Home / Browse projects / Kolhapur, Maharashtra / Green Emerald
Green Emerald
RG-MH-80911 · RERA P53000048296 · Last updated on MahaRERA portal: 23 Jan 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Green Emerald is a Residential / Group Housing project by Shri Munisuvrat Infra in Kolhapur, Maharashtra, registered with MahaRERA as P53000048296 on 22 Dec 2022. The registration is recorded completed; possession was promised by 31 May 2026.
At a glance
Project
- NameGreen Emerald
- TypeResidential / Group Housing
- Location
- Mangalwar peth
- Kolhapur
- Kolhapur (M Corp.)
- Karvir
- 416012
- Pincode416012
- RERA no.P53000048296
- ReraGenie IDRG-MH-80911
Builder
- NameShri Munisuvrat Infra
- Entity typePartnership
- PartnersVanechand Gemraj Oswal, Arvind Hanjarimal Oswal, Sujit Kantilal Oswal, Anita Rajendra Oswal
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Dec 2022
- Promised completion31 May 2026
- Revised completionNone
- Buildings1 building record
- Documents filed71 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Green Emerald | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Green Emerald: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sadhna M Athane |
| Engineer | Madan S Atahne |
| Chartered Accountant | Chetan V Oswal |
| Chartered Accountant | Nilesh N Baheti |
| Partner | Role in project |
|---|---|
| Shri Munisuvrat Infra | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Aug 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Aug 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Jan 2025
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Arch Cert-Completion of Project.pdf | 23 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shri Munisuvrat Infra-Completion Cert.pdf | 23 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Audit Report 23-24-Final-Signed Copy.pdf | 15 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Green Emerald.pdf | 3 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Green Emerald.pdf | 2 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2-A-Site Supervisor Engineer.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Sept 24.pdf | 1 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert-Green Emerald Q-2-24-25.pdf | 1 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Sept 24.pdf | 1 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-June 24.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 24-25 Q1.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-June 24.pdf | 30 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory -.pdf | 23 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Green Emerald sep.pdf | 23 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-March24.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-Dec23.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-Sept23.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-June23.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-March23.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-Dec22.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 CA Certificate March 24 Final signed copy.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certificate Dec 23 Final signed copy.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 CA Certificate Sept 23 Final signed copy.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate March 23 Final signed copy.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate Dec 22 Final signed copy.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate June 23 Final signed copy.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1-Engineer Certificate-Dec 22.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2-Engineer Certificate-March 23.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3-Engineer Certificate-June 23.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4-Engineer Certificate-Sept 23.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5-Engineer Certificate-Dec 23.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6-Engineer Certificate-March 24.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-Dec22.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-March24.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-Dec23.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-Sept23.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-June23.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-March23.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Dec 22.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure June23.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sept23.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Dec23.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure March24.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 2 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf | 2 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13_Eng Cert.pdf | 23 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 15_Quality Assurance Cert.pdf | 23 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 23 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: 16_Unsold flats statement.pdf | 20 Aug 2022 |
| Proforma of Agreement for saleFile: 23 Green Emerald Allotment letter.pdf | 20 Aug 2022 |
| Proforma of Allotment letterFile: 23 Green Emerald Allotment letter.pdf | 20 Aug 2022 |
| Proforma of Allotment letterFile: A2S.pdf | 20 Aug 2022 |
| Proforma of Agreement for saleFile: A2S.pdf | 20 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: 33-35-Deviation Report.pdf | 20 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report of A2S.pdf | 20 Aug 2022 |
| Building plan approvalFile: 6-2 Plan.pdf | 6 Aug 2022 |
| Building plan approvalFile: 6-3 Plan.pdf | 6 Aug 2022 |
| Building plan approvalFile: 6-1 Plan.pdf | 6 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6-1 Plan.pdf | 6 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6-2 Plan.pdf | 6 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6-3 Plan.pdf | 6 Aug 2022 |
| Layout approvalFile: 5_Bhumi Akhilekh Map.pdf | 5 Aug 2022 |
| PAN CardFile: 1_PAN Card.pdf | 5 Aug 2022 |
| Copy of the legal title reportFile: 2_Search report.pdf | 5 Aug 2022 |
| Details of encumbrances concerned to FinanceFile: No encumbrances of Finance.pdf | 5 Aug 2022 |
| Details of encumbrances concerned to LegalFile: No encumbrances of Legal.pdf | 5 Aug 2022 |
| Copy of Layout Approval (in case of layout)File: 5_Bhumi Akhilekh Map.pdf | 5 Aug 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 7_Commencement certificate.pdf | 5 Aug 2022 |
| Declaration about Commencement CertificateFile: 8_Declaration of commencement certificate.pdf | 5 Aug 2022 |
| Declaration in FORM BFile: Form B_compressed.pdf | 5 Aug 2022 |
| CERSAI detailsFile: No security interest.pdf | 5 Aug 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 71 filed documents as one ZIP, foldered, with a manifest
Keep Green Emerald on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kolhapur880+ in Kolhapur
GRUHALAXMI RACHANA
BATU BUILDERS
SRI SRI RESIDENCY
SRI SRI BUILDERS AND DEVELOPERS PROPRIETOR
ONE EARTH
DESHPANDE INFRA
DRONAGIRI
ASHTIN INDIA PVT LTD
JEWEL SQUARE
RATNARAJ BUILDERS AND DEVELOPERS
SAPPHIRE SKY
S.S.Builders and Developers
See every Kolhapur project, with the district possession charts
Builder: Shri Munisuvrat Infra
Shri Munisuvrat Infra has 1 registration on MahaRERA, including Green Emerald. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if Green Emerald is delayed beyond 31 May 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Green Emerald?
The registered promoter entity is Shri Munisuvrat Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Green Emerald?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Green Emerald?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Green Emerald?
The professionals named in the filing: Architect: Sadhna M Athane; Engineer: Madan S Atahne; Chartered Accountant: Chetan V Oswal; Chartered Accountant: Nilesh N Baheti. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Green Emerald?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback