Home / Browse projects / Mumbai Suburban, Maharashtra / Gajanan Plaza

Registered No litigation declared Others project

Gajanan Plaza

By Balaji Construction Co.

RG-MH-90949 · RERA P51800009622 · Last updated on MahaRERA portal: 17 May 2025

Source: official MahaRERA filing

Red flags

  • 14 complaints at MahaRERA
  • Completion date moved by 108 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 108 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
14Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

Gajanan Plaza is a Others project by Balaji Construction Co. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009622 on 22 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 108 months from the original filing. 14 complaints are on record with the regulator.

At a glance

Project

  • NameGajanan Plaza
  • TypeOthers
  • Location
    • 120 ft link road
    • 90ft poisur charkop rd
    • Mahavir nagar
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009622
  • ReraGenie IDRG-MH-90949

Builder

  • NameBalaji Construction Co.
  • Entity typePartnership
  • PartnersMahendra Jayantilal Vora, Chirag Mahendra Vora
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed134 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GAJANAN PLAZANA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

GAJANAN PLAZA: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 17 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area565 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2260.0
Proposed, not sanctioned1,127 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNand Dham, M G Cross Road, Kandivali West, Mumbai 400067

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhijit A Mehta
ArchitectAr Atit Mistry
ArchitectSapre and Associates
EngineerRajeev Shah
PartnerRole in project
Balaji Construction Co.-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001031Dec 2018 → Apr 2020

Reason as filed by the promoterTo whom so ever it may concern this is to bring to your kind knowledge that we have been facing several problems due to which we are applying for extension of the project, the reason for the delay is stated below: 1. Architect for the project resigned on 28/08/2017 2. New Architects appointment made on 06/09/2017 3. Change of Architect submitted to BMC on 15/09/2017 4. New Architect accepted on BMC Console on 17/10/2017 5. CFO NOC for double basement ground and 5 upper floors was applied and obtained under No.CHE/A-3885/BP(WS)AR-CFO dated 06/09/2018 6. EET&C NOC for double basement ground and

EXT51800008430Dec 2018 → Jun 2021

Reason as filed by the promoterAs per application dated 02/11/2020 uploaded in OTHER documents, specifically under Section 5 of MahaRERA Act read with Rule 6 of MahaRERA Rules.

EXT51800003836Dec 2018 → Apr 2020

Reason as filed by the promoterAs per application and other supporting documents uploaded below. We are seeking extension under Section 5 read with Rule 6 of the RERA Act due to reasons set out in the Application which is uploaded at Sr.No.1 giving details, instead of Resolution of Association of Allottees.

EXT51800010296Dec 2018 → Dec 2027

Reason as filed by the promoterIn view of the order of the Hon'ble MahaRERA Appellate Tribunal passed in the hearing held on 29/06/2021, we are making the present application as attached. The Regulatory Order Passed by the Hon'ble Chairperson has been uploaded below.

Complaints filed with MahaRERA14

Case no.ComplainantRespondentFiled
CC006000000055118PRASHANT SUKHADEV MAHAJANBalaji construction company01/07/2018
CC006000000197884PRASHANT SUKHADEV MAHAJANBalaji Construction Co04/08/2021
CC006000000079482Mr. Jayantilal Parsotam MakwanaBalaji Construction Co.27/05/2019
CC006000000192778Balaji Construction Co.Principal Secretary, MahaRERA Authority01/03/2020
CC006000000194706Jayantilal Purshottam MakwanaBalaji Construction Company30/10/2020
CC006000000195552Balaji Construction Co.Maharashtra Real Estate Regulatory Authority07/01/2021
CC006000000198548Chintan ShahBalaji Construction Co.09/10/2021
CC006000000198549Achala PatilM/s Balaji Construction Co09/10/2021
CC006000000198550Hetal ShahBalaji Construction Co09/10/2021
CC006000000198551Shashikumar MishraM/s Balaji Construction Co09/10/2021
CC006000000198552Anjusha KadamM/s Balaji Constuction Co09/10/2021
CC006000000198554Vikram ShahM/s Balalji Construction Co09/10/2021
CC006000000198555Achalal PatilM/s Balaji Construction Co22/10/2021
CC006000000429243Mukesh SoniBALAJI CONSTRUCTION COMPANY14/02/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP - MahaRERA Form 1 - 31-12-2024.pdf17 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP - MahaRERA Form 1 - 31-03-2025.pdf17 May 2025
Certificates of CA (Form 3)File: GP - MahaRERA Form 3 - 31-12-2024.pdf17 May 2025
Certificates of CA (Form 3)File: GP - MahaRERA Form 3 - 31-03-2025.pdf17 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GP - MahaRERA Form 2 - 31-12-2024.pdf17 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GP - MahaRERA Form 2 - 31-03-2025.pdf17 May 2025
Declaration in FORM BFile: GP - MahaRERA Form B - 09-04-2025.pdf25 Apr 2025
Certificates of CA (Form 3)File: Form - 3 BCC Q-3 2023-24.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form - 3 BCC Q-4 2023-24.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form - 3 BCC Q-1 2024-25.pdf3 Dec 2024
Certificates of CA (Form 3)File: Form - 3 BCC Q-2 2024-25.pdf3 Dec 2024
Disclosure of sold/ booked inventoryFile: Gajanan Plaza - 15-12-2023.pdf3 Dec 2024
Disclosure of sold/ booked inventoryFile: Gajanan Plaza - 15-03-2024.pdf3 Dec 2024
Disclosure of sold/ booked inventoryFile: Gajanan Plaza - 15-06-2024.pdf3 Dec 2024
Disclosure of sold/ booked inventoryFile: Gajanan Plaza - 15-09-2024.pdf3 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: GP Form 2A 22-10-2022.pdf3 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form - 5 BCC 2023-24.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP Form 1 30-03-2024.pdf30 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP Form 1 30-06-2024.pdf30 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP Form 1 30-09-2024.pdf30 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP Form 1 31-12-2023.pdf30 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GP Form 2 30-06-2024.pdf30 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GP Form 2 30-09-2024.pdf30 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GP Form 2 31-03-2024.pdf30 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GP Form 2 31-12-2023.pdf30 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GP - Form 5 17-08-2023.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GP Form 2A 22-11-2024.pdf30 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gajanan Plaza Scan copy 30092023.pdf14 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gajanan Plaza Engineer Certificate 30062023.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLDUNSOLD.pdf14 Oct 2023
Certificates of CA (Form 3)File: BCC Rera Certificate compressed.pdf14 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf30 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGI.pdf30 Sep 2023
Certificates of CA (Form 3)File: gpf3.pdf26 Sep 2023
Certificates of CA (Form 5)File: gpf5.pdf26 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM2A31032023.pdf22 Jun 2023
Disclosure of sold/ booked inventoryFile: soldunsold15062023compressed.pdf17 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: scan 2GPARCHCERTcompressed.pdf15 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: scan 1GPENGCERTcompressed.pdf15 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: scan 1GPENGCERTcompressed.pdf15 Jun 2023
Certificates of CA (Form 3)File: Chartered Accountant Certificate 2.pdf15 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf21 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: GP CA Certificate Form 5 - 18-01-2023.pdf24 Mar 2023
Disclosure of sold/ booked inventoryFile: GAJANAN PLAZA SOLD UNSOLD LIST06032023.pdf6 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP RERA Form 1 - Architect Certificate - 31-12-2021.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP RERA Form 1 - Architect Certificate - 30-03-2022.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP RERA Form 1 - Architect Certificate - 30-06-2022.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP RERA Form 1 - Architect Certificate - 30-09-2022.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GP RERA Form 1 - Architect Certificate - 31-12-2022.pdf10 Feb 2023
Certificates of CA (Form 3)File: RERA CA CERTIFICATE 01102022 TO 31122022.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE 31122021.pdf21 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE 31032022.pdf21 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE 30062022.pdf21 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE 30092022.pdf21 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE 31122022.pdf21 Jan 2023
Certificates of CA (Form 3)File: RERA CA CERTIFICATE 01102021TO31122021.pdf21 Jan 2023
Certificates of CA (Form 3)File: RERA CA CERTIFICATE 01012022 TO 31032022.pdf21 Jan 2023
Certificates of CA (Form 3)File: RERA CA CERTIFICATE 01042022 TO 30062022.pdf21 Jan 2023
Certificates of CA (Form 3)File: RERA CA CERTIFICATE 01072022 TO 30092022.pdf21 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA CA CERTIFICATE 19012023.pdf21 Jan 2023
Disclosure of sold/ booked inventoryFile: GP Sold-Unsold 25-12-2021 Corrected.pdf10 Aug 2022
Disclosure of sold/ booked inventoryFile: GP Sold-Unsold 05-07-2022 Corrected.pdf10 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NEW ARCHITECT WORK COMPLETION LETTER.pdf5 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf5 Jul 2022
Disclosure of sold/ booked inventoryFile: GAJANAN PLAJA SOLD UNSOLD LIST003.pdf5 Jul 2022
Certificates of CA (Form 3)File: Certificate-BCC_Q3.pdf5 Jul 2022
Certificates of CA (Form 3)File: Certifcate_Q4.pdf5 Jul 2022
OtherFile: MahaRERA update 05072022.pdf5 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: MAHARERA FORM 5 For annual report of CA.pdf15 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAC.pdf13 Jan 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: CLARIFICATION.pdf13 Jan 2022
Declaration about Commencement CertificateFile: CC Declaration 25-12-2021.pdf25 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Engineer Certificate.pdf25 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - Site Supervisor Certificate.pdf25 Dec 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 25-12-2021.pdf25 Dec 2021
Certificates of CA (Form 3)File: FORM 3 - CA Certificate_small.pdf25 Dec 2021
Disclosure of sold/ booked inventoryFile: GP Sold-Unsold List.pdf21 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GP CA Form 5 21-06-2021.pdf21 Aug 2021
Building plan approvalFile: GP Amended Plan - Part Approval 27-11-2019-compressed.pdf22 Jun 2021
Building plan approvalFile: GP Amended Plan - PARTLY APPROVED LETTER.pdf22 Jun 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 108 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Gajanan Plaza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahavir nagar6,700+ in Mumbai Suburban

2 kmGajanan PlazaCompleted 69Lapsed / revoked 47Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 200 registered projects within 2 km.

Builder: Balaji Construction Co.

Balaji Construction Co. has 2 registrations on MahaRERA, including Gajanan Plaza and NIRVANA ECO HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Gajanan Plaza is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gajanan Plaza?

The registered promoter entity is Balaji Construction Co., a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gajanan Plaza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Gajanan Plaza?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Gajanan Plaza?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gajanan Plaza?

The professionals named in the filing: Architect: Abhijit A Mehta; Architect: Ar Atit Mistry; Architect: Sapre and Associates; Engineer: Rajeev Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gajanan Plaza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gajanan Plaza. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gajanan Plaza to a free account