ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / GAJ OASIS

Registered No litigation declared Others project

GAJ OASIS

By SHIV BUILDERS AND DEVELOPERS

RG-MH-23327 · RERA P52000078635 · Last updated on MahaRERA portal: 2 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

GAJ OASIS is a Others project by SHIV BUILDERS AND DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000078635 on 30 Dec 2024. Possession was promised by 30 Sep 2026 and is now 1 months past that date.

At a glance

Project

  • NameGAJ OASIS
  • TypeOthers
  • Location
    • NODE- PUSHPAK
    • NA
    • Wahal
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000078635
  • ReraGenie IDRG-MH-23327

Builder

  • NameSHIV BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • Other registrations1 more →
  • Completed1 of 2
  • Past their filed date1

Key dates

1 months past promisethis monthRegisteredDec 2024PromisedSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Dec 2024
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GAJ OASISNA87000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

GAJ OASIS: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area476 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2025
LandownerVillageDistrict
BALIRAM NAMA PATILWahalRaigarh
JIVAN BALIRAM PATILWahalRaigarh

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI1725.72
Proposed, not sanctioned1,726 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRD FLOOR SHOP NO 1 TO 5 PRECIOUS EMERALD PLOT NO 27 KAMOTHE SECTOR 21 NAVI MUMBAI KHARGHAR MAHARASHTRA 410209

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRIARCH DESIGN STUDIO
EngineerSC SHRAVANI CONSULTANTS CONSULTING ENGINEERS
Chartered AccountantDHNADEKAR METHWANI AND CO
Chartered AccountantHARIYANI & ASSOCIATES
PartnerRole in project
SHIV BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1_ DEC 24_ GAJ OASIS.pdf2 Jul 2026
Form 2File: FORM 2_ DEC 24_ GAJ OASIS.pdf2 Jul 2026
Form 3File: FORM 3_ DEC 24_ GAJ OASIS (1).pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 2024_ GAJ OASIS.pdf2 Jul 2026
Form 1File: FORM 1_ MARCH 25_ GAJ OASIS.pdf2 Jul 2026
Form 2File: FORM 2_ MARCH 25_ GAJ OASIS.pdf2 Jul 2026
Form 3File: FORM 3_MARCH 25_ GAJ OASIS.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_MARCH 2025_ GAJ OASIS.pdf2 Jul 2026
Form 1File: FORM 1_ JUNE 25_ GAJ OASIS.pdf2 Jul 2026
Form 2File: FORM 2_ JUNE 25_ GAJ OASIS.pdf2 Jul 2026
Form 3File: FORM 3_ JUNE 25_ GAJ OASIS.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ JUNE 2025_ GAJ OASIS (1).pdf2 Jul 2026
Form 1File: FORM 1_ SEP 25_ GAJ OASIS.pdf2 Jul 2026
Form 2File: FORM 2_ SEP 25_ GAJ OASIS.pdf2 Jul 2026
Form 3File: FORM 3_ SEP 25_ GAJ OASIS.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ SEPT 2025_ GAJ OASIS (4).pdf2 Jul 2026
Form 1File: FORM 1_ DEC 25_ GAJ OASIS.pdf2 Jul 2026
Form 2File: FORM 2_ DEC 25_ GAJ OASIS.pdf2 Jul 2026
Form 3File: FORM 3_ DEC 25_ GAJ OASIS_compressed.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 2025_ GAJ OASIS (3).pdf2 Jul 2026
Form 1File: FORM 1_ MARCH 26_ GAJ OASIS.pdf2 Jul 2026
Form 2File: FORM 2_ MARCH 26_ GAJ OASIS.pdf2 Jul 2026
Form 3File: FORM 3_ MARCH 26_ GAJ OASIS_compressed.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MAR26_ GAJ OASIS.pdf2 Jul 2026
Form 5 (FY 2024-2025)File: FORM 5 _ MARCH 25_ GAJ OASIS.pdf6 May 2026
Other - TechnicalFile: DECLARATION.pdf23 Dec 2024
Other - LegalFile: Supplementary Deed Gaj Oasis _compressed.pdf18 Dec 2024
Proforma of Agreement for saleFile: AFS NEW.pdf18 Dec 2024
Other - LegalFile: TRIPARTITE_compressed.pdf10 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A) (1).pdf2 Dec 2024
Other - TechnicalFile: 2 Other - Technical (1).pdf1 Dec 2024
Copy of the legal title reportFile: 1 Copy of the legal title report (1).pdf29 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: REVISED FORM 3 FOR REGISTRATION (1).pdf29 Nov 2024
Other - LegalFile: 1 Other - Technical.pdf29 Nov 2024
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1).pdf29 Nov 2024
Details of encumbrances concerned to FinanceFile: 3 a Details of encumbrances concerned to Finance.pdf28 Nov 2024
Details of encumbrances concerned to FinanceFile: 4 b Details of encumbrances concerned to Legal.pdf28 Nov 2024
Proforma of Allotment letterFile: 17 Proforma of Allotment letter.pdf28 Nov 2024
Declaration in FORM BFile: 9 Declaration in FORM B.pdf28 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14-2 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf28 Nov 2024
CERSAI detailsFile: 12 CERSAI details.pdf28 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: 19 Declaration about all RERA Designated Bank Accounts (Format A) - Declaration for Landow28 Nov 2024
Deviation Report with respect to Allotment letterFile: 22 Deviation Report with respect to Allotment letter.pdf28 Nov 2024
Details of encumbrances concerned to LegalFile: 3 a Details of encumbrances concerned to Finance.pdf28 Nov 2024
Details of encumbrances concerned to LegalFile: 4 b Details of encumbrances concerned to Legal.pdf28 Nov 2024
Deviation Report with respect to model copy of AgreementFile: 23 Deviation Report with respect to model copy of Agreement.pdf28 Nov 2024
Proforma of Agreement for saleFile: 16 bANNEXURE I.pdf28 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 15 Disclosure of Interest in Other Real Estate Organizations.pdf28 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 20 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B).28 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 21 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)-28 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: 13 Disclosure for secured unsecured finance availed for the project.pdf28 Nov 2024
Building plan approvalFile: 6 Building Plan Approval.pdf28 Oct 2024
Layout approvalFile: 5 Copy of Layout Approval (in case of layout).pdf28 Oct 2024
PAN CardFile: 1 PAN CARD.pdf28 Oct 2024
Copy of Layout Approval (in case of layout)File: 5 Copy of Layout Approval (in case of layout).pdf28 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: 7 Commencement Certificates NA Order for plotted development.pdf28 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 6 Building Plan Approval.pdf28 Oct 2024
Other - LegalFile: 24 Other - Legal- Sale Deed_compressed-compressed.pdf28 Oct 2024
Other - FinanceFile: 26 Finance - Partnership Deed-compressed.pdf28 Oct 2024
Other - TechnicalFile: 28 Technical - Partnership Deed-compressed.pdf28 Oct 2024

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GAJ OASIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA5,900+ in Raigarh

Builder: SHIV BUILDERS AND DEVELOPERS

Shiv Builders and Developers has 2 registrations on MahaRERA, including Ganesh Heights and GAJ OASIS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if GAJ OASIS is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAJ OASIS?

The registered promoter entity is SHIV BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAJ OASIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GAJ OASIS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAJ OASIS?

The professionals named in the filing: Architect: TRIARCH DESIGN STUDIO; Engineer: SC SHRAVANI CONSULTANTS CONSULTING ENGINEERS; Chartered Accountant: DHNADEKAR METHWANI AND CO; Chartered Accountant: HARIYANI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAJ OASIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAJ OASIS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAJ OASIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.