Home / Browse projects / Pune, Maharashtra / GRAND ORCHID

Registration lapsed No litigation declared Others project

GRAND ORCHID

By SHREE SIDDHIVINAYAK CONSTRUCTION GROUP

RG-MH-08562 · RERA P52100011707 · Last updated on MahaRERA portal: 23 Sep 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 68 months past the filed date
  • Completion date moved by 17 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2021Possession promised68 months past this date
14 of 44Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 87%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

GRAND ORCHID is a Others project by SHREE SIDDHIVINAYAK CONSTRUCTION GROUP in Pune, Maharashtra, registered with MahaRERA as P52100011707 on 31 Aug 2017. Possession was promised by 28 Feb 2021 and is now 68 months past that date. The completion date has moved by 17 months from the original filing.

At a glance

Project

  • NameGRAND ORCHID
  • TypeOthers
  • Location
    • Sasvad (M Cl)
    • Purandhar
    • Pune
    • 412301
  • Pincode412301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011707
  • ReraGenie IDRG-MH-08562

Builder

  • NameSHREE SIDDHIVINAYAK CONSTRUCTION GROUP
  • Entity typePartnership
  • PartnersNILESH CHANDRAKANT HOLE, VIKAS BALU HOLE, CHANDRAKANT BALASAHEB HIWARKAR
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

68 months past promisethis monthRegisteredAug 2017First promiseSep 2019Revised toFeb 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion28 Feb 2021
  • Revised completionRevised to 28 Feb 2021 (originally 1 Sep 2019)
  • Buildings4 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA50000
B WINGNA50000
C WINGNA50000
D WINGNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 23 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 87%.

A WING36%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%
B WING31%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%
C WING44%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.4%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%
D WING53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.87%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%

Progress on shared amenities15

As on 23 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,874 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Chandrakant Baburao Jagtap & Others as per Aggri.Sasvad (M Cl)Pune

Approvals and building plan

Permissible FSI3735.75
Proposed, not sanctioned3,736 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAGARDEEP HOLE VASTI S NO 16, AT POST UNDRI NEAR BISHAP SCHOOL PUNE 411060

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGOPAL SUTHAR
EngineerSACHIN SADASIV KUDALE
PartnerRole in project
SHREE SIDDHIVINAYAK CONSTRUCTION GROUP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002387Sep 2019 → Aug 2020

Reason as filed by the promoterThe delay in project is on due to non-availability of contractors to execute the finishing work of the building. The external structure of the building is now ready. Labour was not available to complete the finishing tasks etc. Also, we are facing financial crunch as the project is 75% complete and 44 units are unsold. We are aggressively marketing the project and looking for buyers due to current scenario of slow market. We are confident that the financial crunch will be resolved as and when the bookings of all units are done. We request you to grant an extention of 1 year to complete the pro

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Oct 2021

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Declaration on Commencement Certificate.pdf23 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 resized.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2018_compressed.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2019 resized.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2020 resized.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2021 resized.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2021 resized.pdf23 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Fom 2A 2019.pdf23 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Fom 2A 2020.pdf23 Sep 2022
CERSAI detailsFile: CERSAI Report.pdf23 Sep 2022
Certificates of CA (Form 5)File: CA Form 3.pdf23 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: grand orchid form 5 18-19.pdf23 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Grand orchid form 5 19-20.pdf23 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Grand orchid form 5,20-21.pdf23 Sep 2022
Other - TechnicalFile: Fom 2A 2018.pdf23 Sep 2022
Other - TechnicalFile: Fom 2A 2021.pdf23 Sep 2022
Other - TechnicalFile: Fom 2A July 2021 resized (1).pdf23 Sep 2022
CERSAI detailsFile: Cersai Details.pdf25 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID A BUILDING COMPLETION.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID A TO D BUILDING COMPLETION-compressed.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VEDANT B BUILDING COMPLETION.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID A TO D BUILDING COMPLETION-compressed.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID B BUILDING COMPLETION_compressed.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID C BUILDING COMPLETION_compressed.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID C BUILDING COMPLETION_compressed.pdf18 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GRAND ORCHID C BUILDING COMPLETION_compressed.pdf18 Oct 2021
Certificates of CA (Form 5)File: combinepdf.pdf6 Feb 2019
Certificates of CA (Form 3)File: CA Certificate - Grand Orchid.pdf28 Jul 2017
Building plan approvalFile: BCD PLAN.pdf24 Jul 2017
Layout approvalFile: layout.pdf24 Jul 2017
Building plan approvalFile: A building.pdf24 Jul 2017
PAN CardFile: Pan Card.pdf24 Jul 2017
Copy of the legal title reportFile: 003.pdf24 Jul 2017
Copy of the legal title reportFile: B.pdf24 Jul 2017
Details of encumbrancesFile: Declaration.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: layout.pdf24 Jul 2017
Building Plan Approval (IOD)File: A building.pdf24 Jul 2017
Building Plan Approval (IOD)File: BCD PLAN.pdf24 Jul 2017
Declaration in FORM BFile: Form B.pdf24 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Grand Orchid.pdf24 Jul 2017
Proforma of Allotment letterFile: Agreement.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Grand Orchid - Commencement.pdf18 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf18 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 17 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GRAND ORCHID on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sasvad (M Cl)13,700+ in Pune

2 kmGRAND ORCHIDCompleted 12Lapsed / revoked 8Other 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: SHREE SIDDHIVINAYAK CONSTRUCTION GROUP

SHREE SIDDHIVINAYAK CONSTRUCTION GROUP has 3 registrations on MahaRERA, including GRAND ORCHID and Vedant. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that GRAND ORCHID shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GRAND ORCHID is delayed beyond 28 Feb 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GRAND ORCHID?

The registered promoter entity is SHREE SIDDHIVINAYAK CONSTRUCTION GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GRAND ORCHID?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GRAND ORCHID?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GRAND ORCHID?

The professionals named in the filing: Architect: GOPAL SUTHAR; Engineer: SACHIN SADASIV KUDALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GRAND ORCHID?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GRAND ORCHID. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GRAND ORCHID to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.