GANGOTRI RESIDENCES

By Asset Realty

RG-MH-17011 · RERA P52100027597 · Last updated on MahaRERA portal: 20 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

GANGOTRI RESIDENCES is a Residential / Group Housing project by Asset Realty in Pune, Maharashtra, registered with MahaRERA as P52100027597 on 20 Dec 2020. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameGANGOTRI RESIDENCES
  • TypeResidential / Group Housing
  • Location
    • SKYWAYS SERENO ROAD
    • LOHAGAON
    • Lahagaon
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027597
  • ReraGenie IDRG-MH-17011

Builder

  • NameAsset Realty
  • Entity typePartnership
  • PartnersRISHIKESH LAXMAN BHOSALE, PAWANDEEP GURDIYALSINGH GHUMAN

Key dates

22 months past promisethis monthRegisteredDec 2020First promiseDec 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Dec 2020
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GANGOTRI RESIDENCESNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

GANGOTRI RESIDENCES: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area800 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MR NAVNATH GANPATH DHOTRELOHGAONPune

Approvals and building plan

Permissible FSI655.43
Proposed, not sanctioned655 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHOSARI PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATIT ADMULWAR
EngineerK P BADGUJAR CONSULTANT PVT LTD
Chartered AccountantM s RINKESH GUPTA AND ASSOCIATES
PartnerRole in project
Asset Realty-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018791Dec 2022 → Dec 2024

Reason as filed by the promoterDue to Completion Certificate from planning Authority.

EXT52100013435Dec 2022 → Dec 2023

Reason as filed by the promoterDue to Revise Sanction Update

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf20 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf20 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (3).pdf20 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (1).pdf20 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (2).pdf20 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (3).pdf20 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (4).pdf20 May 2025
Layout approvalFile: plan 01-02_compressed.pdf6 Jul 2024
Building plan approvalFile: plan 02-02_compressed.pdf6 Jul 2024
Copy of Layout Approval (in case of layout)File: plan 01-02_compressed.pdf6 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: plan 02-02_compressed.pdf6 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: cc (1).pdf6 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold- Asset.pdf9 Feb 2024
Declaration in FORM BFile: Affidavit - Asset.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aset Reality-1-3 (1).pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate - Asset Realty.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Asset Form-5.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 April.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate - Asset Realty.pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf21 Oct 2023
Disclosure of sold/ booked inventoryFile: 1 Disclosure of sold_ booked inventory (1).pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Asset Realty (1).pdf21 Oct 2023
Declaration about Commencement CertificateFile: Scan20230222125704.pdf22 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf22 Feb 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 (3).pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate - Asset Realty.pdf19 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Scan Copy_compressed.pdf15 Dec 2020
Proforma of Allotment letterFile: Agreement to sale.pdf15 Dec 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 GANGOTRI RESIDENCY.pdf11 Dec 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Asset Realty.pdf11 Dec 2020
Copy of the legal title reportFile: Partnership Deed.pdf9 Dec 2020
Declaration in FORM BFile: Form B Declaration_compressed.pdf9 Dec 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 compressed.pdf9 Dec 2020
Proforma of Allotment letterFile: Allotment Letter.pdf9 Dec 2020
Layout approvalFile: Layout plan.pdf8 Dec 2020
Building plan approvalFile: Sanction Copy 2_compressed.pdf8 Dec 2020
PAN CardFile: Pan Card Asset Realty.pdf8 Dec 2020
Copy of the legal title reportFile: Search Title Report new.pdf8 Dec 2020
Details of encumbrancesFile: Encumbramces.pdf8 Dec 2020
Copy of Layout Approval (in case of layout)File: Layout plan.pdf8 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanction Copy 2_compressed.pdf8 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed (1).pdf8 Dec 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANGOTRI RESIDENCES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near LOHAGAON13,700+ in Pune

2 kmGANGOTRI RESIDENCESCompleted 60Lapsed / revoked 17Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 115 registered projects within 2 km.

Builder: Asset Realty

Asset Realty has 1 registration on MahaRERA, including GANGOTRI RESIDENCES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that GANGOTRI RESIDENCES shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GANGOTRI RESIDENCES is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANGOTRI RESIDENCES?

The registered promoter entity is Asset Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANGOTRI RESIDENCES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANGOTRI RESIDENCES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANGOTRI RESIDENCES?

The professionals named in the filing: Architect: ATIT ADMULWAR; Engineer: K P BADGUJAR CONSULTANT PVT LTD; Chartered Accountant: M s RINKESH GUPTA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANGOTRI RESIDENCES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANGOTRI RESIDENCES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANGOTRI RESIDENCES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.