Home / Browse projects / Raigarh, Maharashtra / GOLDEN VIEW
GOLDEN VIEW
RG-MH-27820 · RERA P52000024295 · Last updated on MahaRERA portal: 17 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 49 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOLDEN VIEW is a Others project by SAMRUDDHI DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000024295 on 3 Feb 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 49 months from the original filing. 12 of the 46 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameGOLDEN VIEW
- TypeOthers
- Location
- PUSHPAK NODE
- PANVEL
- Vadghar (CT)
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000024295
- ReraGenie IDRG-MH-27820
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Feb 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 28 Nov 2022)
- Buildings1 building record
- Documents filed60 files
Current status
Figures as on 17 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GOLDEN VIEW | NA | 6 | 6 | 40 | 6 | 46 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.
GOLDEN VIEW: 40% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 28% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 17 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| ANIL DAGADU GHARAT | Panvel | Raigarh |
| ANUSAYA SHALIK GHARAT | Ulawe | Raigarh |
| DNYANESHWAR TUKARAM GHARAT | Ulawe | Raigarh |
| HASURAM TRIMBAK GHARAT | Ulawe | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GOLDEN VIEW | NA | Rs 4.00 cr | Rs 3.65 cr |
| - | NA | Rs 20.00 lakh | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CLASSICAL DESIGNER |
| Architect | VASTOSPATI DESIGN GROUP |
| Engineer | STRUCON CONSULTING ENGINEERS |
| Engineer | RAJENDRA B. GAVANDI CONSULTANT |
| Chartered Accountant | MANISH KUMAR |
| Chartered Accountant | RSL & CO |
| Chartered Accountant | MANISH K RAMAWATI AND COMPANY |
| Partner | Role in project |
|---|---|
| SAMRUDDHI DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to unforeseen circumstances, we are applying for extension.
Reason as filed by the promoterDUE TO AMENDMENT
Reason as filed by the promoterWe have recently received the new Commencement Certificate and the associated plan. As a result, we kindly request an extension of the current deadline. After the extension is granted, we will proceed with the necessary changes as required
Reason as filed by the promoterThe Project scope was revised, increasing the number of units and requiring a Revised Commencement Certificate, which is awaited. Construction was delayed due to approval-related procedural delays and labour shortage beyond the Promoter’s control.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12503690 | Tanveer Ahmed Noor Mohammed Kokate | Samruddhi Developers | 16/10/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed60
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 final dec 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 final dec 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 final dec 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 final dec 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 final dec 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 2File: form 2 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 2File: form 2 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 2File: form 2 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 2File: form 2 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 2File: form 2 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 FINAL 2025.pdf | 17 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 FINAL 2025.pdf | 17 Feb 2026 |
| Form 2A (FY 2024-2025)File: Scan_20260206_180715.pdf | 14 Feb 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 24 25 compressed.pdf | 5 Feb 2026 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 GV.pdf | 5 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE 22-23.pdf | 5 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE UPDATED FINAL.pdf | 5 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Golden View Form 3-SIGNED.pdf | 5 Jun 2024 |
| Proforma of Agreement for saleFile: Model AFS.pdf | 5 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- MARCH 23 GV.pdf | 4 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- APR 24 GV.pdf | 4 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- MARCH 23 GV.pdf | 4 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- APR 24 GV.pdf | 4 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Golden View 22-23 SIGNED.pdf | 4 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf | 4 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: no deviation form model allotment letter.pdf | 4 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: NO DEVIATION AFS.pdf | 4 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: no encumbrances certificate.pdf | 3 Jun 2024 |
| Details of encumbrances concerned to LegalFile: no encumbrances certificate.pdf | 3 Jun 2024 |
| Declaration in FORM BFile: Form B.pdf | 3 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE 22-23.pdf | 3 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY ASSURANCE 23-24.pdf | 3 Jun 2024 |
| CERSAI detailsFile: Cersai.pdf | 3 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations patio GOLDEN PARK.pdf | 3 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Golden view 2019-20- sign.pdf | 1 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: goldenview 2020-21 -sign.pdf | 1 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Golden View.pdf | 21 Jan 2023 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 19 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 19 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: rev RERA engg plot no 14 sec1 p1.pdf | 19 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality assurance certificate 19-20.pdf | 19 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality assurance certificate 20-21.pdf | 19 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurance certificate 21-22.pdf | 19 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 19 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf | 24 Jan 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT NEW.pdf | 22 Jan 2020 |
| Layout approvalFile: plan.pdf | 21 Jan 2020 |
| Building plan approvalFile: plan.pdf | 21 Jan 2020 |
| PAN CardFile: PARTNERSHIP PAN.pdf | 21 Jan 2020 |
| Copy of the legal title reportFile: PLOT NO 14 TITLE SEARCH REPORT NEW.pdf | 21 Jan 2020 |
| Details of encumbrancesFile: NO ENCUM CERT.pdf | 21 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: plan.pdf | 21 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: plan.pdf | 21 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: cc.pdf | 21 Jan 2020 |
| Declaration in FORM BFile: FORM B.pdf | 21 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC CERT NEW FINAL.pdf | 21 Jan 2020 |
| Proforma of Allotment letterFile: model Agreement.pdf | 21 Jan 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 20 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 60 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GOLDEN VIEW on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PANVEL5,900+ in Raigarh
Filed coordinates, straight-line distance. 322 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: SAMRUDDHI DEVELOPERS
SAMRUDDHI DEVELOPERS has 21 registrations on MahaRERA, including SAI SAMRUDDHI RESIDENCY and RIDDHESH HEIGHTS. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if GOLDEN VIEW is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOLDEN VIEW?
The registered promoter entity is SAMRUDDHI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOLDEN VIEW?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GOLDEN VIEW?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GOLDEN VIEW?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOLDEN VIEW?
The professionals named in the filing: Architect: CLASSICAL DESIGNER; Architect: VASTOSPATI DESIGN GROUP; Engineer: STRUCON CONSULTING ENGINEERS; Engineer: RAJENDRA B. GAVANDI CONSULTANT; Chartered Accountant: MANISH KUMAR; Chartered Accountant: RSL & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOLDEN VIEW?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback