Home / Browse projects / Mumbai Suburban, Maharashtra / GORAI KINARA CHS LTD

Registered Litigation declared Residential / Group Housing project

GORAI KINARA CHS LTD

By JINAM BB REALTORS

RG-MH-02787 · RERA P51800020736 · Last updated on MahaRERA portal: 23 Feb 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 2 complaints at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 60%
26 of 64Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 222 documents Report an error

GORAI KINARA CHS LTD is a Residential / Group Housing project by JINAM BB REALTORS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020736 on 8 May 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 38 of the 64 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGORAI KINARA CHS LTD
  • TypeResidential / Group Housing
  • Location
    • GORAI
    • GORAI II
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • RERA no.P51800020736
  • ReraGenie IDRG-MH-02787

Builder

  • NameJINAM BB REALTORS
  • Entity typePartnership
  • PartnersVISHWASHREE DEVELOPERS PVT LTD, SHEELA NAVALKISHORE SHARMA, UTPAL SUBHASH SHETH, DHRUV UTPAL SHETH

Key dates

this monthRegisteredMay 2019First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 May 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 25 Dec 2022)
  • Buildings1 building record
  • Documents filed222 files

Current status

59%38 of 64 units booked
41.6%Work done, per cost certificate

Figures as on 23 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GORAI KINARA CHS LTDNA222056864

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 60%.

GORAI KINARA CHS LTD: 43% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 23 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area625 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Jul 2025

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI3767.7
Proposed, not sanctioned2,440 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch104, MANAS RESIDENCY, SUBHASH ROAD, NEAR MAYUR CINEMA, KANDIVALI WEST, MUMBAI 67
Estimated costRs 13.54 cr
Cost incurredRs 5.63 cr
Work done41.56%
BuildingWingEstimatedIncurred
GORAI KINARA CHS LTDNARs 12.98 crRs 5.57 cr
-NARs 56.41 lakhRs 6.00 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA R MEHTA
EngineerNARENDRA DESAI DESAI
EngineerBHANUPRASAD RAVAL
Chartered AccountantMAHESH SABOO
Chartered AccountantH V JAIN & ASSOCIATES
Chartered AccountantMITESH NAWAL
Chartered AccountantS M BHAT
PartnerRole in project
JINAM BB REALTORS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018762Dec 2022 → Dec 2025

Reason as filed by the promoterDue to unfortunate death of our one of the Partner. We had issues of permissions & finance issue due to that our project got delay and now we are interested to complete the project with the specific period kindly grant the extension

EXT51800013219Dec 2022 → Dec 2023

Reason as filed by the promoterThe reason extension is being sought out is because of impact of Covid on the project sales and receivables. We target to complete project in near future.

EA21012619531Dec 2022 → Dec 2026

Reason as filed by the promoterDear Sir/Ma’am, We, Jinam BB Realtors, hereby declare the following with respect to the project “GORAI KINARA CHS LTD” bearing registration number P51800020736 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 60% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Oc

Litigation declared1

CaseCourtStatus
CC006000000428871/2024MAHARERAOngoing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000428871MANOHAR YASHWANT PANVALKARJINAM B B REALTORS16/02/2024
CC12600755Shashikant Rajaram ShindeJINAM BB REALTORS09/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed222

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 222 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 December 2025.pdf23 Feb 2026
Withdrawal Update Form 2File: Form 2 December 2025.pdf23 Feb 2026
Withdrawal Update Form 3File: Form 3 December 2025.pdf23 Feb 2026
Withdrawal Update Form 1File: Form 1 September 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 December 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 September 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 December 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 September 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 December 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf12 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf12 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf12 Dec 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025
Form 1File: Form 1.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf22 Jul 2025

How this compares with Mumbai Suburban

59%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GORAI KINARA CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GORAI II6,700+ in Mumbai Suburban

Builder: JINAM BB REALTORS

JINAM BB REALTORS has 1 registration on MahaRERA, including GORAI KINARA CHS LTD. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if GORAI KINARA CHS LTD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GORAI KINARA CHS LTD?

The registered promoter entity is JINAM BB REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GORAI KINARA CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GORAI KINARA CHS LTD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GORAI KINARA CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GORAI KINARA CHS LTD?

The professionals named in the filing: Architect: A R MEHTA; Engineer: NARENDRA DESAI DESAI; Engineer: BHANUPRASAD RAVAL; Chartered Accountant: MAHESH SABOO; Chartered Accountant: H V JAIN & ASSOCIATES; Chartered Accountant: MITESH NAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GORAI KINARA CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GORAI KINARA CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GORAI KINARA CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.