Home / Browse projects / Dakshina Kannada, Karnataka / GENESIS WHITE TRILLIUM
GENESIS WHITE TRILLIUM
RG-KA-18934 · RERA PRM/KA/RERA/1257/334/PR/200722/003503 · Last updated on RERA Karnataka portal: 3 Jul 2020
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
GENESIS WHITE TRILLIUM is a Residential/Group Housing project by GENESIS ENGINEERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/200722/003503 on 22 Jul 2020. Possession is promised by 18 Mar 2022.
At a glance
Project
- NameGENESIS WHITE TRILLIUM
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/200722/003503
- ReraGenie IDRG-KA-18934
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on22 Jul 2020
- Promised completion18 Mar 2022
- Revised completionNone
- Buildings1 building record
- Documents filed71 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GENESIS WHITE TRILLUM | - | - | - | 29 | 0 | 29 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 3 Jul 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 3 Jul 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VISHWANATH KAMATH | - | - |
| ARPANA PRASAD BALIGA | - | - |
| MARKADA SUDHAKAR KAMATH | - | - |
| SRIVIDYA SRINIVAS SHENOY | - | - |
| ARCHANA ARAVIND NAYAK | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUBRAMANYA |
| Engineer | SUBRAMANYA |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed71
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/200722/003503 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| FIRM REGISTRATION CERTIFICATEFile: Firm Registration certificate.jpg | 3 Jul 2020 |
| 2019-20 balance sheet profit and loss account ECTFile: ITR 19-20.pdf | 3 Jul 2020 |
| Partnership deedFile: Partnership Agreement 001.pdf | 3 Jul 2020 |
| Form-B is notarizedFile: Form B Affidavit.pdf | 3 Jul 2020 |
| GPAFile: GPA.pdf | 3 Jul 2020 |
| JDAFile: Joint Development Agreement.pdf | 3 Jul 2020 |
| Notarized Joint Affidavit cum DeclarationFile: Affidavit cum Declaration.pdf | 3 Jul 2020 |
| original sanctioned planFile: ORGINAL SANCATION PLAN.pdf | 3 Jul 2020 |
| Notarized Affidavit for 3(1) VoliationFile: Notarized Affidavit for 3(1) Voliation.pdf | 3 Jul 2020 |
| mescom nocFile: Mescom noc.pdf | 3 Jul 2020 |
| Partnership deedFile: Partnership Agreement.pdf | 3 Jul 2020 |
| Approved Plan or Commencement Certificate | - |
| Existing Project Plan | - |
| Existing Project Plan | - |
| AGREEMENT FOR SALE - WHITE TRILLIUM - DRAFT (1) | - |
| AGREEMENT FOR SALE - WHITE TRILLIUM - DRAFT (1) | - |
| Sale Deed and RTC | - |
| Existing Project Plan | - |
| Existing Project Plan | - |
| Blank | - |
| Project Specifications | - |
| Project Specifications | - |
| Encumbrance Certificate | - |
| Notarised Affidavit_compressed | - |
| Affidavit cum declaration merged | - |
| Khatha | - |
| Joint Development Agreement | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Existing Project Plan | - |
| Existing Project Plan | - |
| Change of land use merged | - |
| Unnamed document | - |
| Balance Sheet 2017 - 2018File: GENESIS ENG-BS.pdf | - |
| Balance Sheet 2016 - 2017File: GENESIS ENG-BS_compressed.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: GENESIS ENG-PL.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: GENESIS ENG-PL.pdf | - |
| Auditor's Report 2017 - 2018File: 2018-19 3CB.pdf | - |
| Auditor's Report 2016 - 2017File: 2017-18 3CB.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: GENESIS ENGINEERS_24-Oct-2019_216161131.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: GENESIS ENGINEERS_17-Oct-2018_338275391.pdf | - |
| Form B Declaration | - |
| Prospectus/BrochureFile: broucher.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_200722_003503.xlsx | - |
| Occupancy CertificateFile: occupancy certificate.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Architect Certificate-completion.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: FORM 4cc-ca report.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: completion affidavit.pdf | - |
| ENGINEER CERTIFICATEFile: Engineers Certificate-completion.pdf | - |
| COMPLETION CERTIFICATEFile: completion certificate.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep GENESIS WHITE TRILLIUM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 34 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: GENESIS ENGINEERS
GENESIS ENGINEERS has 2 registrations on RERA Karnataka, including GENESIS WHITE CORNUS and GENESIS WHITE TRILLIUM. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if GENESIS WHITE TRILLIUM is delayed beyond 18 Mar 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of GENESIS WHITE TRILLIUM?
The registered promoter entity is GENESIS ENGINEERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in GENESIS WHITE TRILLIUM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at GENESIS WHITE TRILLIUM?
The professionals named in the filing: Architect: SUBRAMANYA; Engineer: SUBRAMANYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GENESIS WHITE TRILLIUM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.