Home / Developers / Chirag Developers
Chirag Developers: RERA track record
Others ยท attribution by exact filing name, entity resolution in progress
Chirag Developers has 8 registrations in this build, including Grande View 7 Capital and Grande View 7 Phase III Building K. Its filings disclose 8 earlier MahaRERA projects: 3 of 8 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Grande View 7 Capital | Pune, Maharashtra | - | - | Completed |
| Grande View 7 Phase III Building K | Pune, Maharashtra | - | - | Completed |
| Grande View7 Capital 1 | Pune, Maharashtra | - | - | Registration lapsed |
| Grande View 7 Phase IV Building F&G | Pune, Maharashtra | - | - | Completed |
| Grande View 7 Phase V Building J | Pune, Maharashtra | - | - | Completed |
| Grande View7 Phase VI Buiding I | Pune, Maharashtra | 56 | 82% | Completed |
| GV7 CAPITAL 4 | Pune, Maharashtra | - | - | De-registered |
| Grandeview7 Phase-VII Bldg-L | Pune, Maharashtra | - | - | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| 8/12 A B Wing | 6 Jun 2016 | 11 Dec 2016 | +6 months |
| S No 8 12 A Wing B Wing | 30 Jun 2016 | 4 Nov 2016 | +4 months |
| S NO 8 12 A WING B WING | 30 Jun 2016 | 4 Nov 2016 | +4 months |
| 8/12 A B WING | 30 Jun 2016 | 4 Nov 2016 | +4 months |
| Grande View 7 Phase III S No 8 12 | 30 Jun 2016 | 4 Nov 2016 | +4 months |
| S no 12 A wing B wing | 11 Dec 2016 | 30 Jun 2016 | On time |
| Grande View 7 Capital and Capital I | 30 Apr 2021 | 30 Apr 2021 | On time |
| Grandeview7 Phase-III Bldg-K | 30 Jun 2021 | 7 Jun 2021 | On time |
Frequently asked questions
How do I verify Chirag Developers as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Chirag Developers?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.