Home / Browse projects / Thane, Maharashtra / Gayatri Elegance

Registered No litigation declared Others project

Gayatri Elegance

By Gayatrikripa Developers Private Limited

RG-MH-28113 · RERA P51700024926 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 92%
10 of 140Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

Gayatri Elegance is a Others project by Gayatrikripa Developers Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700024926 on 12 Mar 2020. Possession is promised by 30 Dec 2026. The completion date has moved by 12 months from the original filing. 130 of the 140 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameGayatri Elegance
  • TypeOthers
  • Location
    • INDRALOK
    • PHASE 4
    • NAVGHAR
    • BHAYANDER EAST
    • BHAYANDAR
    • Thane
    • 401105
  • Pincode401105
  • RERA no.P51700024926
  • ReraGenie IDRG-MH-28113

Builder

  • NameGayatrikripa Developers Private Limited
  • Entity typeCompany
  • DirectorsAnshul Hiramani Pandey, Hiramani Premchand Pandey
  • Declared earlier projects1 →

Key dates

this monthRegisteredMar 2020First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Mar 2020
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2025)
  • Buildings1 building record
  • Documents filed66 files

Current status

93%130 of 140 units booked
90.1%Work done, per cost certificate

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Gayatri EleganceNA101012614140

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

Gayatri Elegance: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered1
Open Space1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,380 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Mar 2026

Approvals and building plan

Permissible FSI3380.0
Proposed, not sanctioned2,942 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThakur Village Kandivali East
Estimated costRs 24.74 cr
Cost incurredRs 22.29 cr
Work done90.11%
BuildingWingEstimatedIncurred
Gayatri EleganceNARs 20.76 crRs 19.31 cr
-NARs 3.97 crRs 2.98 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMario E Correa
EngineerRBD Alliance LLP
EngineerRDB Alliance LLP
Chartered AccountantLilani & Co.
Chartered AccountantVINOD KUMAR JAIN
PartnerRole in project
Gayatrikripa Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07012619345Dec 2025 → Dec 2026

Reason as filed by the promoterDue to labour issues, the work could not be completed within the stipulated time limit, otherwise all the approvals are in place and we are expecting the work to be completed within next 12 months.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf20 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf20 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf20 Aug 2026
Withdrawal Update Form 2File: Form 2 (Revised).pdf20 Aug 2026
Withdrawal Update Form 2File: Form 2 (Revised).pdf20 Aug 2026
Withdrawal Update Form 2File: Form 2 (Revised).pdf20 Aug 2026
Withdrawal Update Form 3File: Form 3 Q1.pdf20 Aug 2026
Withdrawal Update Form 3File: Form 3 Q1.pdf20 Aug 2026
Withdrawal Update Form 3File: Form 3 Q1.pdf20 Aug 2026
Withdrawal Update Form 1File: Form 1 Q4.pdf12 Jun 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf12 Jun 2026
Withdrawal Update Form 3File: Signed Form 3 Q4.pdf12 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf4 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf4 Feb 2026
Withdrawal Update Form 3File: Final Signed form 3.pdf4 Feb 2026
Withdrawal Update Form 1File: FORM 1 05 07 25.pdf7 Jan 2026
Withdrawal Update Form 1File: Form 1 30.09.25 A.C..pdf7 Jan 2026
Withdrawal Update Form 2File: FORM 2 05 07 25.pdf7 Jan 2026
Withdrawal Update Form 2File: Form 2 30.09.25 E.C..pdf7 Jan 2026
Withdrawal Update Form 3File: Form 3 G Elegance 16 10 25 final signed compressed.pdf7 Jan 2026
Withdrawal Update Form 3File: Form 3 Q2 FInal.pdf7 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf9 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf9 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf9 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf28 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf28 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Certificate.pdf28 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 G Elegance.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: GKDPL Form 5.pdf20 May 2025
Layout approvalFile: 1.pdf8 Mar 2025
Layout approvalFile: 2.pdf8 Mar 2025
Layout approvalFile: 3.pdf8 Mar 2025
Layout approvalFile: 4.pdf8 Mar 2025
Layout approvalFile: 5.pdf8 Mar 2025
Layout approvalFile: 6.pdf8 Mar 2025
Layout approvalFile: 7.pdf8 Mar 2025
Building plan approvalFile: Register Agreement for Development 2_11zon (2).pdf8 Mar 2025
Building plan approvalFile: Register Agreement for Development 3.pdf8 Mar 2025
Building plan approvalFile: Register Agreement for Development 4.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 1.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 2.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 3.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 4.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 5.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 6.pdf8 Mar 2025
Copy of Layout Approval (in case of layout)File: 7.pdf8 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Register Agreement for Development 2_11zon (2).pdf8 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Register Agreement for Development 3.pdf8 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Register Agreement for Development 4.pdf8 Mar 2025
Building plan approvalFile: Register Agreement for Development 1.pdf7 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Register Agreement for Development 1.pdf7 Mar 2025
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: NEW CC.pdf5 Mar 2025
Proforma of Agreement for saleFile: Revised Agreement For Sale.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect's certificate compressed.pdf3 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gayatri Elegance Form 3 Initial Registration Scanned Final Compressed.pdf3 Mar 2020
Copy of the legal title reportFile: Title certificate GE.pdf28 Feb 2020
Details of encumbrancesFile: Encumbrance Certificate.pdf28 Feb 2020
Declaration in FORM BFile: Form B Gayatri Elegance.pdf28 Feb 2020
Proforma of Allotment letterFile: AGREEMENT FOR SALE MIRA ROAD.pdf28 Feb 2020
Layout approvalFile: Layout plan 1 Compressed.pdf27 Feb 2020
Building plan approvalFile: Building Plan Compress.pdf27 Feb 2020
PAN CardFile: Pancard Gayatrikripa.pdf27 Feb 2020
Copy of Layout Approval (in case of layout)File: Layout plan 1 Compressed.pdf27 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Compress.pdf27 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: CC NA Compressed.pdf27 Feb 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Gayatri Indraprasth, Phase II and III, PanvelSurvey No. 28 .1 and 29 .1 Adai Panvel87CompletedJan 2017Late, Mar 2017

How this compares with Thane

93%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Gayatri Elegance on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near INDRALOK, PHASE 4, NAVGHAR, BHAYANDER EAST7,600+ in Thane

Builder: Gayatrikripa Developers Private Limited

Gayatrikripa Developers Private Limited has 1 registration on MahaRERA, including Gayatri Elegance. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Gayatri Elegance is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gayatri Elegance?

The registered promoter entity is Gayatrikripa Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gayatri Elegance?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Gayatri Elegance?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gayatri Elegance?

The professionals named in the filing: Architect: Mario E Correa; Engineer: RBD Alliance LLP; Engineer: RDB Alliance LLP; Chartered Accountant: Lilani & Co.; Chartered Accountant: VINOD KUMAR JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gayatri Elegance?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gayatri Elegance. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gayatri Elegance to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.