Home / Browse projects / Raigarh, Maharashtra / GAMI TEESTA
GAMI TEESTA
RG-MH-27853 · RERA P52000024267 · Last updated on MahaRERA portal: 17 Jul 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GAMI TEESTA is a Others project by MURJI BHANJI GAMI in Raigarh, Maharashtra, registered with MahaRERA as P52000024267 on 30 Jan 2020. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 6 months from the original filing. 212 of the 221 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.
At a glance
Project
- NameGAMI TEESTA
- TypeOthers
- Location
- 81/1
- 82/1
- 82/2
- 82/5
- PISARVE GAON
- Pisarve
- Panvel
- Raigarh
- 410208
- Pincode410208
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000024267
- ReraGenie IDRG-MH-27853
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on30 Jan 2020
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 30 Jun 2023)
- Buildings2 building records
- Documents filed52 files
Current status
Figures as on 17 Jul 2024, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 9 | 8 | 74 | 4 | 78 |
| WING B | NA | 10 | 9 | 143 | 0 | 143 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 17 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
WING A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 1 | 1 |
| WING B | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESTINATION ARCHITECTS INTERIOR DESIGNS |
| Engineer | S R ESTIMATION |
| Engineer | Million Jobs Private Limited |
| Chartered Accountant | DSSM & CO LLP |
| Chartered Accountant | Nehali & Co |
| Partner | Role in project |
|---|---|
| MURJI BHANJI GAMI | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 6 MONTHS
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Sep 2023
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 gami teesta.pdf | 17 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Engineer Certificate.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT __GAMI TEESTA_09-10-2023.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate Gami TEESTA sep'23.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SIgned Form 5 22-23 Teesta AB.pdf | 30 Sep 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: O C PISARVE GAMI TEESTA.pdf | 7 Sep 2023 |
| Declaration in FORM BFile: FORM B GAMI TEESTA.pdf | 5 Aug 2023 |
| Declaration about Commencement CertificateFile: CC COVERING LETTER (3) (1).pdf | 11 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer FORM 2A fy before 2020.pdf | 10 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer FORM 2A fy before 2021.pdf | 10 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer form 2A new 2022.pdf | 10 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer form 2A new 2023.pdf | 10 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Bank details letter rera.pdf | 10 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 8 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 8 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 8 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf | 29 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 03-04-2020.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 01-04-2021.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 07- 07-2022.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 07-10-2022.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 09-01-2023.pdf | 18 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC2 Engineers Certificate__GAMI TEESTA 10-04-2021.pdf | 18 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC5 Engineers Certificate__GAMI TEESTA_11-04-2022.pdf | 18 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC7 Engineers Certificate__GAMI TEESTA_31-10-2022.pdf | 18 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC8 Engineers Certificate__GAMI TEESTA 20-01-2023.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 14 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 14 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 14 Feb 2023 |
| Details of encumbrancesFile: encumbrance fianancial.pdf | 10 Feb 2023 |
| CERSAI detailsFile: 1 CERSAI details.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Gami Teesta From 05.pdf | 10 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK LETTER GAMI-2.pdf | 30 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Gami TEESTA Sept'22.pdf | 28 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate GAMI TEESTA.pdf | 26 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1 TEESTA.pdf | 13 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate__GAMI TEESTA_DEC 2021.pdf | 3 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate__GAMI TEESTA_DEC 2021.pdf | 3 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pisarve.pdf | 2 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate form 1.pdf | 15 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 15 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate form 5 19-20.pdf | 15 Sep 2021 |
| Layout approvalFile: PLOT LAY OUT PLAN.pdf | 24 Jan 2020 |
| Building plan approvalFile: PISARVE C C.pdf | 24 Jan 2020 |
| Copy of the legal title reportFile: Title Certificate.pdf | 24 Jan 2020 |
| Details of encumbrancesFile: Form B Declaration.pdf | 24 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: PLOT LAY OUT PLAN.pdf | 24 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: PISARVE C C.pdf | 24 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: PISARVE C C.pdf | 24 Jan 2020 |
| Declaration in FORM BFile: Form B Declaration.pdf | 24 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 24 Jan 2020 |
| Proforma of Allotment letterFile: Agreement Draft.pdf | 24 Jan 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| GAMI TRIXIE | SECTOR 20 ULWE | 173 | Completed | Dec 2018 | Oct 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 52 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GAMI TEESTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PISARVE GAON5,900+ in Raigarh
Filed coordinates, straight-line distance. 108 registered projects within 2 km.
Plot No -1 Sector -29 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
Plot No.-1 Sector -39 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
Plot No -1 Sector -31 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
SAI SUNCITY PHASE II
Chariot Properties LLP
Plot No. 14 Sector-37 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
ARIHANT ADARSH PHASE I
ARIHANT SUPERSTRUCTURES LIMITED
See every Raigarh project, with the district possession charts
Builder: MURJI BHANJI GAMI
MURJI BHANJI GAMI has 5 registrations on MahaRERA, including GAMI TRIXIE and GAMI TEESTA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that GAMI TEESTA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GAMI TEESTA is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GAMI TEESTA?
The registered promoter entity is MURJI BHANJI GAMI, an individual as per the filing. Its GSTIN 27AAOPP8909K1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GAMI TEESTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GAMI TEESTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GAMI TEESTA?
The professionals named in the filing: Architect: DESTINATION ARCHITECTS INTERIOR DESIGNS; Engineer: S R ESTIMATION; Engineer: Million Jobs Private Limited; Chartered Accountant: DSSM & CO LLP; Chartered Accountant: Nehali & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GAMI TEESTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback