GAYATRI APARTMENT
RG-MH-19629 · RERA P53000003095 · Last updated on MahaRERA portal: 19 Jul 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GAYATRI APARTMENT is a Others project by Vijaykumar Vasudev Patki in Kolhapur, Maharashtra, registered with MahaRERA as P53000003095 on 4 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 36 months from the original filing.
At a glance
Project
- NameGAYATRI APARTMENT
- TypeOthers
- Location
- Kolhapur (M Corp.)
- Karvir
- Kolhapur
- 416003
- Pincode416003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53000003095
- ReraGenie IDRG-MH-19629
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Aug 2017
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed51 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GAYATRI APARTMENT | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
GAYATRI APARTMENT: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 19 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 4% |
Parking filed13
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shrikant yadav |
| Architect | Abhimanyu Mulik |
| Engineer | Abhimanyu Mulik |
| Chartered Accountant | PRITY ANIKET PACHORE |
| Partner | Role in project |
|---|---|
| Vijaykumar Vasudev Patki | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to heavy flood situation in Kolhapur the construction work was hampered in 2019. 2) Due to tremendous delay in sanctioning revised plan by Kolhapur Municipal Corporation without any reason. File was in warded on Dec - 2018 and was sanctioned by commissioner on 18/7/2020 and yet Bandhkam Parvana / Prarambh Pramanpatra has not been issued to us of revised plan. 3) Covid -19 Pandemic situation, lockdown imposed by Government and due that labor problem we are facing since then. 4) Due new UDCPR bylaws imposed by Maharashtra Government need to get sanctions accordingly from KMC.
Reason as filed by the promoterThe reasons for the delay in the project areas mentioned: 1. Due to the heavy flood situation in Kolhapur, the construction work was hampered in 2019. 2. Due to tremendous delay in sanctioning revised plan by Kolhapur Municipal Corporation without any reason. The file was in warded on 18/12/2018 and was sanctioned by the commissioner on 18/7/2020 and yet the commencement certificate was issued to us on 26/6/2021. 3. Covid -19 Pandemic situation, lockdown imposed by Government, and the labor shortage for almost 6 months. 4. Due to the new UDCPR bylaws imposed by Maharashtra Government need to g
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed51
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| OtherFile: 19 form 5 delay 2223 .pdf | 19 Jul 2024 |
| OtherFile: 19 form 5 delay 2324.pdf | 19 Jul 2024 |
| Declaration in FORM BFile: RERA AFFIDEVIT2024.pdf | 3 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2.pdf | 3 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21 - 22.pdf | 3 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22 - 23.pdf | 3 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2 A SAIT SUPER VISOR.pdf | 3 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY 2024.pdf | 3 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3 CA 2024.pdf | 3 Jul 2024 |
| Certificates of CA (Form 3)File: SOLDUNSOLD CA INVENTORY.pdf | 3 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 22-23.pdf | 3 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 23-24.pdf | 3 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 23-24.pdf | 3 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA FORM 5 2023 2024.pdf | 3 Jul 2024 |
| OtherFile: Letter.pdf | 21 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 G19.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 G19.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: G19 CA Form 3.pdf | 17 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 G19.pdf | 17 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: G19 Sold-unsold inventory.pdf | 26 Dec 2022 |
| Certificates of CA (Form 3)File: G19 CA Form 3.pdf | 26 Dec 2022 |
| Building plan approvalFile: G19 revised plans.pdf | 6 May 2022 |
| Building Plan Approval (IOD)File: G19 revised plans.pdf | 6 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: G19 CC 3-22.pdf | 6 May 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory 19.pdf | 28 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: G19 1718.pdf | 28 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: G19 1819.pdf | 28 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: G19 1920.pdf | 28 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: G19 2021.pdf | 28 Jul 2021 |
| Declaration about Commencement CertificateFile: Declaration 19.pdf | 25 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2a G19 fy19-20.pdf | 22 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2a G19 fy20-21.pdf | 22 Jul 2021 |
| Details of Restarting of Construction work post lockdownFile: g19 post lockdown.pdf | 22 Jul 2021 |
| Building plan approvalFile: sanction plan-19.pdf | 31 Jul 2017 |
| Building plan approvalFile: 19 Proposed Plan.pdf | 31 Jul 2017 |
| Layout approvalFile: sanction plan-19.pdf | 31 Jul 2017 |
| PAN CardFile: Firm pan 19.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Search Report 19.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Patki No Loan 19.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: sanction plan-19.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: sanction plan-19.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 19 Proposed Plan.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement 19.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Form B 19.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Patki 19 Architect.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Patki 19 Engineer.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Patki 19 Ca final.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Agreement to salePlot_No_19_Gayatri (1)-rotated (1).pdf | 31 Jul 2017 |
| OtherFile: Pataki 19 landowner undertaking.pdf | 31 Jul 2017 |
| OtherFile: Development index 19.pdf | 31 Jul 2017 |
| OtherFile: Patki proposed 19 undertaking.pdf | 31 Jul 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Vijaykumar Vasudev PatkiP53000007095 | TARABAI PARK, Kolhapur | 84 | Aug 2017 | Ongoing | Jun 2026Registered original: Jun 2021 | Not delivered |
| OLIVE BRANCH | 1505 1 B Plot No 5 New Palace kolhapur | 7 | - | Completed | Jul 2015 | Late, Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 51 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GAYATRI APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kolhapur (M Corp.)880+ in Kolhapur
24 KEYWEST EAST AND WEST AVENUE
KEYWEST INFRA
Loknagari Karande Mala
VIKESH ABHAYKUMAR OSWAL
KRYSTAL TOWERS
RAYSONS CONSTRUCTIONS
GAYATRI-BHAWANI APARTMENT
Vijaykumar Vasudev Patki
EMINENT VISION TOWER
ACE DEVELOPERS
THE PARKSIDE
DESHPANDE INFRA
See every Kolhapur project, with the district possession charts
Builder: Vijaykumar Vasudev Patki
Vijaykumar Vasudev Patki has 2 registrations on MahaRERA, including GAYATRI-BHAWANI APARTMENT and GAYATRI APARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What does it mean that GAYATRI APARTMENT shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GAYATRI APARTMENT is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GAYATRI APARTMENT?
The registered promoter entity is Vijaykumar Vasudev Patki, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GAYATRI APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GAYATRI APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GAYATRI APARTMENT?
The professionals named in the filing: Architect: Shrikant yadav; Architect: Abhimanyu Mulik; Engineer: Abhimanyu Mulik; Chartered Accountant: PRITY ANIKET PACHORE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GAYATRI APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback