Home / Browse projects / Thane, Maharashtra / GOODWILL UNITY
GOODWILL UNITY
RG-MH-70597 · RERA P51700018463 · Last updated on MahaRERA portal: 22 Nov 2022
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOODWILL UNITY is a Residential / Group Housing project by GOODWILL CONSTRUCTIONS in Thane, Maharashtra, registered with MahaRERA as P51700018463 on 2 Nov 2018. The registration is recorded completed; possession was promised by 30 Jun 2022. 1 complaint is on record with the regulator.
At a glance
Project
- NameGOODWILL UNITY
- TypeResidential / Group Housing
- Location
- SECTOR 08
- SANPADA
- Navi Mumbai (M Corp.)
- Thane
- 400705
- Pincode400705
- RERA no.P51700018463
- ReraGenie IDRG-MH-70597
Builder
- NameGOODWILL CONSTRUCTIONS
- Entity typePartnership
- PartnersHAKIM ASGARALI LAKDAWALA, SHABBIR ASGARALI LAKDAWALA
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on2 Nov 2018
- Promised completion30 Jun 2022
- Revised completionNone
- Buildings2 building records
- Documents filed73 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1 EWS | NA | 5 | 0 | 0 | 0 | 0 |
| BUILDING NO 2 | NA | 25 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING NO 1 EWS73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 45% |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 30% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed212
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HOMEWORK ARCHITECT |
| Engineer | ASSOCIATED CONSULTANTS |
| Partner | Role in project |
|---|---|
| GOODWILL CONSTRUCTIONS | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602127 | Abhimanyu Behera | GOODWILL CONSTRUCTIONS | 11/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Oct 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Oct 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Mar 2022
Documents filed73
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30-9-2022 ABODE FORM 1_compressed.pdf | 22 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Signed Certificate_Form 5_31_03_2021.pdf | 1 Jun 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: EWS OC 01122021.pdf | 15 Mar 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Goodwill Unity OC.pdf | 15 Mar 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM-4 for unity-ews r1.pdf | 15 Mar 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM-4 for unity sale r1.pdf | 15 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Goodwill F2 UNITY 30092021.pdf | 15 Dec 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 Architect Certificate 30092021.pdf | 9 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GC_Form5.pdf | 27 Sep 2021 |
| Layout approvalFile: 7.pdf | 1 Sep 2021 |
| Layout approvalFile: 2.pdf | 1 Sep 2021 |
| Layout approvalFile: 3.pdf | 1 Sep 2021 |
| Layout approvalFile: 4.pdf | 1 Sep 2021 |
| Layout approvalFile: 5.pdf | 1 Sep 2021 |
| Layout approvalFile: 6.pdf | 1 Sep 2021 |
| Layout approvalFile: 8.pdf | 1 Sep 2021 |
| Layout approvalFile: 9.pdf | 1 Sep 2021 |
| Layout approvalFile: 11.pdf | 1 Sep 2021 |
| Layout approvalFile: 12.pdf | 1 Sep 2021 |
| Layout approvalFile: 10.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 2.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 3.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 4.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 5.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 6.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 7.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 8.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 9.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 10.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 11.pdf | 1 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 12.pdf | 1 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate as per rera for UNITY project dtd 30062021.pdf | 16 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Goodwill Unity-FORM 2-Associated Consultants -30062021.pdf | 16 Aug 2021 |
| Certificates of CA (Form 3)File: Goodwill Unity-Form 3-CA Certificate-30062021.pdf | 16 Aug 2021 |
| Proforma of Allotment letterFile: Agreement For Sale 29072021 ABODE.pdf | 29 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory-compressed.pdf | 2 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UNITY 31-12-2020-compressed.pdf | 30 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UNITY 31-03-2021-compressed.pdf | 30 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Goodwill Unity-Form 2 - Engineer's Certificate-31032021 (1)-compressed.pdf | 30 Jun 2021 |
| Certificates of CA (Form 3)File: Goodwill Unity-Form 3-CA Certificate-31032021 (2)-compressed.pdf | 30 Jun 2021 |
| OtherFile: Disclosure of Sold Unsold Inventory-compressed.pdf | 30 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Goodwill Unity 31122021.pdf | 12 Apr 2021 |
| Certificates of CA (Form 3)File: Form 3 Goodwill Unity CA certifciate 31122020 (2).pdf | 12 Apr 2021 |
| OtherFile: internal work completion.pdf | 8 Mar 2021 |
| OtherFile: 21st Slabcompletion.pdf | 8 Mar 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20210127180457971 CONST.pdf | 28 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 UNITY.pdf | 21 Dec 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Goodwill Unity Form 2.pdf | 21 Dec 2020 |
| Certificates of CA (Form 3)File: Goodwill Unity Form 3.pdf | 21 Dec 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 9 Nov 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 9 Nov 2020 |
| Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT LETTER AGRREMENT FOR SALE.pdf | 3 Nov 2020 |
| Details of encumbrancesFile: GC.pdf | 20 Jun 2020 |
| Proforma of Allotment letterFile: REVISED AGREEMENT FOR SALE.pdf | 20 Jun 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 RERA.pdf | 26 Oct 2019 |
| Proforma of Allotment letterFile: FINAL ALLOTMENT AND SALE AGREEMENT.pdf | 6 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 24 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 24 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 24 Apr 2019 |
| OtherFile: PLINTH COMPLETION CERTIFICATE.pdf | 13 Mar 2019 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT - GOODWILL CONSTRUCTIONS.pdf | 29 Oct 2018 |
| Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale - GOODWILL CONSTRUCTIONS.pdf | 29 Oct 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf | 24 Oct 2018 |
| Layout approvalFile: LAYOUT PLAN - GOODWILL CONSTRUCTIONS.PDF | 19 Oct 2018 |
| Details of encumbrancesFile: LETTER OF ENCUMBRANCES - GOODWILL CONSTRUCTIONS.pdf | 19 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN - GOODWILL CONSTRUCTIONS.PDF | 19 Oct 2018 |
| Declaration in FORM BFile: FORM B - GOODWILL CONSTRUCTIONS.pdf | 19 Oct 2018 |
| Building plan approvalFile: COMMENCEMENT CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf | 17 Oct 2018 |
| PAN CardFile: PAN CARD - GOODWILL CONSTRUCTIONS.pdf | 17 Oct 2018 |
| Building Plan Approval (IOD)File: COMMENCEMENT CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf | 17 Oct 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf | 17 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - GOOD WILL CONSTRUCTIONS.pdf | 17 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf | 17 Oct 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- All 73 filed documents as one ZIP, foldered, with a manifest
Keep GOODWILL UNITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SANPADA7,600+ in Thane
Raheja Prime-2
Raheja Universal (Pvt.) Ltd.
Raheja Lunaris-2
Raheja Universal (Pvt.) Ltd.
THE HIVE
BALAJI JINDAL SPACES LLP
Goowill Bizhub Nx
LAKDAWALA PROPERTIES LLP
Raheja Lunaris-1 - Callisto
Raheja Universal (Pvt.) Ltd.
Raheja Prime-1
Raheja Universal (Pvt.) Ltd.
See every Thane project, with the district possession charts
Builder: GOODWILL CONSTRUCTIONS
GOODWILL CONSTRUCTIONS has 1 registration on MahaRERA, including GOODWILL UNITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if GOODWILL UNITY is delayed beyond 30 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOODWILL UNITY?
The registered promoter entity is GOODWILL CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOODWILL UNITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GOODWILL UNITY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GOODWILL UNITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOODWILL UNITY?
The professionals named in the filing: Architect: HOMEWORK ARCHITECT; Engineer: ASSOCIATED CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOODWILL UNITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback