AVALON CITY - C5 and C6
By Classic Promoters and Builders Private Limited
RG-MH-27625 · RERA P52100033855 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- 3 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AVALON CITY - C5 and C6 is a Residential / Group Housing project by Classic Promoters and Builders Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100033855 on 14 Mar 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 101 of the 105 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameAVALON CITY - C5 and C6
- TypeResidential / Group Housing
- Location
- MUMBAI PUNE NATIONAL HIGHWAY
- DAPODI
- Haveli
- Pune
- 411012
- Pincode411012
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100033855
- ReraGenie IDRG-MH-27625
Builder
- NameClassic Promoters and Builders Private Limited
- Entity typeCompany
- CINU70101MH1988PTC047131
- GSTIN27AABCC1200C1ZN
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorAshok Dhanraj Chordia
- Other registrations14 more →
- Completed4 of 15
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Mar 2022
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
- Buildings1 building record
- Documents filed169 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C5 and C6 | NA | 17 | 14 | 105 | 0 | 105 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 46%.
C5 and C6: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 44% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 46% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 16% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MRS. SHOBHADEVI NARSINHA SHINDE | Pune (M Corp.) | Pune |
| SHRI DEEPAK NARSINHA SHINDE | Pune (M Corp.) | Pune |
| SHRI AJIT GUNAJIRAO GHULE | Pune (M Corp.) | Pune |
| SHRI CHETAN NARSINHA SHINDE | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C5 and C6 | NA | Rs 28.78 cr | Rs 21.87 cr |
| - | NA | Rs 2.54 cr | Rs 1.58 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANA Consortium Pvt Ltd |
| Engineer | Swapnil Sonawane |
| Engineer | Khandoba Bulbule |
| Engineer | Ajaykumar Kusekar |
| Chartered Accountant | SPAK & Co |
| Chartered Accountant | RSVA & Co |
| Chartered Accountant | GMKS & Co. |
| Chartered Accountant | Bogati & Co. |
| Partner | Role in project |
|---|---|
| Classic Promoters and Builders Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per order of the Hon'ble Chairman (MahaRERA) Dated 19/01/2026 we request you kindly to grant us extension till 31/03/2027.
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 586/2013/2013 | DISTRICT COURT PUNE | Ongoing |
| 628/2013/2013 | DISTRICT COURT PUNE | Ongoing |
| 56/2019/2019 | DISTRICT COURT PUNE | Ongoing |
| STAMP NO. CRAST/27533/2019/2019 | Shri S R Agarwal Registrar(JUDL II) | Ongoing |
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000471347 | Avalon City C5 | Madhuri Rohan Bahirat | 24/07/2024 |
| CC12503129 | Classic Promoters and Builders Private Limited | Mr Swapnil Gautam Ovhal | 05/09/2025 |
| CC12602853 | Prashant Krushnaji Khamkar | Classic Promoters and Builders Private Limited | 15/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Jan 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jan 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed169
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Avalon C5 and C6 - Jun 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Avon City C5 And C6 -Jun 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Avalon City C5 and C6 - Jun 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Avalon City - C5 C6 - Mar 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Avalon City - C5 C6 - Mar 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Avalon City - C5 C6 - Mar 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Avalon City C5 C6 - Dec 2025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 - Avalon City C5 C6 - Dec 2025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Avalon City C5 C6- Dec 2025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Form 1- Avalon City -C5 C6- Sept 2025.pdf | 17 Dec 2025 |
| Withdrawal Update Form 2File: Form 2- Avalon City -C5 C6- Sept 2025.pdf | 17 Dec 2025 |
| Withdrawal Update Form 3File: Form 3- Avalon City -C5 C6- Sept 2025.pdf | 17 Dec 2025 |
| Withdrawal Update Form 1File: Form 1- Avalon City -C5 C6- Sept 2025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2- Avalon City -C5 C6- Sept 2025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3- Avalon City -C2- Sept 2025.pdf | 18 Oct 2025 |
| Form 5 (FY 2024-2025)File: Avalon City C5 C6-Form 5-FY 24-25.pdf | 5 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 - Avalon C5 C6 Jun 25.pdf | 24 Jul 2025 |
| Withdrawal Update Form 2File: Form 2- Avalon City C5 C6 - Jun 25.pdf | 24 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 - Avalon C5 C6 Jun 25_compressed.pdf | 24 Jul 2025 |
| Withdrawal Update Form 1File: Form 1 - Avalon City C5 C6 - Mar 25.pdf | 10 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 - Avalon City C5 C6 - Mar 25.pdf | 10 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 - Avalon C5 C6 - Mar 25.pdf | 10 Jul 2025 |
| Withdrawal Update Form 1File: Form 1 - Avalon City C5 C6 - Mar 25.pdf | 4 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 - Avalon City C5 C6 - Mar 25.pdf | 4 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 - Avalon C5 C6 - Mar 25.pdf | 4 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Avalon City C5 C6 - Mar 25.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Avalon C5 C6 - Mar 25.pdf | 25 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City C5 C6 - Mar 25.pdf | 25 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Disclosure - Avalon C5 C6 - Dec 24.pdf | 25 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Disclosure - Avalon C5 C6 - Mar 25.pdf | 25 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Avalon City C5 C6- Mar 25.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Avalon C5 C6 - Dec 24.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Avalon City C5 -C6-Sep 2024.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Avalon City - C5 C6 - Jun 2024.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - Mar 24 - Avalon City C5 C6.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Avalon City C5 C6- Dec 23.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3- Avalon City C5 C6 - Sept 23.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Avalon City C5 C6 March-2023.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Avalon C5 C6_Dec 22.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Avalon C5 C6 - Sep-22.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Avalon City C5 C6 Jun-2022.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Avalon C5 C6 - Mar 22.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Avalon C5 C6 Jun 23.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Jun 23.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon C5 C6 - Dec 24.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 -Avalon C5 C6- Sept-24 -.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Jun 24.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Mar 24.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Dec 23.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 3- Avalon City C5 C6- Dec 23.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Sept 23.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Mar 23.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2A Avalon City C5 - C6 March 2023.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Dec 22.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Sept 22.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Jun 22.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Avalon City Avalon C5 C6 - Mar 22.pdf | 6 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Avalon City Wing C5 C6 - Jun 22.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Avalon City -C5 C6 Sept 22.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Avalon C5 C6- Dec 22.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Avalon City C5 -C6 March-2023.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 - Mar 24 - Avalon City C5 C6.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Avalon City - C5 C6 - Jun 2024.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1- Avalon C5 C6 - Sept 24.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Avalon C5 C6 - Dec 24.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Avalon C5 C6 - Mar 22.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Avalon city C5 - C6 - Mar 22.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Avalon City C5 - C6 March 2023.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A - Mar 24 - Avalon City C5 C6.pdf | 1 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Avaln City - C5 - C6 - Form 5 FY 23-24.pdf | 24 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Discloure - Avalon C5 C6 - Sept 2024.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Disclosure Avalon C5 C6 Mar 2024.pdf | 8 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Building 1 and 2 - Avalon City C5 and C6.pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1- Avalon City C5 C6 - Sept 23.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Avalon C5 and C6 Dec 23 Sold Disclosure.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Avalon City C5 C6- Dec 23.pdf | 8 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A - Avalon C5 C6 - Dec 23.pdf | 8 Jan 2024 |
| Layout approvalFile: 01.pdf | 6 Jan 2024 |
| Building plan approvalFile: 02.pdf | 6 Jan 2024 |
| Building plan approvalFile: 03.pdf | 6 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Avalon C-3 | Pimpri Chinchwad Pune 411012 | 47 | Completed | Dec 2019 | Late, Feb 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 169 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AVALON CITY - C5 and C6 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DAPODI13,700+ in Pune
Filed coordinates, straight-line distance. 42 registered projects within 2 km.
GREEN PARK
SANTOSH MHADEO ATOLE
MAYUR SKYLIFE
BUNTY HOMES
Avalon City - C2
Classic Promoters and Builders Private Lim
HORIZON HARMONY
RAMGEET DEVELOPERS
KATE RAMDARA
KATE RAMDARA DEVELOPERS
SAI TOWER
OM SAI CONSTRUCTIONS
Builder: Classic Promoters and Builders Private Limited
Classic Promoters and Builders Private Limited has 15 registrations on MahaRERA, including AVALON CITY C-3 and MUDRA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if AVALON CITY - C5 and C6 is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AVALON CITY - C5 and C6?
The registered promoter entity is Classic Promoters and Builders Private Limited, a company as per the filing. Its CIN U70101MH1988PTC047131 and GSTIN 27AABCC1200C1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AVALON CITY - C5 and C6?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AVALON CITY - C5 and C6?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AVALON CITY - C5 and C6?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AVALON CITY - C5 and C6?
The professionals named in the filing: Architect: ANA Consortium Pvt Ltd; Engineer: Swapnil Sonawane; Engineer: Khandoba Bulbule; Engineer: Ajaykumar Kusekar; Chartered Accountant: SPAK & Co; Chartered Accountant: RSVA & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AVALON CITY - C5 and C6?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback