Home / Browse projects / Thane, Maharashtra / Gami Avant
Gami Avant
By LAL GEBI INFRA PRIVATE LIMITED
RG-MH-31405 · RERA P51700079740 · Last updated on MahaRERA portal: 15 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Rs 100.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LTD
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gami Avant is a Others project by LAL GEBI INFRA PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700079740 on 24 Mar 2025. Possession is promised by 31 Dec 2029. 20 of the 232 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.
At a glance
Project
- NameGami Avant
- TypeOthers
- Location
- Sector No 18
- Vashi
- Navi Mumbai
- Navi Mumbai (M Corp.)
- Thane
- 400703
- Pincode400703
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700079740
- ReraGenie IDRG-MH-31405
Builder
- NameLAL GEBI INFRA PRIVATE LIMITED
- Entity typeCompany
- CINU45309MH2020PTC345469
- GSTIN27AAECL3308B1Z0
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsAMBALA GAMI, AMBALAL GAMI, AMBALAL GAMI
- Other registrations6 more →
- Completed2 of 7
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Mar 2025
- Promised completion31 Dec 2029
- Revised completionNone
- Buildings2 building records
- Documents filed49 files
Current status
Figures as on 15 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LAL GEBI INFRA PVT LTD WING A | NA | 31 | 18 | 93 | 22 | 115 |
| LAL GEBI INFRA PVT LTD WING B | NA | 31 | 15 | 117 | 0 | 117 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 90%.
LAL GEBI INFRA PVT LTD WING A35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 90% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 12% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LAL GEBI INFRA PVT LTD WING B33%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 80% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 4% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed578
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| LAL GEBI INFRA PVT LTD WING A | 134 | 156 | 290 |
| LAL GEBI INFRA PVT LTD WING B | 133 | 155 | 288 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| LAL GEBI INFRA PVT LTD WING B | NA | Rs 45.85 cr | Rs 6.92 cr |
| LAL GEBI INFRA PVT LTD WING A | NA | Rs 33.12 cr | Rs 5.00 cr |
| - | NA | Rs 1.61 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Dimensions Architects Pvt Ltd |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | NB Sayed & Associates |
| Partner | Role in project |
|---|---|
| LAL GEBI INFRA PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Feb 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Feb 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed49
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Gami Avant as on 31-03-2026.pdf | 15 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Gami Avant as on Dec 2025.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Gami Avant as on 31-03-2026.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Gami Avant as on 31-03-2026.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Gami Avant as on 31-03-2026.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Gami Avant as on Dec 2025.pdf | 15 Apr 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Gami Avant for FY 2024-25.pdf | 2 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 - Gami Avant as on Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - Gami Avant as on Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - Gami Avant as on Sep 2025.pdf | 17 Oct 2025 |
| Form 1File: Form 1 - Gami Avant as on June 2025.pdf | 28 Jul 2025 |
| Form 2File: Form 2 - Gami Avant as on June 2025.pdf | 28 Jul 2025 |
| Form 3File: Form 3 - Gami Avant as on June 2025.pdf | 28 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Gami Avant as on June 2025.pdf | 28 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Gami Avant as on March 2025.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Gami Avant as on 31-03-2025.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Gami Avant as on March 2025.pdf | 20 Apr 2025 |
| Building plan approvalFile: Plan-10_compressed.pdf | 1 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan-10_compressed.pdf | 1 Mar 2025 |
| Other - TechnicalFile: CC Verification (8).pdf | 28 Feb 2025 |
| Copy of the legal title reportFile: Title Certificate_Gami Avant_Lal Gebi Infra Private Limited_20022025_compressed (1).pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: First Form 3 - Gami Avant R3 (2).pdf | 24 Feb 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation_AL_Gami Avant_Lal Gebi Infra Private Limited_19022025.pdf | 24 Feb 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation_AFS_Gami Avant_Lal Gebi Infra Private Limited_06032025_compressed.pdf | 24 Feb 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 24 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: ilovepdf_merged (59).pdf | 24 Feb 2025 |
| Proforma of Allotment letterFile: AL_Gami Avant_Lal Gebi Infra Private Limited_19022025.pdf | 20 Feb 2025 |
| Proforma of Agreement for saleFile: Reviewed_AFS_Gami Avant_Lal Gebi Infra Private Limited_06032025 (1) (1).pdf | 20 Feb 2025 |
| Declaration about Commencement CertificateFile: Format D - Declaration of Commencement Certificate (2) (2).pdf | 17 Feb 2025 |
| CERSAI detailsFile: ilovepdf_merged (32).pdf | 17 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance legal gami Avant.pdf | 15 Feb 2025 |
| Declaration in FORM BFile: FORM -B (Promoter) (1).pdf | 15 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance legal gami Avant.pdf | 15 Feb 2025 |
| Building plan approvalFile: Plan Commencement Certificate 07-02-2025-1-3_11zon.pdf | 11 Feb 2025 |
| Building plan approvalFile: Plan Commencement Certificate 07-02-2025-4-6_11zon.pdf | 11 Feb 2025 |
| Building plan approvalFile: Plan-7-8 (1)_11zon.pdf | 11 Feb 2025 |
| PAN CardFile: 1 PAN Card (7).pdf | 11 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Commencement Certificate 07-02-2025-1-3_11zon.pdf | 11 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Commencement Certificate 07-02-2025-4-6_11zon.pdf | 11 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan-7-8 (1)_11zon.pdf | 11 Feb 2025 |
| Other - LegalFile: AGREEMENT TO LEASE LAL GEBI MAFCO_compressed_11zon.pdf | 11 Feb 2025 |
| Layout approvalFile: Plan Commencement Certificate 07-02-2025-9_11zon.pdf | 10 Feb 2025 |
| Copy of Layout Approval (in case of layout)File: Plan Commencement Certificate 07-02-2025-9_11zon.pdf | 10 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate (CC) 07-02-2025.pdf | 10 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter -Dues.pdf | 4 Feb 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Gami Avant.pdf | 4 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance Letter -Dues.pdf | 4 Feb 2025 |
| Other - TechnicalFile: 1 Other - Technical (26) (1).pdf | 4 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexures Gami Avant.pdf | 4 Feb 2025 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Gami TelonP51700080035 | Ghansoli, Thane | 72 | Apr 2025 | Ongoing | Dec 2029 | Not due yet |
| Gami MiravaPR1270002600408 | New Panvel, Raigarh | 327 | May 2026 | Ongoing | Dec 2029 | Not due yet |
| Gami BiancaP52000051188 | Dronagiri, Navi Mumbai, Raigarh | 436 | Jun 2023 | Ongoing | Dec 2027 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 49 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Gami Avant on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vashi, Navi Mumbai7,600+ in Thane
Filed coordinates, straight-line distance. 66 registered projects within 2 km.
Plot No -1A,Sector -19, Vashi Truck Terminal
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
KAMDHENU SHARAYU
Arpee Consultants LLP
Kamdhenu Synergy Square
Krsna Dynasty
10 Marina Bay
EV HOMES CONSTRUCTIONS PVT LTD
Goodwill Bizhub
M/s. Goodwill Dwellings LLP
ARIHANT ALEENTA
ARIHANT ESTATES
See every Thane project, with the district possession charts
Builder: LAL GEBI INFRA PRIVATE LIMITED
LAL GEBI INFRA PRIVATE LIMITED has 7 registrations on MahaRERA, including GAMI JADE and Gami Terra. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Gami Avant is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gami Avant?
The registered promoter entity is LAL GEBI INFRA PRIVATE LIMITED, a company as per the filing. Its CIN U45309MH2020PTC345469 and GSTIN 27AAECL3308B1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gami Avant?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Gami Avant?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Gami Avant?
The professionals named in the filing: Architect: Dimensions Architects Pvt Ltd; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Gami Avant?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback