Home / Browse projects / Mysore, Karnataka / G9 PAVAMANA
G9 PAVAMANA
By G9 PROJECTS
RG-KA-85662 · RERA PRM/KA/RERA/1268/378/PR/200205/003242 · Last updated on RERA Karnataka portal: 23 Jan 2020
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
G9 PAVAMANA is a Residential/Group Housing project by G9 PROJECTS in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/200205/003242 on 5 Feb 2020. Possession is promised by 31 Dec 2022. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameG9 PAVAMANA
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/200205/003242
- ReraGenie IDRG-KA-85662
Builder
- NameG9 PROJECTS
- Entity typeOther
- Authorized SignatoryNagachar Kiran
- OthersNagachar Kiran
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Feb 2020
- Promised completion31 Dec 2022
- Revised completionRevised to 31 Dec 2022 (originally 31 Mar 2022)
- Buildings1 building record
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| G9 PAVAMANA | - | - | - | 32 | 0 | 32 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 23 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 23 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | N. Sridhara |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed62
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/200205/003242 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| declarationFile: declaration - g9.pdf | 23 Jan 2020 |
| Declaration - balance sheetFile: declaration.pdf | 15 Jan 2020 |
| FORM BFile: form b new.pdf | 8 Jan 2020 |
| Joint Affidavit Cum DeclarationFile: jda affidavit.pdf | 8 Jan 2020 |
| Form BFile: form b (2).pdf | 28 Dec 2019 |
| AffidavitFile: affidavit.pdf | 28 Dec 2019 |
| KSPCBFile: Polution Board.pdf | 28 Dec 2019 |
| Financial statements for 2017-18 and 2018-19File: financial.pdf | 11 Dec 2019 |
| Clarification Letter on SY noFile: Clarification letter for sy no..pdf | 11 Dec 2019 |
| conversion orderFile: CONVERSION CERTIFICATE.pdf | 11 Dec 2019 |
| Notarized form-BFile: form b (2).pdf | 11 Dec 2019 |
| Notarized joint affidavit cum declarationFile: affidavit.pdf | 11 Dec 2019 |
| CertificateFile: GST CERTIFICATE.pdf | - |
| commencement certificate | - |
| layout (2) | - |
| layout (2) | - |
| Performa of sale deed | - |
| Performa of Agreement for sale (7) | - |
| sale deed and khata | - |
| layout (2) | - |
| Area development | - |
| Provisional Allotment Letter Format | - |
| Brouchers declaration | - |
| project specification | - |
| EC (2) | - |
| affidavit | - |
| Joint Development Agreement | - |
| Khatha | - |
| Joint Development Agreement | - |
| layout (2) | - |
| layout & Project Specification | - |
| Declaration - na order | - |
| Balance Sheet 2018 - 2019File: Balance Sheet.pdf | - |
| Balance Sheet 2017 - 2018File: Balance Sheet.pdf | - |
| Balance Sheet 2016 - 2017File: Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: P & L declaration.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P & L declaration.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L declaration.pdf | - |
| Director's Report 2018 - 2019File: Directos Report.pdf | - |
| Director's Report 2017 - 2018File: Directos Report.pdf | - |
| Director's Report 2016 - 2017File: Directos Report.pdf | - |
| Cash Flow Statement 2018 - 2019File: Cash flow statement.pdf | - |
| Cash Flow Statement 2017 - 2018File: Cash flow statement.pdf | - |
| Auditor's Report 2018 - 2019File: Auditor’s Report.pdf | - |
| Auditor's Report 2017 - 2018File: Auditor’s Report.pdf | - |
| Auditor's Report 2016 - 2017File: Auditor’s Report.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: ITR declaration.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR declaration.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR declaration.pdf | - |
| form b (2) | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
| Advertisement Copy 1File: Brochure.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_200205_003242.xlsx | - |
| Loan raised documentFile: Letter of confirmation for creation of mortgage.pdf | - |
| Stability CertificateFile: Structural Stability Certificate.pdf | - |
| Consent for operation issued by KSPCBFile: Certificate issued by the KSPCB, Consent for operation of STP Plant.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift License.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Certficate issued by the concerned power supply Authorities.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form 5 - Architect certificate - G9.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: CA Cert Form 4CC G9 Pavamana.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Completion Affidavit G9 Pavamana.pdf | - |
| Engineer CertificateFile: Form 6 - Engineer Certificate G9.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep G9 PAVAMANA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Filed coordinates, straight-line distance. 9 registered projects within 2 km.
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: G9 PROJECTS
G9 PROJECTS has 1 registration on RERA Karnataka, including G9 PAVAMANA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if G9 PAVAMANA is delayed beyond 31 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of G9 PAVAMANA?
The registered promoter entity is G9 PROJECTS. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in G9 PAVAMANA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at G9 PAVAMANA?
The professionals named in the filing: Engineer: N. Sridhara. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in G9 PAVAMANA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback