Home / Browse projects / Palghar, Maharashtra / GAURAV HEIGHTS

Registered Litigation declared Residential / Group Housing project

GAURAV HEIGHTS

By MAHAVIR DEVELOPERS

RG-MH-27294 · RERA P99000009792 · Last updated on MahaRERA portal: 24 Feb 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 93 months
  • 3 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 93 months from the original
16 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
1Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

GAURAV HEIGHTS is a Residential / Group Housing project by MAHAVIR DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000009792 on 22 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 93 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGAURAV HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • -
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000009792
  • ReraGenie IDRG-MH-27294

Builder

  • NameMAHAVIR DEVELOPERS
  • Entity typePartnership
  • PartnersJITENDRA HASTIMLAL JAIN, ANKUR CHETANKUMAR SHAH, JYOTSNA JITDENTRA JAIN, PRAKASH BHAVARLAL JAIN, DILIP BHOGILAL SHAH, MANOJKUMAR MANEKCHAND RATHOD, SHEETAL MANOJKUMAR RATHOD, DHARMESH NAGINCHAND JAIN
  • Other registrations7 more →
  • Completed3 of 8
  • No longer live2 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 1 Jun 2019)
  • Buildings3 building records
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA1212000
B WINGNA1212000
A AND B WING PROPOSEDNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

A WING89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A AND B WING PROPOSED0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 24 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%
LIFTYes100%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered15
Open Space5
BuildingClosed/CoveredOpen SpaceTotal
A WING10313
B WING527

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,605 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jun 2026

Approvals and building plan

Sanctioning authorityVVCMC
Permissible FSI5059.64
Proposed, not sanctioned2,602 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHRI KRISHNA BHUVAN OPP VITHAL MANDIR AGASHI ROAD VIRAR 401303

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHREE CONSULTANT
EngineerMOHD SUFIYAN SHAIKH
Chartered AccountantASHWIN NAIR
PartnerRole in project
MAHAVIR DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000008520Jun 2019 → Dec 2023

Reason as filed by the promoterConsent Resolution is attached

EXT99000005857Jun 2019 → May 2020

Reason as filed by the promoterProject Gaurav Heights is completed Appx. 97% as per Architect` Certificate dated 01-03-2019 , copy of teh same is already uploaded on Maharera Site & Developer has applied to VVCMC - Town Planning Authority for regularization of additional construction by using TDR as per MRTP Act, 1966 on 16-05-2017 & have also applied again on 21-02-2019 copy of the same is enclosed herewith . The sadi Project is under Revise Sanction pending from VVCMC & Applicant has no control over thisa situation & applicant is waiting for the regularization of addtional built up area and proposed area of construction &

EXT99000019395Jun 2019 → Mar 2027

Reason as filed by the promoterWE HAVE NOT RECEIVED OC YET.

Litigation declared1

CaseCourtStatus
4/2015VASAI COURTDECISION PENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000192317Radheshyam guptaMahavir Developers27/01/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf24 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUN 24.pdf22 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEP 24.pdf22 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC 24.pdf22 Feb 2025
Certificates of CA (Form 3)File: FORM 3 JUN 24.pdf22 Feb 2025
Certificates of CA (Form 3)File: FORM 3 SEP 24.pdf22 Feb 2025
Certificates of CA (Form 3)File: FORM 3 DEC 24.pdf22 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUN 24.pdf22 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SEP 24.pdf22 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DEC 24.pdf22 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD JUN 24.pdf22 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD SEP 24.pdf22 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD DEC 24.pdf22 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a mahavir dev.pdf22 Feb 2025
Declaration in FORM BFile: MAHAVIR-OWNER.pdf19 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM A MAHA SIGNED.pdf19 Jun 2024
Declaration in FORM BFile: FORM B.pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A SIGNED.pdf10 Jun 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf10 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SIGNED.pdf7 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MAR 24.pdf7 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a.pdf7 Jun 2024
Certificates of CA (Form 3)File: FORM 3.pdf7 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf7 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 signed.pdf7 Jun 2024
Certificates of CA (Form 3)File: FORM-3 - 30-09-2022.PDF10 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: mahaveer form 1-2.pdf8 Nov 2022
Certificates of CA (Form 3)File: MAHAVIR DEVELOPER FORM-3 - 2021-2022.PDF11 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: MAHAVIR DEVELOPER FORM-5 - 2021 - 2022.PDF11 Oct 2022
Layout approvalFile: MYSCAN_20220912_0003.PDF29 Sep 2022
Building plan approvalFile: MYSCAN_20220912_0001.PDF29 Sep 2022
Building plan approvalFile: MYSCAN_20220912_0004.PDF29 Sep 2022
Building plan approvalFile: MYSCAN_20220912_0005.PDF29 Sep 2022
Copy of Layout Approval (in case of layout)File: MYSCAN_20220912_0003.PDF29 Sep 2022
Building Plan Approval (IOD)File: MYSCAN_20220912_0001.PDF29 Sep 2022
Building Plan Approval (IOD)File: MYSCAN_20220912_0004.PDF29 Sep 2022
Building Plan Approval (IOD)File: MYSCAN_20220912_0005.PDF29 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf29 Sep 2022
Certificates of CA (Form 3)File: FORM-3.PDF29 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.PDF29 Aug 2022
Declaration about Commencement CertificateFile: form d.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: MAHAVIR DEVELOPERS FORM 2A MARCH 20.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: MAHAVIR DEVELOPERS FORM 2A MARCH 21.pdf27 Jul 2021
Disclosure of sold/ booked inventoryFile: MAHAVIR DEVELOPERS DISCLOSURE OF SOLD-BOOKED INVENTORY.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: MAHAVIR DEVELOPERS FORM 5.pdf27 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.PDF28 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT CERTIFICATE.PDF28 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ENGINEER CERTIFICATE.PDF28 Feb 2020
Certificates of CA (Form 3)File: Form 3 CA Certificate.PDF28 Feb 2020
Certificates of CA (Form 3)File: Form 3 C A CERTIFICATE.PDF28 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form - 5.PDF28 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.PDF28 Feb 2020
Proforma of Allotment letterFile: Agrrement for sale.pdf13 Nov 2017
Building plan approvalFile: 1st BLD DRW.pdf30 Jul 2017
Layout approvalFile: Layout.pdf30 Jul 2017
PAN CardFile: Pancard.pdf30 Jul 2017
Copy of the legal title reportFile: search report.pdf30 Jul 2017
Details of encumbrancesFile: Encumbrances 1.pdf30 Jul 2017
Details of encumbrancesFile: Encumbrances 2.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf30 Jul 2017
Building Plan Approval (IOD)File: 1st BLD DRW.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf30 Jul 2017
Declaration in FORM BFile: form B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf30 Jul 2017
Certificates of CA (Form 3)File: FORM 3.pdf30 Jul 2017
Proforma of Allotment letterFile: Sale Agreement Not Ready Request.pdf30 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 93 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GAURAV HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

Builder: MAHAVIR DEVELOPERS

MAHAVIR DEVELOPERS has 8 registrations on MahaRERA, including GAURAV HEIGHTS and MAHAVIR GARDEN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if GAURAV HEIGHTS is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAURAV HEIGHTS?

The registered promoter entity is MAHAVIR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAURAV HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GAURAV HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GAURAV HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAURAV HEIGHTS?

The professionals named in the filing: Architect: SHREE CONSULTANT; Engineer: MOHD SUFIYAN SHAIKH; Chartered Accountant: ASHWIN NAIR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAURAV HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAURAV HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAURAV HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.