Home / Browse projects / Pune, Maharashtra / GREEN PARK
GREEN PARK
RG-MH-04750 · RERA P52100020295 · Last updated on MahaRERA portal: 28 Nov 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 4 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GREEN PARK is a Residential / Group Housing project by SANTOSH MHADEO ATOLE in Pune, Maharashtra, registered with MahaRERA as P52100020295 on 2 Apr 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 59 of the 120 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameGREEN PARK
- TypeResidential / Group Housing
- Location
- Dapodi- Pimpale Gurav Road
- Dapodi
- Pimpri Chinchwad
- Pimpale Gurav
- Haveli
- Pune
- 411012
- Pincode411012
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100020295
- ReraGenie IDRG-MH-04750
Builder
- NameSANTOSH MHADEO ATOLE
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Apr 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed46 files
Current status
Figures as on 28 Nov 2022, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GREEN PARK | NA | 8 | 8 | 120 | 0 | 120 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.
GREEN PARK: 79% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 28 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed120
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership6
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Santosh Mahadeo Atole | Pimpale Gurav | Pune |
| SANDEEP GAUDTE | Pimpale Gurav | Pune |
| SUBHASH RAOSHED GADUTE | Pimpale Gurav | Pune |
| Ujwala Shamrao Gudute | Pimpale Gurav | Pune |
| NILESH SHAMRAO GADUTE | Pimpale Gurav | Pune |
| ASHOK VISHNU GADUTE | Pimpale Gurav | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S K Associates |
| Engineer | santosh atole |
| Chartered Accountant | anupama shetty |
| Partner | Role in project |
|---|---|
| SANTOSH MHADEO ATOLE | - |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000340777 | Vishal Sundar Shettigar | Shree Ganesh Construction Through Proprietor Santosh Atole | 14/04/2024 |
| CC12502381 | Vishwajeet Bhide | SANTOSH MHADEO ATOLE | 14/07/2025 |
| CC12502450 | Sagar Navale | SANTOSH MHADEO ATOLE | 18/07/2025 |
| CC12602747 | DATTATRAY BAPU PATIL | SANTOSH MHADEO ATOLE | 11/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed46
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: FLOOR PLAN (1).pdf | 28 Nov 2022 |
| Layout approvalFile: FLOOR PLAN 2 (1).pdf | 28 Nov 2022 |
| Layout approvalFile: LAYOUT PLAN.pdf | 28 Nov 2022 |
| Layout approvalFile: LAYOUT PLAN 2.pdf | 28 Nov 2022 |
| Layout approvalFile: TERRACE FLOOR PLAN.pdf | 28 Nov 2022 |
| Layout approvalFile: CC.pdf | 28 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: FLOOR PLAN (1).pdf | 28 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: FLOOR PLAN 2 (1).pdf | 28 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 28 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 2.pdf | 28 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: TERRACE FLOOR PLAN.pdf | 28 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: CC.pdf | 28 Nov 2022 |
| Declaration about Commencement CertificateFile: CC.pdf | 28 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 28 Nov 2022 |
| Certificates of CA (Form 3)File: FORM 3 SSO.pdf | 28 Nov 2022 |
| Proforma of Agreement for saleFile: 2 Proforma of Allotment letter.pdf | 28 Nov 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DETAILS.pdf | 28 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: 1 Proforma of Allotment letter.pdf | 28 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: 2 Proforma of Allotment letter.pdf | 28 Nov 2022 |
| OtherFile: TAX PAID RECEIPTS.pdf | 17 Jun 2019 |
| OtherFile: TAX PAID RECEIPTS.pdf | 17 Jun 2019 |
| OtherFile: NA Green Park.pdf | 20 May 2019 |
| Details of encumbrancesFile: ATOLE Flat Allotment Document.pdf | 10 May 2019 |
| Details of encumbrancesFile: ATOLE Flat Allotment Document.pdf | 10 May 2019 |
| Details of encumbrancesFile: ATOLE Flat Allotment Document.pdf | 10 May 2019 |
| Details of encumbrancesFile: ATOLE Flat Allotment Document.pdf | 10 May 2019 |
| Details of encumbrancesFile: No encumburance Cert.pdf | 28 Mar 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM NO1 Architects Certificate.pdf | 28 Mar 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM NO2 ENGI Certificate.pdf | 28 Mar 2019 |
| Certificates of CA (Form 3)File: FORM NO3 CA Certificate.pdf | 28 Mar 2019 |
| Proforma of Allotment letterFile: Allotmant Letter.pdf | 28 Mar 2019 |
| Proforma of Allotment letterFile: Draft Aggreement.pdf | 28 Mar 2019 |
| Building plan approvalFile: Floor Plan.pdf | 27 Mar 2019 |
| Building plan approvalFile: order.pdf | 27 Mar 2019 |
| Building plan approvalFile: Parking Plan.pdf | 27 Mar 2019 |
| Building plan approvalFile: Terrace.pdf | 27 Mar 2019 |
| Layout approvalFile: Layout.pdf | 27 Mar 2019 |
| PAN CardFile: 1Pan Card.pdf | 27 Mar 2019 |
| Copy of the legal title reportFile: 2Search Title.pdf | 27 Mar 2019 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 27 Mar 2019 |
| Building Plan Approval (IOD)File: Floor Plan.pdf | 27 Mar 2019 |
| Building Plan Approval (IOD)File: order.pdf | 27 Mar 2019 |
| Building Plan Approval (IOD)File: Parking Plan.pdf | 27 Mar 2019 |
| Building Plan Approval (IOD)File: Terrace.pdf | 27 Mar 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: 12Comminsment Certificate.pdf | 27 Mar 2019 |
| Declaration in FORM BFile: SANTOSH ATOLE.pdf | 27 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 46 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GREEN PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dapodi, Pimpri Chinchwad13,700+ in Pune
Filed coordinates, straight-line distance. 50 registered projects within 2 km.
AVALON CITY - C5 and C6
Classic Promoters and Builders Private Lim
MAYUR SKYLIFE
BUNTY HOMES
Avalon City - C2
Classic Promoters and Builders Private Lim
HORIZON HARMONY
RAMGEET DEVELOPERS
KATE RAMDARA
KATE RAMDARA DEVELOPERS
SAI TOWER
OM SAI CONSTRUCTIONS
Builder: SANTOSH MHADEO ATOLE
SANTOSH MHADEO ATOLE has 1 registration on MahaRERA, including GREEN PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that GREEN PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GREEN PARK is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GREEN PARK?
The registered promoter entity is SANTOSH MHADEO ATOLE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GREEN PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GREEN PARK?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GREEN PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GREEN PARK?
The professionals named in the filing: Architect: S K Associates; Engineer: santosh atole; Chartered Accountant: anupama shetty. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GREEN PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback