Home / Browse projects / Dhule, Maharashtra / G K ARCADE
G K ARCADE
RG-MH-49182 · RERA P49800050308 · Last updated on MahaRERA portal: 4 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 11 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Dhule registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
G K ARCADE is a Others project by GOPAL KASHINATH KELE HUF in Dhule, Maharashtra, registered with MahaRERA as P49800050308 on 1 Apr 2023. Possession was promised by 30 Nov 2025 and is now 11 months past that date. 2 of the 18 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameG K ARCADE
- TypeOthers
- Location
- NAKANE ROAD
- WALWADI DEOPUR DHULE
- Walwadi (CT)
- Dhule
- 424002
- Pincode424002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P49800050308
- ReraGenie IDRG-MH-49182
Builder
- NameGOPAL KASHINATH KELE HUF
- Entity typeOthers
- Named personsMRS RUPALI PRANESH LAD (KELE), SHARV PRANESH LAD (KELE), PRANJALI GOPAL LAD (KELE), AKSHARA PRANESH LAD (KELE), GOPAL KASHINATH KELE HUF, MR GOPAL KASHINATH KELE (LAD), MRS SUNANDA GOPAL KELE (LAD), MR PRITESH GOPAL LAAD (KELE), MRS HARSHADA PRITESH LAD (KELE), MR PRANESH GOPAL LAD (KELE)
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Apr 2023
- Promised completion30 Nov 2025
- Revised completionNone
- Buildings1 building record
- Documents filed35 files
Current status
Figures as on 4 Jun 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| G K ARCADE | NA | 4 | 3 | 18 | 0 | 18 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 25%.
G K ARCADE: 48% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed22
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership10
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MR GOPAL KASHINATH KELE | Walwadi (CT) | Dhule |
| MRS SUNANDA GOPAL KELE | Walwadi (CT) | Dhule |
| MR PRITIESH GOPAL KELE (LAD) | Pune (M Corp.) | Pune |
| MRS HARSHADA PRITESH KELE (LAD) | Pune (M Corp.) | Pune |
| MR PRANESH GOPAL KELE (LAD) | Pune (M Corp.) | Pune |
| RUPALI PRANESH LAD (KELE) | Pune (M Corp.) | Pune |
| SHARV PRANESH LAD (KELE) | Pune (M Corp.) | Pune |
| PRANJALI GOPAL LAD (KELE) | Pune (M Corp.) | Pune |
| AKSHARA PRANESH LAD (KELE) | Pune (M Corp.) | Pune |
| GOPAL KASHINATH KELE HUF | Walwadi (CT) | Dhule |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HEMANT B ISAI BHALCHANDRA ISAI |
| Engineer | HEMANT B ISAI BHALCHANDRA ISAI |
| Chartered Accountant | K U Nabariya & Company |
| Chartered Accountant | AKSHAY CHHAJED |
| Partner | Role in project |
|---|---|
| GOPAL KASHINATH KELE HUF | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jun 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed35
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: KELE KAKA.pdf | 4 Jun 2025 |
| Form 1File: Form No 1 30-06-2024.pdf | 4 Jun 2025 |
| Form 2File: Form No 2 30-06-2024.pdf | 4 Jun 2025 |
| Form 2File: Form No 2 30-06-2024.pdf | 4 Jun 2025 |
| Form 2File: Form No 2 15-07-2024.pdf | 4 Jun 2025 |
| Form 1File: Form No 1 15-07-2024.pdf | 4 Jun 2025 |
| Form 3File: 31-03-2025 Form No 3.pdf | 4 Jun 2025 |
| Form 2File: Form No 2 15-07-2024.pdf | 4 Jun 2025 |
| Form 5 (FY 2023-2024)File: 2024 Audit Report.pdf | 4 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No 1 G K Arcade.pdf | 29 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No 2 G K Arcade.pdf | 29 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca Certificate G K Arcade_compressed.pdf | 29 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5 G K Arcade.pdf | 29 Aug 2023 |
| Proforma of Agreement for saleFile: GKArked 11032023.pdf | 11 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Modal DRAFT AGREEMENT FOR SALE 2023.pdf | 11 Mar 2023 |
| Copy of the legal title reportFile: Tital Report GKA2023.pdf | 3 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: detail of ecumbaranc 2023.pdf | 3 Mar 2023 |
| Details of encumbrances concerned to LegalFile: detail of ecumbaranc 2023.pdf | 3 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cERTIFICATE 2023com.pdf | 3 Mar 2023 |
| Other - FinanceFile: own fund letter.pdf | 3 Mar 2023 |
| Layout approvalFile: LAY OUT.pdf | 5 Feb 2023 |
| Building plan approvalFile: BUILDING PLAN.pdf | 5 Feb 2023 |
| PAN CardFile: PAN CARD HUF.pdf | 5 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: LAY OUT.pdf | 5 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf | 5 Feb 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 5 Feb 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 5 Feb 2023 |
| Declaration in FORM BFile: Form B.pdf | 5 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No 1.pdf | 5 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 5 Feb 2023 |
| CERSAI detailsFile: Cersai GK arcade CTS 3530.pdf | 5 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 5 Feb 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 5 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account.pdf | 5 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: Annexure 1.pdf | 5 Feb 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| G K MARKET PHASE 1 | WALWAD | 12 | Completed | Jun 2023 | Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dhule
Computed across the 71 Dhule projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 35 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep G K ARCADE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WALWADI DEOPUR DHULE71 in Dhule
Filed coordinates, straight-line distance. 18 registered projects within 2 km.
SHIVAM PLAZA
ALKA VASANTRAO WANKHEDE
Bhalchandra Regency
Om Shiv Infra
Nakshatram Athashri
Divine Infrastructure
Dreams Anuram
Dream House Builders And Developers
Dream's GTP
New Dream House Builders and Developers
NAKSHATRA AVENUE
DHARMNITI CONSTRUCTION PRIVATE LIMITED
See every Dhule project, with the district possession charts
Builder: GOPAL KASHINATH KELE HUF
GOPAL KASHINATH KELE HUF has 1 registration on MahaRERA, including G K ARCADE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Dhule district page.
Frequently asked questions
What does it mean that G K ARCADE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if G K ARCADE is delayed beyond 30 Nov 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of G K ARCADE?
The registered promoter entity is GOPAL KASHINATH KELE HUF, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in G K ARCADE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for G K ARCADE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at G K ARCADE?
The professionals named in the filing: Architect: HEMANT B ISAI BHALCHANDRA ISAI; Engineer: HEMANT B ISAI BHALCHANDRA ISAI; Chartered Accountant: K U Nabariya & Company; Chartered Accountant: AKSHAY CHHAJED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in G K ARCADE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback