ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / GEETA PALACE

Completed No litigation declared Others project

GEETA PALACE

By ASHAPURA PROPERTIES

RG-MH-14419 · RERA P52000023559 · Last updated on MahaRERA portal: 24 Jan 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 20 documents Report an error

GEETA PALACE is a Others project by ASHAPURA PROPERTIES in Raigarh, Maharashtra, registered with MahaRERA as P52000023559 on 19 Dec 2019. The registration is recorded completed; possession was promised by 30 Dec 2023.

At a glance

Project

  • NameGEETA PALACE
  • TypeOthers
  • Location
    • PUSHPAK NODE
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000023559
  • ReraGenie IDRG-MH-14419

Builder

  • NameASHAPURA PROPERTIES
  • Entity typePartnership
  • PartnerLADHA BHACHU VAVIYA
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2019PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Dec 2019
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed20 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GEETA PALACENA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

GEETA PALACE: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area190 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
BALKRISHNA VINAYAK ZUGEPanvelRaigarh

Approvals and building plan

Permissible FSI284.11
Proposed, not sanctioned284 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAiroli Sector 5 Branch

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL ARCHITECTS
EngineerSHRAVANI CONSULTANTS
Chartered AccountantCA JYOTI B GAJRA
PartnerRole in project
ASHAPURA PROPERTIES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Jan 2023

Documents filed20

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5.PDF31 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.PDF31 Dec 2021
Layout approvalFile: ACC DRG New File (1).pdf16 Dec 2019
Building plan approvalFile: ACC DRG New File (1).pdf16 Dec 2019
Copy of Layout Approval (in case of layout)File: ACC DRG New File (1).pdf16 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: ACC DRG New File (1).pdf16 Dec 2019
OtherFile: Membership.pdf13 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf20 Nov 2019
Details of encumbrancesFile: Encumbrances.pdf16 Nov 2019
Declaration in FORM BFile: FORM B.pdf16 Nov 2019
Declaration in FORM BFile: FORM B - ZUGE.pdf16 Nov 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: 150 CC.pdf9 Oct 2019
Building plan approvalFile: PLAN.pdf6 Oct 2019
PAN CardFile: ASHAPURA PROPERTIES PANCARD.pdf6 Oct 2019
Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf6 Oct 2019
Proforma of Allotment letterFile: AGREEMENT FOR SALE - GEETA PALACE.pdf6 Oct 2019
Copy of the legal title reportFile: TITLE CERTIFICATE ASHAPURA.pdf27 Sep 2019
Copy of the legal title reportFile: SEARCH REPORT ASHAPURA.pdf27 Sep 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
BALAJI KRUPAPLOT NO 112 SECTOR 21 GHANSOLI12CompletedDec 2013Dec 2013

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GEETA PALACE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUSHPAK NODE5,900+ in Raigarh

Builder: ASHAPURA PROPERTIES

ASHAPURA PROPERTIES has 1 registration on MahaRERA, including GEETA PALACE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if GEETA PALACE is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GEETA PALACE?

The registered promoter entity is ASHAPURA PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GEETA PALACE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GEETA PALACE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GEETA PALACE?

The professionals named in the filing: Architect: ATUL PATEL ARCHITECTS; Engineer: SHRAVANI CONSULTANTS; Chartered Accountant: CA JYOTI B GAJRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GEETA PALACE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GEETA PALACE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GEETA PALACE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.