Home / Browse projects / Mumbai Suburban, Maharashtra / GARUDA SHATRUNJAY
GARUDA SHATRUNJAY
By MESSERS SHREE UMIYA BUILDERS & DEVELOPERS
RG-MH-35850 · RERA P51800011329 · Last updated on MahaRERA portal: 19 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 20 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GARUDA SHATRUNJAY is a Others project by MESSERS SHREE UMIYA BUILDERS & DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011329 on 31 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing. 33 of the 180 units on this registration are recorded sold or booked, and 16 of 33 construction stages are filed complete. 20 complaints are on record with the regulator.
At a glance
Project
- NameGARUDA SHATRUNJAY
- TypeOthers
- Location
- RAM BAUG LANE
- BORVALI
- Borivali
- Mumbai Suburban
- 400092
- Pincode400092
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800011329
- ReraGenie IDRG-MH-35850
Builder
- NameMESSERS SHREE UMIYA BUILDERS & DEVELOPERS
- Entity typePartnership
- PartnersCHAGGAN KANJI POKAR, RAVILAL JETHA PATEL, JETHA RAJA PATEL, RAJESHKUMAR VALLABHDAR JOTANGIA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 25 Dec 2024)
- Buildings3 building records
- Documents filed180 files
Current status
Figures as on 19 May 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| REHAB BUILDING | NA | 24 | 24 | 0 | 0 | 0 |
| GARUDA SHATRUNJAY | NA | 44 | 34 | 180 | 0 | 180 |
| RESERVATION BUILDING | NA | 9 | 3 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 19 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 24%.
REHAB BUILDING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GARUDA SHATRUNJAY100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
RESERVATION BUILDING48%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 24% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities20
As on 19 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 30% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| PUMP ROOM | Yes | 0% |
| FITNESS AREA | Yes | 0% |
| ENTRANCE LOBBY | Yes | 0% |
| DG SETS | Yes | 0% |
| BMS ROOM | Yes | 0% |
Parking filed118
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCVISHAN INFRATECH LIMITED |
| Engineer | SURA AND ASSOCIATES |
| Chartered Accountant | NEHALI & CO |
| Partner | Role in project |
|---|---|
| MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReason for Extension of our project name Garuda Shatrunjay located at Village Magathane & Poisur, Taluka Borivali & Goregaon District Mumbai PIN: 400092 admeasuring 4390.30 sq. mts. bearing MahaRERA Registration No. PS1800011329, is due to Covid Pandemic, short of labour, short of material and Government Approvals, etc. Issues related to contractor management have also played a critical role in the delays. Problems include miscommunication among subcontractors, inadequate project oversight, and a lack of adherence to schedules. We recognize that these management challenges have resulted in Ine
Complaints filed with MahaRERA20
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000251404 | Vinod Ravji Karani | M/s Shree Umiya Builders & Developers | 09/06/2022 |
| CC12401147 | Kiran Balkrishna Valanger | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 17/12/2024 |
| CC12500975 | Ravilal Maru | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 20/03/2025 |
| CC12501098 | Neena Rajesh Parekh | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 01/04/2025 |
| CC12501096 | Trupti Zaveri | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 01/04/2025 |
| CC12501097 | Himanshu Shah | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 01/04/2025 |
| CC12501248 | Alka Sanjay Hemady | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 15/04/2025 |
| CC12504145 | Kirit Magia | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 24/11/2025 |
| CC12504149 | Amit Magia | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 24/11/2025 |
| CC12600813 | Alok Harish Shastri | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 13/02/2026 |
| CC12600833 | Priyank Ramesh Jain | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 14/02/2026 |
| CC12601397 | Rohit Vijaykumar Sangoi | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 13/03/2026 |
| CC12602764 | Riddhi Nikesh Doshi | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 12/05/2026 |
| CC12601829 | DHRUPAL DEEPAK SHAH | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 28/03/2026 |
| CC12602372 | Anish Shantilal Chheda | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 22/04/2026 |
| CC12602781 | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | Sonal Satish Mehta | 13/05/2026 |
| CC12602863 | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | Riddhi Nikesh Doshi | 16/05/2026 |
| CC12603764 | Shilpa Sharad Vani | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 18/06/2026 |
| CC12604328 | Monish Girish Gala | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 10/07/2026 |
| CC12604329 | Anand Ghevarchand Gurlia | MESSERS SHREE UMIYA BUILDERS & DEVELOPERS | 10/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed180
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 180 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 2025.pdf | 19 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 1.pdf | 18 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 2.pdf | 18 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 3.pdf | 18 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory disclosure revised.pdf | 11 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 09 24.pdf | 9 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 03 24.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf | 4 Jan 2025 |
| Declaration in FORM BFile: Form B - Notarized (1).pdf | 30 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf | 30 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Rehab Bldg 1-JUNE 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Reserve Bldg 2-JUNE 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Sale Bldg 3-JUNE 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Rehab Bldg 1-SEPT 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Reserve Bldg 2-SEPT 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Sale Bldg 3-SEPT 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Rehab Bldg 1-DEC 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Reserve Bldg 2-DEC 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Sale Bldg 3-DEC 2022.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 1.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 2.pdf | 13 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 3.pdf | 13 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 24 Bldg 1.pdf | 13 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 24 Bldg 2.pdf | 13 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 24 Bldg 3.pdf | 13 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Final FY 22-23.pdf | 13 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Final FY 23-24.pdf | 13 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 24 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 23 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 23 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 23 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 23 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 24 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 24 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 24 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 24 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 24 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 22 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 22 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 22 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 22 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 22 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 1.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 3.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 2.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 22 Bldg 1.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A jan to march 22-23.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A oct to dec 22-23.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A jan to march 23-24.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A april to june 23-24.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A july to sep 23-24.pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A oct to dec 23-24.pdf | 12 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 24 Bldg 3.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 jan to march 23 - Bldg 1.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 1.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 2.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 3.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -july to sep 23 Bldg 3.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 24 Bldg 2.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 jan to march 23 Bldg 2.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 jan to march 23 Bldg 3.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 23 Bldg 1.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 23 Bldg 2.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 april to june 23 bldg 3.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 23 Bldg 1.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 23 Bldg 2.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 oct to dec 23 Bldg 1.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - oct to dec 23 Bldg 2.pdf | 11 Dec 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 180 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GARUDA SHATRUNJAY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BORVALI6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 57 registered projects within 2 km.
Hiranandani Bluecrest
SHODEN DEVELOPERS PRIVATE LIMITED
KANAKIA PRIVAASA TOWER 1 & 2
KANAKIA TRANSPARENT DEVELOPERS PRIVATE LIM
BHOOMI AIRAVAT
Bhoomi Shashwat Estate Private limited
Shraddha Paradise
Shraddha Prime Projects Limited
UNIQUE REGALIA
UNIQUE SHANTI DEVELOPERS LLP
NICCO VANASHRI AND NICCO HEIGHTS
NEW INDIA CONSTRUCTION COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: MESSERS SHREE UMIYA BUILDERS & DEVELOPERS
MESSERS SHREE UMIYA BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including GARUDA SHATRUNJAY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that GARUDA SHATRUNJAY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GARUDA SHATRUNJAY is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GARUDA SHATRUNJAY?
The registered promoter entity is MESSERS SHREE UMIYA BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GARUDA SHATRUNJAY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GARUDA SHATRUNJAY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GARUDA SHATRUNJAY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GARUDA SHATRUNJAY?
The professionals named in the filing: Architect: ARCVISHAN INFRATECH LIMITED; Engineer: SURA AND ASSOCIATES; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GARUDA SHATRUNJAY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback