ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / GARUDA SHATRUNJAY

Registration lapsed No litigation declared Others project

GARUDA SHATRUNJAY

By MESSERS SHREE UMIYA BUILDERS & DEVELOPERS

RG-MH-35850 · RERA P51800011329 · Last updated on MahaRERA portal: 19 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 20 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
16 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 24%
147 of 180Units unsoldnot recorded sold or booked
20Complaints at MahaRERAon this registration
Jump to the 180 documents Report an error

GARUDA SHATRUNJAY is a Others project by MESSERS SHREE UMIYA BUILDERS & DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011329 on 31 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing. 33 of the 180 units on this registration are recorded sold or booked, and 16 of 33 construction stages are filed complete. 20 complaints are on record with the regulator.

At a glance

Project

  • NameGARUDA SHATRUNJAY
  • TypeOthers
  • Location
    • RAM BAUG LANE
    • BORVALI
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011329
  • ReraGenie IDRG-MH-35850

Builder

  • NameMESSERS SHREE UMIYA BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnersCHAGGAN KANJI POKAR, RAVILAL JETHA PATEL, JETHA RAJA PATEL, RAJESHKUMAR VALLABHDAR JOTANGIA

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseDec 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 25 Dec 2024)
  • Buildings3 building records
  • Documents filed180 files

Current status

18%33 of 180 units booked

Figures as on 19 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
REHAB BUILDINGNA2424000
GARUDA SHATRUNJAYNA44341800180
RESERVATION BUILDINGNA93000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 19 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 24%.

REHAB BUILDING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GARUDA SHATRUNJAY100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RESERVATION BUILDING48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure24%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities20

As on 19 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes30%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
PUMP ROOMYes0%
FITNESS AREAYes0%
ENTRANCE LOBBYYes0%
DG SETSYes0%
BMS ROOMYes0%

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered118

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,390 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jun 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI23901.71
Proposed, not sanctioned14,156 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCOMMERCIAL BRANCH BN AGARWAL MARKET SHYAMKAMAL TRADE CENTRE,VILE PARLE EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCVISHAN INFRATECH LIMITED
EngineerSURA AND ASSOCIATES
Chartered AccountantNEHALI & CO
PartnerRole in project
MESSERS SHREE UMIYA BUILDERS & DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025657Dec 2024 → Jun 2026

Reason as filed by the promoterReason for Extension of our project name Garuda Shatrunjay located at Village Magathane & Poisur, Taluka Borivali & Goregaon District Mumbai PIN: 400092 admeasuring 4390.30 sq. mts. bearing MahaRERA Registration No. PS1800011329, is due to Covid Pandemic, short of labour, short of material and Government Approvals, etc. Issues related to contractor management have also played a critical role in the delays. Problems include miscommunication among subcontractors, inadequate project oversight, and a lack of adherence to schedules. We recognize that these management challenges have resulted in Ine

Complaints filed with MahaRERA20

Case no.ComplainantRespondentFiled
CC006000000251404Vinod Ravji KaraniM/s Shree Umiya Builders & Developers09/06/2022
CC12401147Kiran Balkrishna ValangerMESSERS SHREE UMIYA BUILDERS & DEVELOPERS17/12/2024
CC12500975Ravilal MaruMESSERS SHREE UMIYA BUILDERS & DEVELOPERS20/03/2025
CC12501098Neena Rajesh ParekhMESSERS SHREE UMIYA BUILDERS & DEVELOPERS01/04/2025
CC12501096Trupti ZaveriMESSERS SHREE UMIYA BUILDERS & DEVELOPERS01/04/2025
CC12501097Himanshu ShahMESSERS SHREE UMIYA BUILDERS & DEVELOPERS01/04/2025
CC12501248Alka Sanjay HemadyMESSERS SHREE UMIYA BUILDERS & DEVELOPERS15/04/2025
CC12504145Kirit MagiaMESSERS SHREE UMIYA BUILDERS & DEVELOPERS24/11/2025
CC12504149Amit MagiaMESSERS SHREE UMIYA BUILDERS & DEVELOPERS24/11/2025
CC12600813Alok Harish ShastriMESSERS SHREE UMIYA BUILDERS & DEVELOPERS13/02/2026
CC12600833Priyank Ramesh JainMESSERS SHREE UMIYA BUILDERS & DEVELOPERS14/02/2026
CC12601397Rohit Vijaykumar SangoiMESSERS SHREE UMIYA BUILDERS & DEVELOPERS13/03/2026
CC12602764Riddhi Nikesh DoshiMESSERS SHREE UMIYA BUILDERS & DEVELOPERS12/05/2026
CC12601829DHRUPAL DEEPAK SHAHMESSERS SHREE UMIYA BUILDERS & DEVELOPERS28/03/2026
CC12602372Anish Shantilal ChhedaMESSERS SHREE UMIYA BUILDERS & DEVELOPERS22/04/2026
CC12602781MESSERS SHREE UMIYA BUILDERS & DEVELOPERSSonal Satish Mehta13/05/2026
CC12602863MESSERS SHREE UMIYA BUILDERS & DEVELOPERSRiddhi Nikesh Doshi16/05/2026
CC12603764Shilpa Sharad VaniMESSERS SHREE UMIYA BUILDERS & DEVELOPERS18/06/2026
CC12604328Monish Girish GalaMESSERS SHREE UMIYA BUILDERS & DEVELOPERS10/07/2026
CC12604329Anand Ghevarchand GurliaMESSERS SHREE UMIYA BUILDERS & DEVELOPERS10/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed180

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 180 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 2025.pdf19 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 1.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 2.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Bldg 3.pdf18 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventory disclosure revised.pdf11 Jan 2025
Certificates of CA (Form 3)File: form 3 09 24.pdf9 Jan 2025
Certificates of CA (Form 3)File: form 3 03 24.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf4 Jan 2025
Declaration in FORM BFile: Form B - Notarized (1).pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf30 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Rehab Bldg 1-JUNE 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Reserve Bldg 2-JUNE 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Sale Bldg 3-JUNE 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Rehab Bldg 1-SEPT 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Reserve Bldg 2-SEPT 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Sale Bldg 3-SEPT 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Rehab Bldg 1-DEC 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Reserve Bldg 2-DEC 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 - Sale Bldg 3-DEC 2022.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 1.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 2.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 3.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 24 Bldg 1.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 24 Bldg 2.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 24 Bldg 3.pdf13 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Final FY 22-23.pdf13 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Final FY 23-24.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 24 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 23 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 23 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 23 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 23 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 24 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 24 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 24 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 24 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 24 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 22 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 22 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 july to sep 22 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 22 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 22 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 1.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 jan to march 23 Bldg 3.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 april to june 23 Bldg 2.pdf12 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct to dec 22 Bldg 1.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A jan to march 22-23.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A oct to dec 22-23.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A jan to march 23-24.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A april to june 23-24.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A july to sep 23-24.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A oct to dec 23-24.pdf12 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 24 Bldg 3.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 jan to march 23 - Bldg 1.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 1.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 2.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 24 Bldg 3.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -july to sep 23 Bldg 3.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 24 Bldg 2.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 jan to march 23 Bldg 2.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 jan to march 23 Bldg 3.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 23 Bldg 1.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 april to june 23 Bldg 2.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 april to june 23 bldg 3.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 23 Bldg 1.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 july to sep 23 Bldg 2.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 oct to dec 23 Bldg 1.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - oct to dec 23 Bldg 2.pdf11 Dec 2024

How this compares with Mumbai Suburban

18%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GARUDA SHATRUNJAY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORVALI6,700+ in Mumbai Suburban

2 kmGARUDA SHATRUNJAYCompleted 33Lapsed / revoked 18Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: MESSERS SHREE UMIYA BUILDERS & DEVELOPERS

MESSERS SHREE UMIYA BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including GARUDA SHATRUNJAY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that GARUDA SHATRUNJAY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GARUDA SHATRUNJAY is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GARUDA SHATRUNJAY?

The registered promoter entity is MESSERS SHREE UMIYA BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GARUDA SHATRUNJAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GARUDA SHATRUNJAY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GARUDA SHATRUNJAY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GARUDA SHATRUNJAY?

The professionals named in the filing: Architect: ARCVISHAN INFRATECH LIMITED; Engineer: SURA AND ASSOCIATES; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GARUDA SHATRUNJAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GARUDA SHATRUNJAY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GARUDA SHATRUNJAY to a free account