Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

GAJANAN TOWER is a Residential / Group Housing project by SWARAJYA INFRA in Sangli, Maharashtra, registered with MahaRERA as P53100048910 on 24 Jan 2023. The registration is recorded completed; possession was promised by 2 Dec 2023.

At a glance

Project

  • NameGAJANAN TOWER
  • TypeResidential / Group Housing
  • Location
    • DHAMANI ROAD
    • NEAR MAHESHWARI GARDEN
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • RERA no.P53100048910
  • ReraGenie IDRG-MH-68005

Builder

  • NameSWARAJYA INFRA
  • Entity typePartnership
  • PartnersPRAKASH LAXMANRAO PATIL, AJAY VISHNU JADHAV, SHAHRUKH PIRSAB SHAIKH

Key dates

this monthRegisteredJan 2023PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2023
  • Promised completion2 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GAJANAN TOWERNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

GAJANAN TOWER: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area305 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
SHOBHA ARUNKUMAR PATILSangli Miraj Kupwad (M Corp.)Sangli
KALPANA VIJAY JADHAVSangli Miraj Kupwad (M Corp.)Sangli
SWARAJYA INFRASangli Miraj Kupwad (M Corp.)Sangli
KALPANA VIJAY PATILSangli Miraj Kupwad (M Corp.)Sangli

Approvals and building plan

Permissible FSI704.2
Proposed, not sanctioned704 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch120 A YASH AVENUE RAM MANDIR CORNER SANGLI

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAKASH LAXMANRAO PATIL
EngineerPRAKASH LAXMANRAO PATIL
Chartered AccountantROHIT KUNDLIK KALE
Chartered AccountantGaurav S Rajpal & Co
PartnerRole in project
SWARAJYA INFRA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53100018204Dec 2023 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Oct 2024

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Gajanan Tower for FY 2023-24 (1).pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SW Form 1 Reraeasy.pdf16 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: SW Form 4 Reraeasy.pdf16 Oct 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: SF.pdf16 Oct 2024
Status of ConveyanceFile: Conv.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SW 2A Reraeasy (1).pdf16 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Swarajya OC (1)_compressed.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SW_FORM 1_JUNE 24.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SW_FORM 2_JUNE 24.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: SW_UNSOLD INVENTORY_JUNE 24.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SW_FORM 3_JUNE 24.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SW_FORM 1_MAR 24.pdf21 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SW_FORM 2_MAR 24.pdf21 Apr 2024
Disclosure of sold/ booked inventoryFile: SW_UNSOLD_MAR 24.pdf21 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SW_FORM 3_MAR 24.pdf21 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_SW_Dec23.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sw_Dec23_11zon.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sw_Dec23_11zon.pdf16 Jan 2024
Declaration in FORM BFile: Form B.pdf11 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf11 Dec 2023
Disclosure of sold/ booked inventoryFile: Circular 29.pdf11 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SW Form 1 Sep 23.pdf13 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SW Form 2 Sep 23.pdf13 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SW Form 3 Sep 23_compressed.pdf13 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 of Gajanan Tower for FY 22-23.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Gajanan Tower as on 2022-23.pdf5 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SW Form 3 Jun 23_compressed.pdf25 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KL Form 1 Jun 23.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SW Form 1 Jun 23.pdf19 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SW Form 2 Jun 23.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SW_Arch_Q4_22-23.pdf25 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SW_Engg_Q4_22-23.pdf25 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SW_Form 3_Q4_22-23_compressed.pdf25 May 2023
Declaration in FORM BFile: Promoter Form B -Gajanan Infra.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A -Merged -Gajanan Tower.pdf5 Jan 2023
Other - TechnicalFile: Landowner Form B -Gajanan Infra.pdf5 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf15 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf8 Dec 2022
CERSAI detailsFile: CERCAI.pdf8 Dec 2022
Other - LegalFile: development Agreement.pdf8 Dec 2022
Other - LegalFile: development Agreement 1.pdf8 Dec 2022
Copy of the legal title reportFile: 2_Legal Title.pdf30 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 19_CA Cert.pdf12 Nov 2022
Details of encumbrances concerned to FinanceFile: 4_Legal Encumbrance.pdf7 Nov 2022
Details of encumbrances concerned to FinanceFile: 3_Encumbrance Finance.pdf7 Nov 2022
Details of encumbrances concerned to LegalFile: 4_Legal Encumbrance.pdf7 Nov 2022
Details of encumbrances concerned to LegalFile: 3_Encumbrance Finance.pdf7 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10_Architect Certificate.pdf7 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11_Engg Certificate.pdf7 Nov 2022
Building plan approvalFile: Gajanan Tower Building Permission.pdf4 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Gajanan Tower Building Permission.pdf4 Nov 2022
Declaration about Commencement CertificateFile: Format D Gajanan Tower 160123.pdf2 Nov 2022
Proforma of Allotment letterFile: Allotment letter.pdf2 Nov 2022
Proforma of Agreement for saleFile: Pg 1 to 9.pdf31 Oct 2022
Proforma of Agreement for saleFile: Pg 10 to 20_compressed_compressed_compressed.pdf31 Oct 2022
Layout approvalFile: 5_Saction plan.PDF30 Oct 2022
PAN CardFile: GAJANAN TOWERS PAN CARD.pdf30 Oct 2022
Copy of Layout Approval (in case of layout)File: 5_Saction plan.PDF30 Oct 2022
Deviation Report with respect to Allotment letterFile: 35_Deviation OF Allotment of Sales.pdf30 Oct 2022
Deviation Report with respect to model copy of AgreementFile: 16_Deviation for Agreement for Sale.pdf30 Oct 2022

How this compares with Sangli

11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep GAJANAN TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR MAHESHWARI GARDEN790+ in Sangli

Builder: SWARAJYA INFRA

SWARAJYA INFRA has 1 registration on MahaRERA, including GAJANAN TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if GAJANAN TOWER is delayed beyond 2 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAJANAN TOWER?

The registered promoter entity is SWARAJYA INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAJANAN TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GAJANAN TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAJANAN TOWER?

The professionals named in the filing: Architect: PRAKASH LAXMANRAO PATIL; Engineer: PRAKASH LAXMANRAO PATIL; Chartered Accountant: ROHIT KUNDLIK KALE; Chartered Accountant: Gaurav S Rajpal & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAJANAN TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAJANAN TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAJANAN TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.