ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Green Meadows Phase 1

Registration lapsed Litigation declared Residential / Group Housing project

Green Meadows Phase 1

By NANDAN RAINBOW REALTIES LLP

RG-MH-84041 · RERA P52100054816 · Last updated on MahaRERA portal: 11 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 2 cases
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 30.00 crore secured on the land, in favour of ICICI Bank

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
63 of 77Construction stages doneacross 7 buildings; furthest along: Basement (if any), 0%
36 of 51Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

Green Meadows Phase 1 is a Residential / Group Housing project by NANDAN RAINBOW REALTIES LLP in Pune, Maharashtra, registered with MahaRERA as P52100054816 on 12 Feb 2024. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 12 months from the original filing. 15 of the 51 units on this registration are recorded sold or booked, and 63 of 77 construction stages are filed complete.

At a glance

Project

  • NameGreen Meadows Phase 1
  • TypeResidential / Group Housing
  • Location
    • Pachane
    • Mawal
    • Pune
    • 412115
  • Pincode412115
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054816
  • ReraGenie IDRG-MH-84041

Builder

  • NameNANDAN RAINBOW REALTIES LLP
  • Entity typePartnership
  • PartnersRAVI JAIN, ROHAN KOTKAR
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

4 months past promisethis monthRegisteredFeb 2024First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Feb 2024
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings7 building records
  • Documents filed104 files

Current status

29%15 of 51 units booked
93.8%Work done, per cost certificate

Figures as on 11 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Row House No 01 to 05NA22505
Row House No 06 to 10NA22505
Row House No 11 to 15NA22505
Row House No 43 to 51NA22909
Row House No 34 to 42NA22909
Row House NO 25 to 33NA22909
Row House No 16 to 24NA20909

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 11 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

63 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Basement (if any), at 0%.

Row House No 01 to 0582%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 06 to 1082%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 11 to 1582%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 43 to 5182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 34 to 4282%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House NO 25 to 3382%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 16 to 2482%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51
BuildingClosed/CoveredTotal
Row House No 01 to 0555
Row House No 06 to 1055
Row House No 11 to 1555
Row House No 43 to 5199
Row House No 34 to 4299
Row House NO 25 to 3399
Row House No 16 to 2499

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area7,409 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI Bank
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on29 Oct 2025

Approvals and building plan

Permissible FSI10372.03
Proposed, not sanctioned6,289 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1194/8, Ramchandra Sabhamandap, Ghole road, Shivajinagar, Pune - 411005
Estimated costRs 21.72 cr
Cost incurredRs 20.38 cr
Work done93.85%
BuildingWingEstimatedIncurred
Row House No 43 to 51NARs 3.60 crRs 3.38 cr
Row House No 34 to 42NARs 3.60 crRs 3.38 cr
Row House NO 25 to 33NARs 3.60 crRs 3.38 cr
Row House No 16 to 24NARs 3.60 crRs 3.38 cr
Row House No 01 to 05NARs 2.00 crRs 1.88 cr
Row House No 06 to 10NARs 2.00 crRs 1.88 cr
Row House No 11 to 15NARs 2.00 crRs 1.88 cr
-NARs 1.32 crRs 1.20 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCRYSTAL ARCH
EngineerSANTOSH RUNWAL
Chartered AccountantPRITESH R NAHAR & ASSOCIATES
Chartered AccountantSPCM and Associates
PartnerRole in project
NANDAN RAINBOW REALTIES LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028312Jun 2025 → Jun 2026

Reason as filed by the promoteri)Due to Heavy Rainfall Roads leading to the site are usually flooded or damaged, thus restricting material transportation and worker movement ii) Wet and muddy conditions increase the risk of accidents, halting operations iii) Prolonged rain washed away work already completed or lead to water-logging, requiring rework iv) Workers from remote areas do not show up regularly due to transport issues, personal commitments, or weather conditions v) Last year being election year majority of labour went to their hometowns for voting, and also when the labour goes to hometown for festivals they are no

Litigation declared2

CaseCourtStatus
273/2019Civil Judge Jr Division Vadgaon MavalPending for WS
116/2024Vadgaon MavalOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - RH.pdf11 Jun 2026
Withdrawal Update Form 2File: RH Form 2-.pdf11 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf11 Jun 2026
Form 2A (FY 2026-2027)File: Form 2A- GM-RH-6-4-26.pdf11 Jun 2026
Withdrawal Update Form 1File: Form 1 - RH.pdf17 Jan 2026
Withdrawal Update Form 2File: RH Form 2-.pdf17 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf17 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5_FINAL_GMP1 Dec25.pdf15 Jan 2026
Withdrawal Update Form 1File: Form 1 Architech Certificate -July-25.pdf30 Oct 2025
Withdrawal Update Form 1File: Form 1 Architech Certificate -Oct-25.pdf30 Oct 2025
Withdrawal Update Form 2File: Form - 2 Aug 2025_.pdf30 Oct 2025
Withdrawal Update Form 2File: Form - 2 Oct 2025_.pdf30 Oct 2025
Withdrawal Update Form 3File: Form - 3 Aug 25.pdf30 Oct 2025
Withdrawal Update Form 3File: Form - 3 Oct 2025.pdf30 Oct 2025
Form 2A (FY 2024-2025)File: Form -2A-2024.pdf30 Oct 2025
Form 2A (FY 2023-2024)File: Form -2A-2023.pdf30 Oct 2025
Form 2A (FY 2025-2026)File: Form - 2A Aug 2025.pdf30 Oct 2025
Withdrawal Update Form 1File: Form 1 Architech Certificate -July-25.pdf29 Oct 2025
Withdrawal Update Form 2File: Form - 2 Aug 2025_.pdf29 Oct 2025
Withdrawal Update Form 3File: CA CERTIFICATE.pdf29 Oct 2025
Declaration in FORM BFile: Form B.pdf21 Jun 2025
Declaration in FORM BFile: New Form B.pdf21 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New-Form 1.pdf21 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3.pdf21 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: new -Form -3.pdf21 Jun 2025
Disclosure of sold/ booked inventoryFile: new- Discolsure of sold -book inventory.pdf21 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: New-Form 5.pdf21 Jun 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf18 Jun 2025
Disclosure of sold/ booked inventoryFile: NEW SOLD UNSOLD.pdf18 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 pdf.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nanadan Rainbow Realties LLP -Form 3-Sept-24- RH.pdf5 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 .pdf5 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A.pdf5 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 -Dec-24.pdf17 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2.pdf17 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold-Booked Inventory.pdf17 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf17 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer Certificate.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer Certificate_compressed.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory.pdf25 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- Quality Assurance.pdf25 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SIGNED- Green Meadows Phase-1.pdf25 Nov 2024
Details of encumbrances concerned to FinanceFile: Exh- 1 and Order_compressed.pdf24 Oct 2024
Details of encumbrances concerned to LegalFile: Exh- 1 and Order_compressed.pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Crystal Arch Form 1 Architect's Certificate.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed (1).pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTARY.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf26 Jul 2024
Copy of the legal title reportFile: Title Opinion Compressed.pdf14 May 2024
Copy of the legal title reportFile: Supplementary Title Opinion Compressed.pdf14 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Green Meadows Ph 1 Form 1.pdf14 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Green Meadows Ph 1 - Form 2 08042024 Compressed.pdf14 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Green Meadows Ph 1 - Form 2A 08042024.pdf14 May 2024
Disclosure of sold/ booked inventoryFile: Green Meadows Ph 1 Sold Booked.pdf14 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Green Meadows Ph 1 - Form 3 18042024.pdf14 May 2024
Proforma of Agreement for saleFile: Revised Agreement for sale of Row House 25-04-2024.pdf14 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised NA order.pdf21 Feb 2024
CERSAI detailsFile: CERSAI_Search_Report_200297611713_For_Debtor_Based_Search_21_02_2024_12_56_15_029.pdf21 Feb 2024
Proforma of Agreement for saleFile: Agreement for sale of Row House.pdf21 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report Phase 1.pdf21 Feb 2024
Layout approvalFile: 02_06_page-0001 Edited Newest-2-1.pdf14 Feb 2024
Building plan approvalFile: 03_06_GREEN_page-0001 Edit.pdf14 Feb 2024
Copy of Layout Approval (in case of layout)File: 02_06_page-0001 Edited Newest-2-1.pdf14 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 03_06_GREEN_page-0001 Edit.pdf14 Feb 2024
Proforma of Agreement for saleFile: Agreement for sale of Row House Revised 14022024.pdf14 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report 14-02-2024.pdf14 Feb 2024
Other - TechnicalFile: Annexure A.pdf31 Jan 2024
Other - TechnicalFile: Declaration regarding plot area.pdf30 Jan 2024
Other - TechnicalFile: Declaration regarding permissible and proposed FSI.PDF30 Jan 2024
Layout approvalFile: Layout Plan.pdf26 Dec 2023
Building plan approvalFile: Plan.pdf26 Dec 2023
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf26 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf26 Dec 2023

How this compares with Pune

29%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Green Meadows Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pachane13,700+ in Pune

Builder: NANDAN RAINBOW REALTIES LLP

NANDAN RAINBOW REALTIES LLP has 3 registrations on MahaRERA, including Green Meadows Phase 2 and Green Meadows Phase 1. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Green Meadows Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Green Meadows Phase 1 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Green Meadows Phase 1?

The registered promoter entity is NANDAN RAINBOW REALTIES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Green Meadows Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Green Meadows Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Green Meadows Phase 1?

The professionals named in the filing: Architect: CRYSTAL ARCH; Engineer: SANTOSH RUNWAL; Chartered Accountant: PRITESH R NAHAR & ASSOCIATES; Chartered Accountant: SPCM and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Green Meadows Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Green Meadows Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Green Meadows Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.