Home / Browse projects / Pune, Maharashtra / Grande View7 Phase VI Buiding I

Completed No litigation declared Residential / Group Housing project

Grande View7 Phase VI Buiding I

By Chirag Developers

RG-MH-13098 · RERA P52100022032 · Last updated on MahaRERA portal: 11 Dec 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 1 extension taken
  • Rs 10.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 50%
10 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

Grande View7 Phase VI Buiding I is a Residential / Group Housing project by Chirag Developers in Pune, Maharashtra, registered with MahaRERA as P52100022032 on 25 Aug 2019. The registration is recorded completed; possession was promised by 30 Jun 2026. The completion date has moved by 30 months from the original filing. 46 of the 56 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameGrande View7 Phase VI Buiding I
  • TypeResidential / Group Housing
  • Location
    • Ambegaon BK
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • RERA no.P52100022032
  • ReraGenie IDRG-MH-13098

Builder

  • NameChirag Developers
  • Entity typeOthers
  • Named personsSANJAY SHRADHANAND TYAGI, RAJEEV SHRADHANAND TYAGI, NITIN BALRAJ TYAGI, VINODKUMAR JAICHANDLAL MITTAL, RAMESH PARASRAM BHATIA
  • Other registrations7 more →
  • Completed6 of 8
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredAug 2019First promiseDec 2023Revised toJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Aug 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed83 files

Current status

82%46 of 56 units booked
95.7%Work done, per cost certificate

Figures as on 11 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
I BuildingNA151456056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 50%.

I Building: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes98%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes98%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed57

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots57
Closed/Covered40
Open Space17

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,156 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 10.00 crore
CERSAI search filedYes
Declared on22 Jul 2025

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI6618.0
Proposed, not sanctioned6,618 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 2/3, ATLANTA BUILDING, GROUND FLOOR, NARIMAN POINT, MUMBAI 400 021
Estimated costRs 22.42 cr
Cost incurredRs 21.47 cr
Work done95.73%
BuildingWingEstimatedIncurred
I BuildingNARs 17.12 crRs 16.37 cr
-NARs 5.30 crRs 5.10 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVoussoirs Architect & interior Designers
EngineerMAYURESH M GIDDE
Engineermahesh kulkarni
Chartered Accountantpradeep more
Chartered AccountantVinod N Nikam
PartnerRole in project
Chirag Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017276Dec 2023 → Jun 2026

Reason as filed by the promoterProposed Extended Date of Completion 30/06/2026

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Layout Plan- revised-April-2025 _.pdf11 Dec 2025
Building plan approvalFile: SHEET 02_.pdf11 Dec 2025
Building plan approvalFile: SHEET 03_.pdf11 Dec 2025
Building plan approvalFile: SHEET 03_.pdf11 Dec 2025
Building plan approvalFile: SHEET 04.pdf11 Dec 2025
Building plan approvalFile: SHEET 05.pdf11 Dec 2025
Building plan approvalFile: SHEET 06.pdf11 Dec 2025
Building plan approvalFile: SHEET 07_.pdf11 Dec 2025
Occupational CertificateFile: I Building - Full OC.pdf11 Dec 2025
Occupational CertificateFile: Explanatory Declaration.pdf11 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 - Chirag Developers.pdf13 Nov 2025
Withdrawal Update Form 1File: Gv7 Bldg I Form 1 Q2.pdf15 Oct 2025
Withdrawal Update Form 2File: Gv7 Bldg I Form 2 Q2.pdf15 Oct 2025
Withdrawal Update Form 3File: Gv7 I BLDG FORM 3 QTR 2- 25-26.pdf15 Oct 2025
Withdrawal Update Form 1File: Gv7 Bldg I Form 1.pdf23 Jul 2025
Withdrawal Update Form 2File: Gv7 Bldg I Form 2.pdf23 Jul 2025
Withdrawal Update Form 3File: Gv7 Bldg I Form 3.pdf23 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 Chirag I building_23-24.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC.pdf13 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf13 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG.pdf13 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf13 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A.pdf13 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: sold unsold.pdf13 Jan 2025
Details of encumbrancesFile: I Bldg.pdf16 Nov 2024
Details of encumbrancesFile: I Bldg.pdf16 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf13 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf13 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf13 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf13 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf13 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD I BUI.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R1 CA.pdf25 Apr 2024
Disclosure of sold/ booked inventoryFile: GRANDE VIEW 7 I BUILDING.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT FORM 1 I BLDG Q4 RERA 202324 31 03 2024.pdf8 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4 RERA ENGG CERT FORM 2 I BLDG 31 03 2024.pdf8 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q4 RERA QUALITY CERT FORM 2A I BLDG 31 03 2024.pdf8 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT FORM 3 I BLDG 31 03 2024 Q4 2023 2024.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD UNSOLD DATA BLDG I RERA Q3 2023-24.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 RERA 2023-24 FORM - 1 ARCH CERTIFICATE I BLDG.pdf11 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 RERA 2023-24 FORM - 2 ENGG CERTIFICATE I BLDG.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q3 RERA 2023-24 FORM - 2A QUALITY CERTIFICATE I BLDG.pdf11 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERT BLDG I RERA Q3 2023-24.pdf11 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 - 2023 ENGG CERTIFICATE - I BUILDING.pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 - 2023 ENGG CERTIFICATE - I BUILDING.pdf7 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q2 - 2023 QUALITY CERTIFICATE - I BUILDING.pdf7 Oct 2023
Disclosure of sold/ booked inventoryFile: Q2 - 2023 DISCLOSURE DATA - I BUILDING.pdf7 Oct 2023
Copy of the legal title reportFile: 8 Project Information.pdf7 May 2023
Copy of the legal title reportFile: 9 Project Information.pdf7 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 7 Project Information (1).pdf7 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE I BUILDING_11zon (1).pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE I BUILDING.pdf16 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE I BUILDING.pdf16 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY CERTIFICATE I BUILDING.pdf16 Apr 2023
Other - LegalFile: Declaration_Build_I_Plan Change.pdf27 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 300921.pdf10 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 -Phase v Building I- FY 20-21 (1).PDF1 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chirag Developers Building I Form3.PDF15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: I Form 5 FY 19-20-5.pdf15 Jan 2021
Details of encumbrancesFile: Details of encumbrances.pdf17 Aug 2019
Details of encumbrancesFile: Details of encumbrances.pdf17 Aug 2019
Layout approvalFile: Copy of Layout Approval (in case of layout) (1).pdf12 Aug 2019
Building plan approvalFile: Building Plan Approval.pdf12 Aug 2019
Building plan approvalFile: Building Plan Approval (IOD)1 (1).pdf12 Aug 2019
PAN CardFile: PAN Card.pdf12 Aug 2019
Copy of the legal title reportFile: Copy of the legal title report.pdf12 Aug 2019
Details of encumbrancesFile: Details of encumbrances.pdf12 Aug 2019
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval (in case of layout) (1).pdf12 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf12 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval (IOD)1 (1).pdf12 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf12 Aug 2019
Declaration in FORM BFile: FORM B.pdf12 Aug 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Grande View 7 Phase III S No 8 12S.no 8 .12 Grande View 7 Ambegaon bk pune189CompletedJun 2016Late, Nov 2016

How this compares with Pune

82%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Grande View7 Phase VI Buiding I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambegaon BK13,700+ in Pune

Builder: Chirag Developers

Chirag Developers has 8 registrations on MahaRERA, including Grande View 7 Capital and Grande View 7 Phase III Building K. Its filings disclose 8 earlier MahaRERA projects: declares 3 of 8 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Grande View7 Phase VI Buiding I is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Grande View7 Phase VI Buiding I?

The registered promoter entity is Chirag Developers, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Grande View7 Phase VI Buiding I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Grande View7 Phase VI Buiding I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Grande View7 Phase VI Buiding I?

The professionals named in the filing: Architect: Voussoirs Architect & interior Designers; Engineer: MAYURESH M GIDDE; Engineer: mahesh kulkarni; Chartered Accountant: pradeep more; Chartered Accountant: Vinod N Nikam. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Grande View7 Phase VI Buiding I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Grande View7 Phase VI Buiding I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Grande View7 Phase VI Buiding I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.