ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / GOODWILL METROPOLIS WEST PHASE 2

Completed No litigation declared Residential / Group Housing project

GOODWILL METROPOLIS WEST PHASE 2

By KRUTI CONSTRUCTIONS

RG-MH-14594 · RERA P52100023272 · Last updated on MahaRERA portal: 15 Jan 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Installation of Lifts, 90%
0Complaints at MahaRERAon this registration
Jump to the 30 documents Report an error

GOODWILL METROPOLIS WEST PHASE 2 is a Residential / Group Housing project by KRUTI CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100023272 on 9 Dec 2019. The registration is recorded completed; possession was promised by 30 Dec 2023.

At a glance

Project

  • NameGOODWILL METROPOLIS WEST PHASE 2
  • TypeResidential / Group Housing
  • Location
    • PORWAL ROAD
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • RERA no.P52100023272
  • ReraGenie IDRG-MH-14594

Builder

  • NameKRUTI CONSTRUCTIONS
  • Entity typePartnership
  • PartnersAtul Mansukh Nawale, Kumarpal Ratanchand Sanghvi, Nikhil Vinod Goyal, Asha Kamlesh Rupawat, Hemlata Ashok Agarwal, Rasila Rajendra Rupawat, Balkrishna Dnyanoba Khandve, Mansukh Murlidhar Nawale, Hemant Shantilal Jain, Chirayush Vinod Agarwal, Bharati Mahendra Rupawat, Mukesh Anantram Goyal and 3 more
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredDec 2019PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Dec 2019
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed30 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WINGNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

C WING: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 15 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes100%

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered1
Open Space34

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,752 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6020.57
Proposed, not sanctioned6,021 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch3 SIGNET HOUSE , ALANDI ROAD, YERWADA, 411006

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Imran Shaikh of Cubix Architects Associates
EngineerAJINKYA CHAVAN
Chartered AccountantCA SUMIT BANSAL
PartnerRole in project
KRUTI CONSTRUCTIONS-

Litigation declared1

CaseCourtStatus
1104/2017CivilPending and Purshis filed by Plaintiff in the said Court and no encumbrance certified by Adv Mahesh

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Nov 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Dec 2021

Documents filed30

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Goodwill Metropolis Phase 2 Society Formation.pdf15 Jan 2022
Architect’s Certificate on Completion of Project (Form 4)File: Kruti Construction Form 4 Architect Completion Cer.pdf14 Dec 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Kruti Construction -283.pdf6 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed F1 GMWP2 2021to22 Q2.pdf9 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F2A GMWP2 2021to22 Q2.pdf9 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kruti Construction.pdf15 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kruti Constructions Form 3.pdf15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 Kruti Constructions FY1920.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 Kruti Constructions FY2021.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F2A 30062020 P123 KCP2-compressed.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F2A 30092020 P123 KCP2-compressed.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F2A 31122020 P123 KCP2-compressed.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F2A 31032021 P123 KCP2-compressed.pdf27 Jul 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE NEW.pdf24 Jul 2021
Declaration about Commencement CertificateFile: Goodwill Metropolis West Phase 2 - Declaration About CC - 21072021.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GOODWILL METROPOLIS WEST Form 2A.pdf21 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5B3D37DA1-converted.pdf3 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Kruti Constructions QAC Report.pdf10 Jun 2020
Declaration in FORM BFile: Form B Declaration final.pdf22 Nov 2019
Layout approvalFile: DP Layout comp.pdf20 Nov 2019
Copy of the legal title reportFile: title 1.pdf20 Nov 2019
Copy of the legal title reportFile: Purshis.pdf20 Nov 2019
Copy of the legal title reportFile: title 2_compressed (1).pdf20 Nov 2019
Details of encumbrancesFile: Details of Encumbrances final.pdf20 Nov 2019
Copy of Layout Approval (in case of layout)File: DP Layout comp.pdf20 Nov 2019
Proforma of Allotment letterFile: C wing Draft Ag Final and Allotment letter.pdf20 Nov 2019
Building plan approvalFile: KC Plans RERA_C.pdf13 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: KC Plans RERA_C.pdf13 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: KC revised CC.pdf13 Nov 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 04112019.pdf5 Nov 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GOODWILL METROPOLIS WEST PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near LOHGAON13,700+ in Pune

Builder: KRUTI CONSTRUCTIONS

KRUTI CONSTRUCTIONS has 2 registrations on MahaRERA, including Goodwill Metropolis West Phase 1 and GOODWILL METROPOLIS WEST PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GOODWILL METROPOLIS WEST PHASE 2 is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GOODWILL METROPOLIS WEST PHASE 2?

The registered promoter entity is KRUTI CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GOODWILL METROPOLIS WEST PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GOODWILL METROPOLIS WEST PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GOODWILL METROPOLIS WEST PHASE 2?

The professionals named in the filing: Architect: Ar Imran Shaikh of Cubix Architects Associates; Engineer: AJINKYA CHAVAN; Chartered Accountant: CA SUMIT BANSAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOODWILL METROPOLIS WEST PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOODWILL METROPOLIS WEST PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOODWILL METROPOLIS WEST PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.