Registration lapsed No litigation declared Others project

GAYATRI APARTMENT

By Vijaykumar Vasudev Patki

RG-MH-19629 · RERA P53000003095 · Last updated on MahaRERA portal: 19 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

GAYATRI APARTMENT is a Others project by Vijaykumar Vasudev Patki in Kolhapur, Maharashtra, registered with MahaRERA as P53000003095 on 4 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameGAYATRI APARTMENT
  • TypeOthers
  • Location
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416003
  • Pincode416003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000003095
  • ReraGenie IDRG-MH-19629

Builder

  • NameVijaykumar Vasudev Patki
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GAYATRI APARTMENTNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

GAYATRI APARTMENT: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 19 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes4%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered13

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area650 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2330.3
Proposed, not sanctioned1,179 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChandramala Apartment Near Creshar chowk Kolhapur

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShrikant yadav
ArchitectAbhimanyu Mulik
EngineerAbhimanyu Mulik
Chartered AccountantPRITY ANIKET PACHORE
PartnerRole in project
Vijaykumar Vasudev Patki-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000010242Jun 2021 → Jun 2022

Reason as filed by the promoterDue to heavy flood situation in Kolhapur the construction work was hampered in 2019. 2) Due to tremendous delay in sanctioning revised plan by Kolhapur Municipal Corporation without any reason. File was in warded on Dec - 2018 and was sanctioned by commissioner on 18/7/2020 and yet Bandhkam Parvana / Prarambh Pramanpatra has not been issued to us of revised plan. 3) Covid -19 Pandemic situation, lockdown imposed by Government and due that labor problem we are facing since then. 4) Due new UDCPR bylaws imposed by Maharashtra Government need to get sanctions accordingly from KMC.

EXT53000011815Jun 2021 → Jun 2024

Reason as filed by the promoterThe reasons for the delay in the project areas mentioned: 1. Due to the heavy flood situation in Kolhapur, the construction work was hampered in 2019. 2. Due to tremendous delay in sanctioning revised plan by Kolhapur Municipal Corporation without any reason. The file was in warded on 18/12/2018 and was sanctioned by the commissioner on 18/7/2020 and yet the commencement certificate was issued to us on 26/6/2021. 3. Covid -19 Pandemic situation, lockdown imposed by Government, and the labor shortage for almost 6 months. 4. Due to the new UDCPR bylaws imposed by Maharashtra Government need to g

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: 19 form 5 delay 2223 .pdf19 Jul 2024
OtherFile: 19 form 5 delay 2324.pdf19 Jul 2024
Declaration in FORM BFile: RERA AFFIDEVIT2024.pdf3 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21 - 22.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22 - 23.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2 A SAIT SUPER VISOR.pdf3 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY 2024.pdf3 Jul 2024
Certificates of CA (Form 3)File: FORM 3 CA 2024.pdf3 Jul 2024
Certificates of CA (Form 3)File: SOLDUNSOLD CA INVENTORY.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 22-23.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 23-24.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 23-24.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA FORM 5 2023 2024.pdf3 Jul 2024
OtherFile: Letter.pdf21 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 G19.pdf17 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 G19.pdf17 Feb 2023
Certificates of CA (Form 3)File: G19 CA Form 3.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 G19.pdf17 Feb 2023
Disclosure of sold/ booked inventoryFile: G19 Sold-unsold inventory.pdf26 Dec 2022
Certificates of CA (Form 3)File: G19 CA Form 3.pdf26 Dec 2022
Building plan approvalFile: G19 revised plans.pdf6 May 2022
Building Plan Approval (IOD)File: G19 revised plans.pdf6 May 2022
Commencement Certificates / NA Order for plotted developmentFile: G19 CC 3-22.pdf6 May 2022
Disclosure of sold/ booked inventoryFile: Inventory 19.pdf28 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: G19 1718.pdf28 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: G19 1819.pdf28 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: G19 1920.pdf28 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: G19 2021.pdf28 Jul 2021
Declaration about Commencement CertificateFile: Declaration 19.pdf25 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2a G19 fy19-20.pdf22 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2a G19 fy20-21.pdf22 Jul 2021
Details of Restarting of Construction work post lockdownFile: g19 post lockdown.pdf22 Jul 2021
Building plan approvalFile: sanction plan-19.pdf31 Jul 2017
Building plan approvalFile: 19 Proposed Plan.pdf31 Jul 2017
Layout approvalFile: sanction plan-19.pdf31 Jul 2017
PAN CardFile: Firm pan 19.pdf31 Jul 2017
Copy of the legal title reportFile: Search Report 19.pdf31 Jul 2017
Details of encumbrancesFile: Patki No Loan 19.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: sanction plan-19.pdf31 Jul 2017
Building Plan Approval (IOD)File: sanction plan-19.pdf31 Jul 2017
Building Plan Approval (IOD)File: 19 Proposed Plan.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement 19.pdf31 Jul 2017
Declaration in FORM BFile: Form B 19.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Patki 19 Architect.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Patki 19 Engineer.pdf31 Jul 2017
Certificates of CA (Form 3)File: Patki 19 Ca final.pdf31 Jul 2017
Proforma of Allotment letterFile: Agreement to salePlot_No_19_Gayatri (1)-rotated (1).pdf31 Jul 2017
OtherFile: Pataki 19 landowner undertaking.pdf31 Jul 2017
OtherFile: Development index 19.pdf31 Jul 2017
OtherFile: Patki proposed 19 undertaking.pdf31 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Vijaykumar Vasudev PatkiP53000007095TARABAI PARK, Kolhapur84Aug 2017OngoingJun 2026Registered original: Jun 2021Not delivered
OLIVE BRANCH1505 1 B Plot No 5 New Palace kolhapur7-CompletedJul 2015Late, Apr 2017

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one moved by 36 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is among them

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep GAYATRI APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kolhapur (M Corp.)880+ in Kolhapur

Builder: Vijaykumar Vasudev Patki

Vijaykumar Vasudev Patki has 2 registrations on MahaRERA, including GAYATRI-BHAWANI APARTMENT and GAYATRI APARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What does it mean that GAYATRI APARTMENT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GAYATRI APARTMENT is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAYATRI APARTMENT?

The registered promoter entity is Vijaykumar Vasudev Patki, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAYATRI APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GAYATRI APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAYATRI APARTMENT?

The professionals named in the filing: Architect: Shrikant yadav; Architect: Abhimanyu Mulik; Engineer: Abhimanyu Mulik; Chartered Accountant: PRITY ANIKET PACHORE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAYATRI APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAYATRI APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAYATRI APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.