ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / GARDEN VIEW

Completed No litigation declared Residential / Group Housing project

GARDEN VIEW

By AJIT SURESH BANE

RG-MH-00521 · RERA P51600000880 · Last updated on MahaRERA portal: 21 Nov 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Nov 2020Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

GARDEN VIEW is a Residential / Group Housing project by AJIT SURESH BANE in Nashik, Maharashtra, registered with MahaRERA as P51600000880 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Nov 2020.

At a glance

Project

  • NameGARDEN VIEW
  • TypeResidential / Group Housing
  • Location
    • Shiv Road
    • Panchak
    • Jail Road
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600000880
  • ReraGenie IDRG-MH-00521

Builder

  • NameAJIT SURESH BANE
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017PromisedNov 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Nov 2020
  • Revised completionNone
  • Buildings2 building records
  • Documents filed41 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
FIRST BUILDINGNA90000
SECOND BUILDINGNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

FIRST BUILDING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SECOND BUILDING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Open Space20
BuildingOpen SpaceTotal
FIRST BUILDING1414
SECOND BUILDING66

Land and ownership5

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
LandownerVillageDistrict
RAJENDRA EKNATH BORADEJail RoadNashik
MRS. SATYABHAMA MADHAV BORADEJail RoadNashik
SANTOSH MADHAV BORADEJail RoadNashik
DASHRATH MADHAV BORADEJail RoadNashik
SIDDHESHWAR MADHAV BORADEJail RoadNashik

Approvals and building plan

Permissible FSI3922.67
Proposed, not sanctioned3,923 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNASHIK ROAD, NASHIK

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDATTATRAY RAMRAO GADE
EngineerDILIP NAMDEO GADAKH
PartnerRole in project
AJIT SURESH BANE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Dec 2020

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: audit_report20-21.pdf21 Nov 2021
Status of ConveyanceFile: DECLARATION.pdf21 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FROM 5 19-20.pdf19 Feb 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: DECLARATION.pdf19 Feb 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf25 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5_18-19.pdf23 Jan 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion.pdf15 Dec 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf29 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_18-07-2020.pdf28 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_18-07-2020.pdf28 Jul 2020
Certificates of CA (Form 3)File: Form 3.pdf28 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf15 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf15 Oct 2018
Certificates of CA (Form 3)File: FORM 3.pdf15 Oct 2018
Certificates of CA (Form 5)File: FORM 5.pdf15 Oct 2018
Building plan approvalFile: Building Approval 2.pdf19 Jan 2018
Building Plan Approval (IOD)File: Building Approval 2.pdf19 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf19 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf19 Jan 2018
Certificates of CA (Form 3)File: Chartered Accountants Certificate.pdf19 Jan 2018
Certificates of CA (Form 3)File: Annexure A.pdf19 Jan 2018
Building plan approvalFile: Building Apporal.pdf18 Jan 2018
Building Plan Approval (IOD)File: Building Apporal.pdf18 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf18 Jan 2018
Declaration in FORM BFile: Form-B.pdf18 Jan 2018
Building plan approvalFile: MYSCAN_20170720_0004[1].pdf20 Jul 2017
Building plan approvalFile: MYSCAN_20170720_0007[1].pdf20 Jul 2017
Layout approvalFile: LAYOUT AND APPROVAL_Compressed.pdf20 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT AND APPROVAL_Compressed.pdf20 Jul 2017
Building Plan Approval (IOD)File: MYSCAN_20170720_0004[1].pdf20 Jul 2017
Building Plan Approval (IOD)File: MYSCAN_20170720_0007[1].pdf20 Jul 2017
Proforma of Allotment letterFile: Specimen Draft of Allottment Letter.pdf20 Jul 2017
Certificates of CA (Form 3)File: FORM 3 _Compressed.pdf14 Jul 2017
Proforma of Allotment letterFile: sale proforma com.pdf14 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE_Compressed.pdf12 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE_Compressed.pdf12 Jul 2017
PAN CardFile: PAN.pdf4 Jul 2017
Copy of the legal title reportFile: TITLE REPORT_Compressed.pdf4 Jul 2017
Details of encumbrancesFile: NO ENCUMBRANCE CERTIFICATE_Compressed.pdf4 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: NMC COMMENCEMENT CERTIFICATE_Compressed.pdf4 Jul 2017
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION _Compressed.pdf4 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHREE KASHISHWAR APPARTMENTS NO 14 4C 1 SHIV ROAD NEAR RAJRAJESHWARI MANGAL KARYALAY DASAK NASHIK31CompletedMar 2013Mar 2013

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GARDEN VIEW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Panchak4,100+ in Nashik

2 kmGARDEN VIEWCompleted 10Lapsed / revoked 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: AJIT SURESH BANE

AJIT SURESH BANE has 1 registration on MahaRERA, including GARDEN VIEW. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if GARDEN VIEW is delayed beyond 30 Nov 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GARDEN VIEW?

The registered promoter entity is AJIT SURESH BANE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GARDEN VIEW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GARDEN VIEW?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GARDEN VIEW?

The professionals named in the filing: Architect: DATTATRAY RAMRAO GADE; Engineer: DILIP NAMDEO GADAKH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GARDEN VIEW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GARDEN VIEW. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GARDEN VIEW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.