Home / Browse projects / Nashik, Maharashtra / GREENLANDS
GREENLANDS
RG-MH-15023 · RERA P51600034059 · Last updated on MahaRERA portal: 20 Jan 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GREENLANDS is a Mixed project by SUDHIR SUNIL BODKE in Nashik, Maharashtra, registered with MahaRERA as P51600034059 on 17 Mar 2022. The registration is recorded completed; possession was promised by 31 Dec 2026. 0 of the 4 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameGREENLANDS
- TypeMixed
- Location
- STADIUM HIRAWADI ROAD
- PANCHVATI
- Nashik
- 422003
- Pincode422003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600034059
- ReraGenie IDRG-MH-15023
Builder
- NameSUDHIR SUNIL BODKE
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on17 Mar 2022
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed81 files
Current status
Figures as on 20 Jan 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GREENLANDS | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.
GREENLANDS70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
NA Plot Without StructureNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUDHIR SUNIL BODKE | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANJAY MHALAS |
| Engineer | NITIN TEKALE |
| Chartered Accountant | B S FADANVIS AND ASSICIATES |
| Chartered Accountant | Lathi and Tapadiya |
| Chartered Accountant | Narendra Navandar and Co |
| Partner | Role in project |
|---|---|
| SUDHIR SUNIL BODKE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Dec 2024
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2A.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUN 24.pdf | 20 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20241004044019.pdf | 23 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Archi Certi Form 1 Mar To june 24.pdf | 15 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rera Form A-2 Mar To june 24.pdf | 15 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DEC 23.pdf | 18 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F 2 MAR 24.pdf | 18 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Sudhir Bodke Dt-31-03-2024_0_0001.pdf | 18 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DEC 23.pdf | 25 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MAR 24.pdf | 25 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A SITE DEC 23.pdf | 25 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A MAR 24.pdf | 25 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Sudhir Bodke Dt-31-12-2023_0001.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From-2.pdf | 3 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annexure F of Sunil Bodke March 2022_0001.pdf | 9 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F of Sunil Bodke March 2023_0001.pdf | 9 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31 Mar 22.pdf | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 Jun 22.pdf | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 sep 22.pdf | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DEC 22.pdf | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC 31 mar 23.pdf | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 jun 23.pdf | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 Sep 23.pdf | 3 Nov 2023 |
| Building plan approval or NA orderFile: 5 Project Information.pdf | 7 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 5 Project Information.pdf | 7 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 4 Project Information.pdf | 7 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 02.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Greenlands March -22_0001.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Greenlands June -22_0001.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certficate Greenlands Sep- 22_0001.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Greenlands Dec-22_0001.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Greenlands March -23_0001.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Greenlands June- 23_0001.pdf | 7 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Greenlands Sep-23_0001.pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-03-22.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-06-22.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-09-22.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-12-22.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-03-23.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-06-23.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-09-23.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3-4-2022.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05-07-2022.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4-10-2022.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4-1-2023.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4-4-2023.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3-7-2023.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 04-04-2022.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3-7-2022.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 6-10-2022.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5-1-2023.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4-4-2023(3).pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3-7-2023(2).pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3-10-2023.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 04.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 07.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold-unsold 01.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold- Unsold-03.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold 05.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold -unsold 06.pdf | 5 Oct 2023 |
| CERSAI detailsFile: Undertaking Cersai.pdf | 12 Mar 2022 |
| Copy of the legal title reportFile: Title Report-compressed.pdf | 10 Mar 2022 |
| Details of encumbrancesFile: No Encumbere Certificate.pdf | 10 Mar 2022 |
| Declaration in FORM BFile: From B new-compressed.pdf | 10 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NEW_compressed.pdf | 10 Mar 2022 |
| Proforma of Allotment letterFile: AGREEMENT TO SALE FORMATE.pdf | 10 Mar 2022 |
| Proforma of Allotment letterFile: allotment letter.pdf | 10 Mar 2022 |
| Building plan approval or NA orderFile: BP 1-4.pdf | 19 Feb 2022 |
| Building plan approval or NA orderFile: BP 2-4.pdf | 19 Feb 2022 |
| Building plan approval or NA orderFile: BP 3-4.pdf | 19 Feb 2022 |
| Building plan approval or NA orderFile: BP 4-4.pdf | 19 Feb 2022 |
| Layout approvalFile: plot no 1 to 4 712-compressed.pdf | 19 Feb 2022 |
| PAN CardFile: sudhir bodke Pan.PDF | 19 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: plot no 1 to 4 712-compressed.pdf | 19 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BP 1-4.pdf | 19 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BP 2-4.pdf | 19 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BP 3-4.pdf | 19 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BP 4-4.pdf | 19 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate-compressed.pdf | 19 Feb 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
Keep GREENLANDS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PANCHVATI4,100+ in Nashik
Filed coordinates, straight-line distance. 105 registered projects within 2 km.
THE PLATINUM MALL BY PARKSYDE
JAIKUMAR CONSTRUCTIONS LTD
AVADH UTOPIA
DHATRAK CONSTRUWELL
ROONGTA ELEGANTE APARTMENT
ROONGTA LANDMARKS LLP
Siddhivinayak Trade Center
Dhatrak Constructions
G SQUARE
GIRI ASSOCIATE CONSTRUCTION
SADGURU HOMES
SHREE SADGURU HOMES
See every Nashik project, with the district possession charts
Builder: SUDHIR SUNIL BODKE
SUDHIR SUNIL BODKE has 1 registration on MahaRERA, including GREENLANDS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if GREENLANDS is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GREENLANDS?
The registered promoter entity is SUDHIR SUNIL BODKE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GREENLANDS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GREENLANDS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GREENLANDS?
The professionals named in the filing: Architect: SANJAY MHALAS; Engineer: NITIN TEKALE; Chartered Accountant: B S FADANVIS AND ASSICIATES; Chartered Accountant: Lathi and Tapadiya; Chartered Accountant: Narendra Navandar and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GREENLANDS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback