Home / Browse projects / Pune, Maharashtra / Green Fantasy Phase-III

Registration lapsed No litigation declared Plotted project

Green Fantasy Phase-III

By Shree Mangalmurti Associates Phase-I

RG-MH-60596 · RERA P52100016595 · Last updated on MahaRERA portal: 29 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 37 months past the filed date
  • Completion date moved by 53 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2023Possession promised37 months past this date
1 of 37Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Green Fantasy Phase-III is a Plotted project by Shree Mangalmurti Associates Phase-I in Pune, Maharashtra, registered with MahaRERA as P52100016595 on 23 May 2018. Possession was promised by 30 Sep 2023 and is now 37 months past that date. The completion date has moved by 53 months from the original filing. 36 of the 37 units on this registration are recorded sold or booked.

At a glance

Project

  • NameGreen Fantasy Phase-III
  • TypePlotted
  • Location
    • Pune-Solapur Road
    • Uruli Kanchan
    • Haveli
    • Pune
    • 412202
  • Pincode412202
  • RERA no.P52100016595
  • ReraGenie IDRG-MH-60596

Builder

  • NameShree Mangalmurti Associates Phase-I
  • Entity typePartnership
  • GSTIN27ACQFS9759J1ZZ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersATIT SHRIKANT ADMULWAR, KIRAN VASANT PAWAR, ATUL SITARAM HARPALE, GAJANAN SAHEBRAO HARPALE, PRAVIN RAVINDRA KOKATE, RAHUL DATTATRAY KUNJIR, YOGESH NAMDEV CHOUDHARI, AVINASH ASHOK KUNJIR, ABA BALASAHEB CHAUDHARI, RAMCHANDRA KRISHNARAO RANDHAVE, DILIP SHIVAJI UNDRE, DEVIDAS DNYANOBA KADAM
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

37 months past promisethis monthRegisteredMay 2018First promiseApr 2019Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 May 2018
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 30 Apr 2019)
  • BuildingsNot stated in filing
  • Documents filed57 files

Current status

97%36 of 37 units booked

Figures as on 29 Jan 2024, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 29 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes80%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Land and ownership18

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,717 sq m
Land owned byThe promoter, with other names on the file
Named landowners18
LandownerVillageDistrict
Anita Ratikant YadavUruli KanchanPune
Balasaheb Gopalrao KanchanUruli KanchanPune
Dattatray Bhagwan DarekarUruli KanchanPune
Dhanaji Gopalrao KanchanUruli KanchanPune
Govind Rambhau TapkirUruli KanchanPune
Kailas Gopal KanchanSasvad (M Cl)Pune
Laxman Vitthal KanchanUruli KanchanPune
Pandurang Vitthal KanchanUruli KanchanPune
Ramdas Vitthal KanchanUruli KanchanPune
Vilas Gopalrao KanchanUruli KanchanPune
Vilas Karbhari KanchanUruli KanchanPune
Bapuso Mukunda KanchanUruli KanchanPune
Madhu KaleUruli KanchanPune
Narayan DarekarUruli KanchanPune
Sujata KhedekarUruli KanchanPune
Sanjay KhedekarUruli KanchanPune
Tulsabai KhedekarUruli KanchanPune
Balasaheb DarekarUruli KanchanPune

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLONI KALBHOR, PUNE

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtit Admulwar
PartnerRole in project
Shree Mangalmurti Associates Phase-I-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011113Apr 2019 → Sep 2023

Reason as filed by the promoter1. Purchase deeds of some plot holders in the project were not registered. 2. Customer Recovery Receivable Amount Pending. 3. Section 66 (1) of the Maharashtra Regional Planning and Town Planning Act, 1966, has been reserved for the planned HC-59 (Health Center) on our project under Uruli Kanchan Urban Health Center (Sheet No. 9) of the Pune Metropolitan Region Draft Development Plan. We have raised the objection on 18/08/2021.

EXT52100006177Apr 2019 → Apr 2021

Reason as filed by the promoterNot Sale Plots & No Work Completed For Covid 19 Lock down

EXT52100001899Apr 2019 → Apr 2020

Reason as filed by the promoterMinimum Booking & Work In Progress

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- I) 31-03-2023 NEW.pdf29 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- I) 30-06-2023 NEW.pdf29 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- I) 30-09-2023 NEW.pdf29 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (Disclosure of Interest in Other Real Estate Organizations).pdf25 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 CA PH -III -2022-23.pdf25 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA PH -III 31-03-2022.pdf17 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- III) 31-12-2021 NEW.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- III) 30-06-2022 NEW.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- III) 30-09-2022 NEW.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- III) 31-12-2022 NEW.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE (P- III) 31-03-2022 NEW.pdf14 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate (P- III) 31-03-2023 NEW.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE FOR SOLD BOOKED UNITS 13-10-2023 Phase III.pdf13 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2 Engineer Certificate RERA (P-III) 30-03-2023 NEW.pdf12 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SMA Form 5 PH - III 2018-19 (1).pdf18 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SMA Form 5 PH -III -2021-22.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SMS Form 5 PH - III - 2019 - 20.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SMA Form 5 PH -III -2020-21.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SMA Form 5 PH -III -2021-22.pdf10 Feb 2023
Proforma of Agreement for saleFile: 11111111.pdf10 Feb 2023
CERSAI detailsFile: हमीपत्र CERSAI फेज ३ Kb.pdf15 Feb 2022
Certificates of CA (Form 3)File: sma 3 31 3 21.pdf22 Sep 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate 01-09-2021 Phase III.pdf11 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate (P- III) 26-06-2021.pdf11 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE P- III 30-09-2021.pdf11 Sep 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE FOR SOLD BOOKED UNITS 01-09-2021 Phase III.pdf11 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A RERA- III 01-03-2020.pdf18 Mar 2020
Building plan approval or NA orderFile: 001-010.pdf16 May 2018
Building plan approval or NA orderFile: 002-010.pdf16 May 2018
Building plan approval or NA orderFile: 003-010.pdf16 May 2018
Building plan approval or NA orderFile: 004-010.pdf16 May 2018
Building plan approval or NA orderFile: 005-010.pdf16 May 2018
Building plan approval or NA orderFile: 007-010.pdf16 May 2018
Building plan approval or NA orderFile: 008-010.pdf16 May 2018
Building plan approval or NA orderFile: 009-010.pdf16 May 2018
Building plan approval or NA orderFile: 009-010.pdf16 May 2018
Layout approvalFile: 001-010.pdf16 May 2018
Copy of the legal title reportFile: 123.pdf16 May 2018
Copy of Layout Approval (in case of layout)File: 001-010.pdf16 May 2018
Building Plan Approval (IOD)File: 001-010.pdf16 May 2018
Building Plan Approval (IOD)File: 002-010.pdf16 May 2018
Building Plan Approval (IOD)File: 003-010.pdf16 May 2018
Building Plan Approval (IOD)File: 004-010.pdf16 May 2018
Building Plan Approval (IOD)File: 005-010.pdf16 May 2018
Building Plan Approval (IOD)File: 007-010.pdf16 May 2018
Building Plan Approval (IOD)File: 008-010.pdf16 May 2018
Building Plan Approval (IOD)File: 009-010.pdf16 May 2018
Building Plan Approval (IOD)File: 009-010.pdf16 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Manglamurti cc.pdf16 May 2018
Certificates of CA (Form 3)File: P- III.pdf16 May 2018
Proforma of Allotment letterFile: Flat Ag Shree Mangalmurti -RERA.pdf16 May 2018
PAN CardFile: Mangalmurti Pan card 1.pdf15 May 2018
Details of encumbrancesFile: encompress letter.pdf15 May 2018
Declaration in FORM BFile: form B Phase III.pdf15 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificat P-III Revised (2).pdf15 May 2018
OtherFile: NA Order.pdf15 May 2018

How this compares with Pune

97%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 53 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Green Fantasy Phase-III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Uruli Kanchan13,700+ in Pune

Builder: Shree Mangalmurti Associates Phase-I

Shree Mangalmurti Associates Phase-I has 2 registrations on MahaRERA, including Green Fantasy Phase-I and Green Fantasy Phase-III. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Green Fantasy Phase-III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Green Fantasy Phase-III is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Green Fantasy Phase-III?

The registered promoter entity is Shree Mangalmurti Associates Phase-I, a partnership as per the filing. Its GSTIN 27ACQFS9759J1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Green Fantasy Phase-III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Green Fantasy Phase-III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Green Fantasy Phase-III?

The professionals named in the filing: Architect: Atit Admulwar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Green Fantasy Phase-III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Green Fantasy Phase-III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Green Fantasy Phase-III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.