Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 66 months
- 6 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GAURI EXCELLENCY is a Others project by M/S GAURI LAND DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004832 on 9 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 66 months from the original filing. 309 of the 315 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 8 complaints are on record with the regulator.
At a glance
Project
- NameGAURI EXCELLENCY
- TypeOthers
- Location
- CHARKOP
- KANDIVALI WEST
- Borivali
- Mumbai Suburban
- 400067
- Pincode400067
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004832
- ReraGenie IDRG-MH-25140
Builder
- NameM/S GAURI LAND DEVELOPERS LLP
- Entity typePartnership
- PartnersNARESH VELJI GOGARI, PIYUSH MORARJI SHAH, PARESH VALLABHDAS THAKKAR, MANOJ VELJI GOGARI
- Other registrations2 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2020)
- Buildings1 building record
- Documents filed136 files
Current status
Figures as on 26 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GAURI EXCELLENCY WING A AND B | NA | 37 | 31 | 304 | 11 | 315 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
GAURI EXCELLENCY WING A AND B: 83% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 31% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 85% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed216
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GAURI EXCELLENCY WING A AND B | NA | Rs 114.63 cr | Rs 114.63 cr |
| - | NA | Rs 23.37 cr | Rs 23.15 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMEER KULKARNI |
| Engineer | TUSHAR SUTHAR |
| Chartered Accountant | NEHALI AND CO |
| Chartered Accountant | NEHALI & CO |
| Partner | Role in project |
|---|---|
| M/S GAURI LAND DEVELOPERS LLP | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to delay in getting approval from concerned authority the project was not able to get completed in time. Request you to please get us one year extension.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/12/2024
Reason as filed by the promoterDue to delay in getting the approval from the concerned authority, the project was not able to get completed on the above mentioned date and we were not able to provide the possession to our clients. Therefore, we would like to request you to further grant us the extension up to 30/06/2025.
Reason as filed by the promoterWe would like to request you that the project named as "Gauri Excellency" which is located at Babharekar Nagar, Near Hindustan Naka, Charkop, Kandivali (West). Mumbai - 400067 having its Registration No P51800004832 was mentioned to be completed on 30/06/2025 The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry After the labour issue got resolved & the project kick started then the project in half of the midway required Environment Clearance and Highrise NOC and
Reason as filed by the promoterI kindly want to bring to your attention the ongoing Issue we are facing regarding pending payments from our customers for the work completed in their flats. Despite numerous follow-ups by our CRM team through emails, WhatsApp messages, and phone calls, we are experiencing no payments as customers are providing various excuses for not fulfilling their financial commitments. Additionally, we have attempted to communicate the necessity of the MAHARERA extension to our customers, but unfortunately, we have not received any positive response from them to proceed with the New MAHARERA Extension. Gi
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000292825 | PARTHA NATH | GAURI EXCELLENCY | 25/09/2022 |
| CC006000000396636 | Vincent Joseph Gomes | M/s. Gauri Land Developers LLP | 13/07/2023 |
| CC006000000396908 | Bhavesh Panchal | Gauri Land Developers LLP | 01/08/2023 |
| CC006000000397266 | Ganesh M Shetty | M/s. Gauri Land Developers LLP | 30/08/2023 |
| CC006000000408313 | Vaibhav Shashikant Bhandari | Gauri Land Developers LLP | 02/12/2023 |
| CC12500271 | MRINAL TRIPATHI | M/S GAURI LAND DEVELOPERS LLP | 25/01/2025 |
| CC12502176 | Ashwini Dinesh Mohite | M/S GAURI LAND DEVELOPERS LLP | 01/07/2025 |
| CC12603029 | Radhika Shashikant Powar | M/S GAURI LAND DEVELOPERS LLP | 22/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed136
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 GAURI EX.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: FORM 2 GAURI EX.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: FORM 3 GAURI EXCELLANCY March 26.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 1 Dec 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 1 Dec 2025 |
| Withdrawal Update Form 2File: FORM2.pdf | 1 Dec 2025 |
| Withdrawal Update Form 2File: FORM2.pdf | 1 Dec 2025 |
| Withdrawal Update Form 3File: Resigned CA CERTIFICATE- GAURI EXCELLANCY sept 25.pdf | 1 Dec 2025 |
| Withdrawal Update Form 3File: Resigned CA CERTIFICATE- GAURI EXCELLANCY sept 25.pdf | 1 Dec 2025 |
| Withdrawal Update Form 1File: form 1.pdf | 25 Nov 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 25 Nov 2025 |
| Withdrawal Update Form 3File: gauri excelllency final june 25.pdf | 25 Nov 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 15 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 (3).pdf | 15 Apr 2025 |
| Certificates of CA (Form 3)File: Resigned CA CERTIFICATE- GAURI EXCELLANCY Dec24.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 14 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 14 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINERR CERTIFICATE GAURI EX.pdf | 14 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure- Gauri Excellency.pdf | 28 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 27 Dec 2024 |
| Declaration in FORM BFile: GAURI EXCELLANCY AFFIDAVIT.pdf | 25 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate (1).pdf | 24 Dec 2024 |
| Certificates of CA (Form 3)File: Signed_CA CERTIFICATE- GAURI EXCELLANCY sept 24.pdf | 24 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 24 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 17 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2 A.pdf | 17 Aug 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 31 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 31 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 31 May 2024 |
| Certificates of CA (Form 3)File: CA FORM 3.pdf | 1 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 23 Q4.pdf | 21 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 23 Q4.pdf | 21 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 23 Q4.pdf | 14 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSURE - GAURI - 28-11-2023.pdf | 20 Jan 2024 |
| Declaration in FORM BFile: Form B.pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer form 2A .pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf | 29 Nov 2023 |
| CERSAI detailsFile: Cersai declaration.pdf | 29 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold - Gauri Excellency (1).pdf | 28 Nov 2023 |
| Certificates of CA (Form 3)File: CA Form 3 GAURI EXCELLANCY sept 23.pdf | 28 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ca form 5 22-23.pdf | 27 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf | 23 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY.pdf | 26 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate NX.pdf | 26 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Gauri Exce Jul 2023.pdf | 27 Jul 2023 |
| Form 2AFile: Form 2A Gauri exce.pdf | 27 Jul 2023 |
| Certificates of CA (Form 3)File: Signed Ca Certificate Gauri Excellancy june'23 (1).pdf | 22 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gauri Exc form 2.pdf | 25 May 2023 |
| Certificates of CA (Form 3)File: Signed Ca Excellancy.pdf | 25 May 2023 |
| Certificates of CA (Form 3)File: Signed Ca Certificate Gauri Excellancy march'23.pdf | 20 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC parishram SRA.pdf | 24 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 13 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD, BOOKED INVENTORY copy.pdf | 21 Jan 2023 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 6 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf | 6 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf | 6 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf | 6 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gauri Excellency ARCHITECH CERTIFICATE.pdf | 2 Nov 2022 |
| Certificates of CA (Form 3)File: Signed Ca Certificate Gauri Excellancy sep'22.pdf | 1 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gauri Exc R1 Oct 2022.pdf | 21 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 GAURI EXECELLENCE.pdf | 3 Aug 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gauri 2 EXEC Aug 2022 22-20.pdf | 3 Aug 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GAURI EXC FORM 2.pdf | 17 May 2022 |
| Certificates of CA (Form 3)File: Ca Certificate Gauri Excellancy New Format.pdf | 12 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate GLLP.pdf | 12 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A GLLP.pdf | 11 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 29 Jan 2022 |
| Certificates of CA (Form 3)File: Ca Certificate Gauri Excellancy New Format.pdf | 27 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gauri Certificate - 4832 FORM(1).pdf | 18 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GAURI EX 48.pdf | 21 Oct 2021 |
| Form 2AFile: GLLP FORM 2A.pdf | 19 Oct 2021 |
| Certificates of CA (Form 3)File: FORM 3 S.pdf | 15 Oct 2021 |
| Form 2AFile: GLLP FORM 2A.pdf | 14 Jul 2021 |
| Certificates of CA (Form 3)File: signed CA Certificate Gauri Excellancy 1 MAR'21_2.pdf | 2 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1.pdf | 16 Apr 2021 |
| Form 2AFile: 2A_2.pdf | 16 Apr 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 2 Mar 2021 |
| Certificates of CA (Form 3)File: signed Ca certificate (5).pdf | 21 Jan 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 136 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GAURI EXCELLENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KANDIVALI WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 252 registered projects within 2 km.
Ruparel Optima Ph I
Ruparel Infra & Realty Pvt Ltd
"SALE BLDG NO. 6 (A & B) WING KNOWN AS NORTHER
N.ROSE DEVELOPERS PVT LTD
JP Commerz
Metallica Industries Limited
Ruparel Skygreens I
Shree Siddhivinayak Infrastructure & Realt
ShreejiAikyam
Rushabh Developers
Shiv Vardaan
NAVKARMIK HOMES LLP, URVI CONSTRUCTION
See every Mumbai Suburban project, with the district possession charts
Builder: M/S GAURI LAND DEVELOPERS LLP
M/S GAURI LAND DEVELOPERS LLP has 3 registrations on MahaRERA, including GAURI EXCELLENCY and GAURI EXCELLENCY NX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that GAURI EXCELLENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GAURI EXCELLENCY is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GAURI EXCELLENCY?
The registered promoter entity is M/S GAURI LAND DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GAURI EXCELLENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GAURI EXCELLENCY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GAURI EXCELLENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GAURI EXCELLENCY?
The professionals named in the filing: Architect: SAMEER KULKARNI; Engineer: TUSHAR SUTHAR; Chartered Accountant: NEHALI AND CO; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GAURI EXCELLENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback