Home / Browse projects / Raigarh, Maharashtra / GOVIND GREENS
GOVIND GREENS
RG-MH-30085 · RERA P52000029833 · Last updated on MahaRERA portal: 21 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 30 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOVIND GREENS is a Residential / Group Housing project by PRIYAL BUILDCON LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000029833 on 8 Jul 2021. Possession is promised by 30 Nov 2026. The completion date has moved by 30 months from the original filing. 21 of the 54 units on this registration are recorded sold or booked, and 17 of 27 construction stages are filed complete.
At a glance
Project
- NameGOVIND GREENS
- TypeResidential / Group Housing
- Location
- swapnanagari
- morbe dam road
- VILLAGE KEWALE
- Kevale
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000029833
- ReraGenie IDRG-MH-30085
Builder
- NamePRIYAL BUILDCON LLP
- Entity typeOthers
- Named personsJAYESH BHUPENDRA GANDHI, JAYSHRI DINESH JETHVA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Jul 2021
- Promised completion30 Nov 2026
- Revised completionRevised to 30 Nov 2026 (originally 31 May 2024)
- Buildings3 building records
- Documents filed119 files
Current status
Figures as on 21 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GOVIND GREENS | Wing A | 5 | 4 | 16 | 0 | 16 |
| GOVIND GREENS | WING B | 5 | 4 | 16 | 0 | 16 |
| GOVIND GREENS | Wing C | 6 | 5 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
GOVIND GREENS · wing Wing A99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
GOVIND GREENS · wing WING B97%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
GOVIND GREENS · wing Wing C72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | 80% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed34
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| GOVIND GREENS Wing A | 11 | 11 |
| GOVIND GREENS WING B | 12 | 12 |
| GOVIND GREENS Wing C | 11 | 11 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| RAJENDRA JAWANMAL GANDHI | Panvel | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 20.00 lakh | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AN ARCH |
| Engineer | RAHUL SASHTE & ASSOCIATES |
| Engineer | Jayesh Gandhi |
| Chartered Accountant | POOJA PATWARI |
| Chartered Accountant | Dipika Patel |
| Chartered Accountant | Manish Kumar Gupta |
| Partner | Role in project |
|---|---|
| PRIYAL BUILDCON LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in receiving Plinth Completion Certificate from the planning authority
Reason as filed by the promoterProcuring Additional FSI for C Wing
Reason as filed by the promoter1. The project stands at 90% completion. 2. The consent of 52.38% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- a. Unfavourable Market Conditions b. Financial Constraints c. Shortage of Skilled Labour and Construction Materials d. Increased Construction Cost e. Unfavourable Weather Conditions 6. The revised date of completion is now 30/11/2026. 7. We hereby assure the Hon’ble Authority that the project shall be fully comp
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 May 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 May 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Nov 2026
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: Amended CC Approved Plan Sheet 1.pdf | 21 May 2026 |
| Building plan approvalFile: Amended CC Approved Plan Sheet 2.pdf | 21 May 2026 |
| Building plan approvalFile: Amended CC Approved Plan Sheet 3.pdf | 21 May 2026 |
| Building plan approvalFile: Amended CC Approved Plan Sheet 4.pdf | 21 May 2026 |
| Building plan approvalFile: Amended CC Approved Plan Sheet 5.pdf | 21 May 2026 |
| Withdrawal Update Form 1File: From No 1 Govind Greens 31 03 2026_compressed.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: From No 1 Govind Greens 31 03 2026_compressed.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: From No 2 Govind Greens 31 03 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: From No 2 Govind Greens 31 03 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: From No 3 Govind Greens 31 12 2025.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: Form No 3 Govind Greens 31 03 2026_260508_174553.pdf | 8 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A_05-05-2026.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: From No 1 Govind Greens 31 12 2025.pdf | 9 Feb 2026 |
| Withdrawal Update Form 2File: From No 2 Govind Greens 31 12 2025.pdf | 9 Feb 2026 |
| Withdrawal Update Form 3File: From No 3 Govind Greens 31 12 2025.pdf | 9 Feb 2026 |
| Withdrawal Update Form 1File: 1 Form No 1 Arichtect Certificate_compressed.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form No 1 30 09 2025 (Architect Certificate).pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: 2 Engineer Cerificaqte Form 2 30 06 2025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: 2 Engineer Cerificaqte Form 2 30 06 2025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: 3 Form No 3 C A Certificate 30 06 2025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: 3 Form No 3 C A Certificate 30 06 2025.pdf | 4 Feb 2026 |
| Form 2A (FY 2024-2025)File: Annexure A 2024 2025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form No 1 30 09 2025 (Architect Certificate).pdf | 23 Dec 2025 |
| Withdrawal Update Form 1File: Form No 1 30 09 2025 (Architect Certificate).pdf | 23 Dec 2025 |
| Withdrawal Update Form 2File: Form no 2 Engineers certificate.pdf | 23 Dec 2025 |
| Withdrawal Update Form 2File: Form no 2 Engineers certificate.pdf | 23 Dec 2025 |
| Withdrawal Update Form 3File: From No 3 G G 30 09 2025.pdf | 23 Dec 2025 |
| Withdrawal Update Form 3File: From No 3 G G 30 09 2025.pdf | 23 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form No 5 Govind Greens AY 2025 26.pdf | 23 Dec 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 2 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 20102024.pdf | 20 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 C A Certifcate 31 12 2024.pdf | 20 Jun 2025 |
| Declaration in FORM BFile: Affidavit.pdf | 16 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate form 1.pdf | 8 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No 2 (Engineer's Certiifcate).pdf | 8 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure sold inventory.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Annexure -C (form 2A).pdf | 8 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 31122024 compressed.pdf | 29 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate From No 2 dt 31 12 2024.pdf | 29 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30062024.pdf | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Achitect Certificate 27 12 2023.pdf | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 19102024.pdf | 28 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form No 3 C A Certifcate 30 06 2024.pdf | 28 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 From 3 C A certificate 31 12 2023.pdf | 28 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Engineer Certificate 30092024.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form no 2 30 06 2024.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30092024.pdf | 28 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf | 16 Dec 2024 |
| Declaration in FORM BFile: Form B Jayesh Gandhi 24052025.pdf | 20 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance Govind Greens.pdf | 18 Jun 2024 |
| Proforma of Agreement for saleFile: Model Sale Agreement RERA Govind Greens.pdf | 18 Jun 2024 |
| Proforma of Allotment letterFile: Model form of allotment letter Govind Greens.pdf | 18 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: Govind Greens Allotment letter deviation.pdf | 18 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: Govind Greens AFS deviation.pdf | 18 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbance Legal.pdf | 5 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Encumbance Legal.pdf | 5 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Book Inventory.pdf | 5 Jun 2024 |
| CERSAI detailsFile: Cersai declaration.pdf | 5 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Form a Jayshri Jethwa.pdf | 5 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 5 Jun 2024 |
| Proforma of Agreement for saleFile: Agreement for Sale draft.pdf | 5 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 5 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM No 2 Engineer Certificate 31 03 2024.pdf | 24 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Quality certificate from Eng.pdf | 24 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM No 3 C A Certificate 23 05 2024.pdf | 24 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE 30-09-2023.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Achitect Certificate 27 12 2023.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE 31-03-2024.pdf | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-1 ARCHITECT CERTIFICATE 30-09-2023.pdf | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No 2 Engineer certificate 31 03 2024.pdf | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 ENGINEER CERTIFCATE DEC 2023.pdf | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 CA Certificate - 31-12-2023.pdf | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form No 3 C A Certifcate 31 03 2024.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1Architect certificage 30 06 23.pdf | 27 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Enginerring Certificate 30 06 2023.pdf | 27 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 C A Certificate from no 3 signed.pdf | 27 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 5 CA Certificate Form 5 F Y 2022 2023.pdf | 27 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 5 CA Certificate Form 5 F Y 2022 2023.pdf | 27 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificage FORM 3 31 03 2023.pdf | 27 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GOVIND GREENS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VILLAGE KEWALE5,900+ in Raigarh
Filed coordinates, straight-line distance. 31 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: PRIYAL BUILDCON LLP
PRIYAL BUILDCON LLP has 1 registration on MahaRERA, including GOVIND GREENS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if GOVIND GREENS is delayed beyond 30 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOVIND GREENS?
The registered promoter entity is PRIYAL BUILDCON LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOVIND GREENS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GOVIND GREENS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOVIND GREENS?
The professionals named in the filing: Architect: AN ARCH; Engineer: RAHUL SASHTE & ASSOCIATES; Engineer: Jayesh Gandhi; Chartered Accountant: POOJA PATWARI; Chartered Accountant: Dipika Patel; Chartered Accountant: Manish Kumar Gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOVIND GREENS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback