2019
Details of encumbrancesFile: Emcumberance Certificate Grishma Heights.pdf2 Mar 2019
Declaration in FORM BFile: Affidavit Grishma Heights.pdf2 Mar 2019
Details of encumbrancesFile: Edelweiss Letter.pdf12 Sep 2018
Building plan approvalFile: 3rd IOD- Copy.pdf30 Jul 2017
Layout approvalFile: compresspdf_4C3WRgvN.pdf30 Jul 2017
PAN CardFile: Pan Card COLOR.pdf30 Jul 2017
Copy of the legal title reportFile: Title Certificate - MG Road- 26 July 2017.pdf30 Jul 2017
Details of encumbrancesFile: Grishma Heights Self Dec Encumb.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: compresspdf_4C3WRgvN.pdf30 Jul 2017
Building Plan Approval (IOD)File: 3rd IOD- Copy.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 4 Jan 2016-ilovepdf-compressed.pdf30 Jul 2017
Declaration in FORM BFile: Affidavit Cum Declaration - Grishma Heights - 29-07-2017.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate MG Road - Grishma Heights 20-07-2017.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Grishma heights (Engineers Certificate) Nexus.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA Certificate - Grishma (1)-ilovepdf-compressed.pdf30 Jul 2017
Proforma of Allotment letterFile: Final Allotment Letter.pdf30 Jul 2017
Proforma of Allotment letterFile: Sale Agreement Draft Grishma Heights.pdf30 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
AABIEL PARADISENEAR FALSA BUSINESS PARK OPP MAXUS MALL Bhayandar West THANE 40110136CompletedDec 2014Late, Mar 2015
TRISHUL HEIGHTBANDARPAKADI OFF LINK ROAD KANDIVALI WEST31CompletedMar 2012Late, Aug 2014
KAILASH RAMKRIPAKAILASH RAMKRIPA BUILDING PLOT NO 6 KAILASH RAMPUR ROAD MALAD EAST MUMBAI 40009733CompletedFeb 2011Late, Mar 2011

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Grishma Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kandivali west6,700+ in Mumbai Suburban

2 kmGrishma HeightsCompleted 124Lapsed / revoked 65Other 146Dot size: filed unitsN

Filed coordinates, straight-line distance. 335 registered projects within 2 km.

Builder: RIGHT CHANNEL CONSTRUCTION PVT LTD

RIGHT CHANNEL CONSTRUCTION PVT LTD has 6 registrations on MahaRERA, including DELTA HOUSE and AABIEL AVENUE. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Grishma Heights is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Grishma Heights?

The registered promoter entity is RIGHT CHANNEL CONSTRUCTION PVT LTD, a company as per the filing. Its CIN U45202MH2008PTC188854 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Grishma Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Grishma Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Grishma Heights?

The professionals named in the filing: Architect: D.P Associates; Engineer: Hiren Tanna. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Grishma Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Grishma Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Grishma Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.