Home / Browse projects / Palghar, Maharashtra / GOKULDHAM ZONE 01
GOKULDHAM ZONE 01
By RAJ SHREE NIRMAN BUILDERS PVT.LTD.
RG-MH-26935 · RERA P99000011596 · Last updated on MahaRERA portal: 15 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 96 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOKULDHAM ZONE 01 is a Residential / Group Housing project by RAJ SHREE NIRMAN BUILDERS PVT.LTD. in Palghar, Maharashtra, registered with MahaRERA as P99000011596 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 96 months from the original filing. 79 of the 92 units on this registration are recorded sold or booked, and 20 of 44 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameGOKULDHAM ZONE 01
- TypeResidential / Group Housing
- Location
- NA
- pam
- Palghar
- 401501
- Pincode401501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000011596
- ReraGenie IDRG-MH-26935
Builder
- NameRAJ SHREE NIRMAN BUILDERS PVT.LTD.
- Entity typeCompany
- ChairpersonPARESH CHOTALAL MER
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2018)
- Buildings4 building records
- Documents filed77 files
Current status
Figures as on 15 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 6 | 5 | 18 | 0 | 18 |
| WING B | NA | 6 | 5 | 18 | 0 | 18 |
| WING C | NA | 5 | 4 | 26 | 7 | 33 |
| WING D | NA | 6 | 5 | 16 | 7 | 23 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.
WING A75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING B75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING C66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING D66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 1 | 1 |
| WING B | 1 | 1 |
| WING D | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 2.18 cr | Rs 2.10 cr |
| WING B | NA | Rs 2.18 cr | Rs 2.10 cr |
| WING C | NA | Rs 1.63 cr | Rs 1.56 cr |
| WING D | NA | Rs 1.63 cr | Rs 1.56 cr |
| - | NA | Rs 12.05 lakh | Rs 10.24 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VASTU SHILP ASSOCIATES nishant patil |
| Engineer | DARSH CONSULTANT |
| Engineer | DILIP SHARMA LICENCED SUPERVISOR LICENCED PLUMBER ENGINEERS & CONTRACTORS |
| Chartered Accountant | SSRV AND Associates |
| Partner | Role in project |
|---|---|
| Raj Shree Nirman Builders Pvt Ltd | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDate 02nd April 2019 Dear sir, Greeting of the day! We are inform you that as per RERA our project complete as on 31st DEC 2018 but some following reason we are not complete the project on time 1. Insufficient or inadequate workforce 2. Suppliers create a problem regarding the pay payment earlier basic 3. Shortage of Raw Materials. So we are request to you please Extension our project date. Thanks & Regards, For Raj Shree Nirman Builders PVT. LTD .
Reason as filed by the promoterDear sir, Greeting of the day! We are inform you that as per RERA our project complete as on 31st DEC 2019 but some following reason we are not complete the project on time 1. Insufficient or inadequate workforce 2. Suppliers create a problem regarding the pay payment earlier basic 3. Shortage of Raw Materials. So we are request to you please Extension our project date. Thanks & Regards, For Raj Shree Nirman Builders PVT. LTD .
Reason as filed by the promoterDate 31/12/ 2022 Dear sir, Greeting of the day! We are inform you that as per RERA our project complete as on 30th DEC 2022 but some following reason we are not complete the project on time 1. Insufficient or inadequate workforce 2. Suppliers create a problem regarding the pay payment earlier basic 3. Shortage of Raw Materials. So we are request to you please Extension our project date. Thanks & Regards, For Raj Shree Nirman Builders PVT. LTD .
Reason as filed by the promoterImpact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materi
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000408086 | SANJAY CHANDU GORAWA | M/s Raj Shree Nirman Builders Pvt. Ltd. | 29/12/2023 |
| CC12600340 | Raghavendra Pratap singh | Raj Shree Nirman Builders Pvt Ltd | 18/01/2026 |
| CC12603228 | SANJAY CHANDU GORAWA | Raj Shree Nirman Builders Pvt Ltd | 29/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed77
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Q1 Architects Certficate A B C D wing_compressed.pdf | 15 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q1 Architects Certficate A B C D wing_compressed.pdf | 15 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q1 Architects Certficate A B C D wing_compressed.pdf | 15 Jul 2026 |
| Withdrawal Update Form 2File: A wing B wing C and D Q 4.pdf | 15 Jul 2026 |
| Withdrawal Update Form 2File: form 2A wing B wing C and D Q1.pdf | 15 Jul 2026 |
| Withdrawal Update Form 2File: form 2A wing B wing C and D Q1.pdf | 15 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate from Q4.pdf | 15 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate from Q4.pdf | 15 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate from Q4.pdf | 15 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Architects Certficate A B C D wing _compressed.pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: A wing B wing C and D Q 4.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate from Q4.pdf | 1 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1_DEC 25_GOULDHAM ZONE 1.pdf | 17 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2_DEC 25_ GOKULDHAM PHASE I A B C D WING.pdf | 17 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3_DEC 25_GOKULDHAM ZONE 1.pdf | 17 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1_DEC 25_GOULDHAM ZONE 1.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2_DEC 25_ GOKULDHAM PHASE I A B C D WING.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3_DEC 25_GOKULDHAM ZONE 1.pdf | 27 Jan 2026 |
| Form 1File: FORM 1_ DEC 24_ GOKULDHAM PHASE I_compressed.pdf | 22 Dec 2025 |
| Form 2File: FORM 2_ DEC 25_ GOKULDHAM PHASE I.pdf | 22 Dec 2025 |
| Form 3File: FORM 3_ DEC 24_ GOKULDHAM PHSE I.pdf | 22 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_DEC 24_GOKULDHAM ZONE 1.pdf | 22 Dec 2025 |
| Form 1File: FORM 1_ MARCH 25_ GOKULDHAM PHASE I_compressed.pdf | 22 Dec 2025 |
| Form 2File: FORM 2_ MARCH 25_ GOKULDHAM PHASE I.pdf | 22 Dec 2025 |
| Form 3File: FORM 3_ MARCH 25_ GOKUL DHAM PHASE I.pdf | 22 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_MARCH 25_GOKULDHAM ZONE 1.pdf | 22 Dec 2025 |
| Form 1File: FORM 1_ JUNE 25_ GOKULDHAM PHASE I_compressed.pdf | 22 Dec 2025 |
| Form 2File: FORM 2_ JUNE 25_ GOKULDHAM PHASE I.pdf | 22 Dec 2025 |
| Form 3File: FORM 3_ JUNE 25_ GOKULDHAN ZONE I.pdf | 22 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_JUNE 25_GOKULDHAM ZONE 1..pdf | 22 Dec 2025 |
| Form 1File: FORM 1_ SEP 25_ GOKULDHAM PHASE I_compressed.pdf | 22 Dec 2025 |
| Form 2File: FORM 2_ SEP 25_ GOKULDHAM PHASE I.pdf | 22 Dec 2025 |
| Form 3File: FORM 3_SEP 25_GOKULDHAM ZONE 1.pdf | 22 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_SEP 25_GOKULDHAM ZONE 1.pdf | 22 Dec 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A_25.pdf | 22 Dec 2025 |
| Form 5 (FY 2024-2025)File: Scan form 5.pdf | 30 Sep 2025 |
| Disclosure of sold/ booked inventoryFile: Q1 Sold Unsold.pdf | 18 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Apr to June 2025.pdf | 18 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 CA.pdf | 20 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 20 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 14 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sold and unsold inventory.pdf | 12 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 5 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate A,B,C,D,H,I,J Wing.pdf | 27 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf | 20 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 2022-23.pdf | 19 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate .pdf | 16 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: SoldUnsold Inventory.pdf | 16 Sep 2023 |
| Declaration about Commencement CertificateFile: Declaration About commencement certificate.pdf | 21 Apr 2023 |
| Declaration in FORM BFile: FORM B.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A FY 2019-2020.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY 2020-2021.pdf | 21 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold inventory.pdf | 21 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 2018-19.pdf | 21 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY2019-20.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2 A.pdf | 8 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5 2021-2022.pdf | 31 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank.pdf | 1 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: zone-i form-5.pdf | 29 Oct 2021 |
| Certificates of CA (Form 5)File: RAJSHREENIRMAN ZONE I FORM-5.pdf | 16 Jan 2019 |
| Certificates of CA (Form 3)File: raj shree.pdf | 31 Jul 2017 |
| PAN CardFile: raj shree pan card.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: Zone I- Title Report.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: index II- zone I.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: raj shree CC.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: boisar 1 I.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer cert A B.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer cert C D.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE DRAFT OF RERA.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Declaration zone 1.pdf | 30 Jul 2017 |
| Layout approvalFile: Layout.pdf | 29 Jul 2017 |
| Building plan approvalFile: Type J-J1 Wing C (1).pdf | 29 Jul 2017 |
| Building plan approvalFile: Type G-G1 Wing A,B,D,H,I,J.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Type G-G1 Wing A,B,D,H,I,J.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Type J-J1 Wing C (1).pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate- zone I.pdf | 29 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| GOKULDHAM ZONE 2P99000012100 | Boisar, Palghar | Sep 2017 | Certificate Signed | Oct 2018 | Late, Jan 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 77 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GOKULDHAM ZONE 01 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NA3,200+ in Palghar
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: RAJ SHREE NIRMAN BUILDERS PVT.LTD.
RAJ SHREE NIRMAN BUILDERS PVT.LTD. has 1 registration on MahaRERA, including GOKULDHAM ZONE 01. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if GOKULDHAM ZONE 01 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOKULDHAM ZONE 01?
The registered promoter entity is RAJ SHREE NIRMAN BUILDERS PVT.LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOKULDHAM ZONE 01?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GOKULDHAM ZONE 01?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GOKULDHAM ZONE 01?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOKULDHAM ZONE 01?
The professionals named in the filing: Architect: VASTU SHILP ASSOCIATES nishant patil; Engineer: DARSH CONSULTANT; Engineer: DILIP SHARMA LICENCED SUPERVISOR LICENCED PLUMBER ENGINEERS & CONTRACTORS; Chartered Accountant: SSRV AND Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOKULDHAM ZONE 01?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback