GALAXY PRAYAG
RG-MH-02078 · RERA P50500010247 · Last updated on MahaRERA portal: 15 Feb 2023
Source: official MahaRERA filing
Red flags
- Completion date moved by 48 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GALAXY PRAYAG is a Residential / Group Housing project by SHASHANK PANDE in Nagpur, Maharashtra, registered with MahaRERA as P50500010247 on 24 Aug 2017. The registration is recorded completed; possession was promised by 31 Mar 2023. The completion date has moved by 48 months from the original filing.
At a glance
Project
- NameGALAXY PRAYAG
- TypeResidential / Group Housing
- Location
- NAGPUR
- Nagpur (M Corp.)
- Nagpur (Urban)
- 440022
- Pincode440022
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500010247
- ReraGenie IDRG-MH-02078
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on24 Aug 2017
- Promised completion31 Mar 2023
- Revised completionRevised to 31 Mar 2023 (originally 31 Mar 2019)
- Buildings1 building record
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GALAXY PRAYAG | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.
GALAXY PRAYAG: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 15 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NALINI SATISHCHANDRA BUTE | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIKAS PADOLE |
| Engineer | VIKAS PADOLE |
| Partner | Role in project |
|---|---|
| SHASHANK PANDE | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterHIGH COURT HAS PUT STAY PERIOD ON THE PROJECT DUE TO SOME LITIGATION MATTER THUS PROMOTER CAN NOT COMPLETE PROJECT WITHIN THE DUE PERIOD SPECIFIED AT THE TIME OF REGISTRATION . NOW LITIGATION HAS ENDED IN MY FAVOUR & I HAVE RESTARTED THE PROJECT. I REQUEST YOU TO EXTEND TIME PERIOD FOR COMPLETION OF MY PROJECT “GALAXY PRAYAG” BY 18 MONTHS.
Reason as filed by the promoterHIGH COURT HAD PUT STAY ORDER ON PROJECT NOW ALL LEGAL DISPUTE WERE RESOLVED & I HAVE OBTAINED ALL NECESSARY PERMISSION FROM RESPECTIVE AUTHORITY. PLEASE ALLOW ME EXTENDED TIME PERIOD FOR PROJECT COMPLETION.
Reason as filed by the promoterapplication for completion submitted awaited from competent authority
Reason as filed by the promoterThe building is complete and architect certificate is also issued. The application to Nagpur Municipal corporation is also fined for issue of completion certificate. The application for Airport NOC is also made. The approvals are pending from the authority
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Feb 2023
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE.pdf | 15 Feb 2023 |
| Certificates of CA (Form 3)File: prayag march ca cert28122022_compressed.pdf | 30 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL REPORT ON STATEMENT OF ACCOUNT (1).pdf | 28 Dec 2022 |
| Declaration about Commencement CertificateFile: commecement certificate.pdf | 22 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EGINEERS.pdf | 22 Dec 2022 |
| Layout approvalFile: MAP2_compressed 1F.pdf | 20 Feb 2022 |
| Layout approvalFile: MAP1_compresseD F2.pdf | 20 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: MAP2_compressed 1F.pdf | 20 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: MAP1_compresseD F2.pdf | 20 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: SANCTION OF BUILDING _PERMIT.pdf | 20 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GALAXY PRAYAG ARCHITECT CERTIFICATE.pdf | 20 Feb 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GALAXY PRAYAG ENGINEER CERTIFICATE.pdf | 20 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: rera to ram sir.pdf | 20 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Prayag developer 19-20.pdf | 30 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Prayag developers 20-21.pdf | 30 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHIT 5 JULY 2021.pdf | 15 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGI 5 JULY 2021.pdf | 15 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: CERTIFICATE.pdf | 15 Aug 2021 |
| Certificates of CA (Form 3)File: CA CERTIFICATE June 21.pdf | 15 Aug 2021 |
| Layout approvalFile: BUILDING PLAN 1.pdf | 13 Jan 2020 |
| Layout approvalFile: PLAN 2.pdf | 13 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: BUILDING PLAN 1.pdf | 13 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: PLAN 2.pdf | 13 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: REVISED SANTION PLAN.pdf | 30 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 311218.pdf | 30 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 30062018.pdf | 30 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 30092018.pdf | 30 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 30060218.pdf | 30 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 30092018.pdf | 30 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 31032019.pdf | 30 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 31122018.pdf | 30 Dec 2019 |
| OtherFile: LATEST SERACH REPORT.pdf | 30 Dec 2019 |
| OtherFile: COURT DECLARATION OF PROPRIETOR.pdf | 30 Dec 2019 |
| OtherFile: HIGH COURT ORDER.pdf | 30 Dec 2019 |
| Certificates of CA (Form 5)File: Prayag Form 5.pdf | 30 Sep 2019 |
| Certificates of CA (Form 5)File: PRAYAG.pdf | 30 Sep 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE MARCH 2018.pdf | 27 Apr 2018 |
| OtherFile: STAY ORDER.pdf | 27 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Galaxy Prayag PERMIT.pdf | 21 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Art.pdf | 21 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng.pdf | 21 Apr 2018 |
| Certificates of CA (Form 3)File: ca certificate 1.pdf | 21 Apr 2018 |
| Building plan approvalFile: Galaxy Prayag PERMIT.pdf | 31 Jul 2017 |
| Layout approvalFile: MAP.pdf | 31 Jul 2017 |
| PAN CardFile: PAN CARD.PDF | 31 Jul 2017 |
| Copy of the legal title reportFile: Tital Search report-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: encumbrance.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MAP.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Galaxy Prayag PERMIT.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Affidavit.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: letter of allotment.pdf | 31 Jul 2017 |
| OtherFile: declaration.pdf | 31 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHANTI PRAYAG | LAXMI NAGAR | 18 | Completed | Jun 2015 | Late, Apr 2017 |
| SHRI DATTA PRAYAG | LAXMI NAGAR | 20 | Completed | Feb 2014 | Late, Jan 2015 |
| DIVYA PRAYAG | WANJARI NAGAR | 26 | Completed | Apr 2013 | Late, May 2015 |
| BHAKTI PRAYAG | LAXMI NAGAR | 15 | Completed | Feb 2011 | Late, Feb 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
Keep GALAXY PRAYAG on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAGPUR2,800+ in Nagpur
Filed coordinates, straight-line distance. 57 registered projects within 2 km.
VEDANT BERYL
NANIS BUILDCON PRIVATE LIMITED
SHRILA APARTMENTS
MAXX BUILDER AND DEVELOPERS
USHA DEEPAK THOOL
USHA DEEPAK THOOL
SHREEKRISHNA HEMPRABHA
SHREE KRISHNA INFRAVENTURES
PIONEER ORION
PIONEER INFRASTRUCTURES COMPANY PRIVATE LI
SAPHALYA
DELTA DEVELOPERS
See every Nagpur project, with the district possession charts
Builder: SHASHANK PANDE
SHASHANK PANDE has 2 registrations on MahaRERA, including GALAXY PRAYAG and PRAYAG PARADISE. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if GALAXY PRAYAG is delayed beyond 31 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GALAXY PRAYAG?
The registered promoter entity is SHASHANK PANDE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GALAXY PRAYAG?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GALAXY PRAYAG?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GALAXY PRAYAG?
The professionals named in the filing: Architect: VIKAS PADOLE; Engineer: VIKAS PADOLE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GALAXY PRAYAG?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback