Home / Browse projects / Four Seasons Private Residences Phase - 2

Registration lapsed No litigation declared Residential / Group Housing project

Four Seasons Private Residences Phase - 2

By Provenance Land Private Limited

RG-MH-04502 · RERA P51900022056 · Last updated on MahaRERA portal: 3 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 60%
0Complaints at MahaRERAon this registration
Jump to the 152 documents Report an error

Four Seasons Private Residences Phase - 2 is a Residential / Group Housing project by Provenance Land Private Limited in Worli, 400018, registered with MahaRERA as P51900022056 on 25 Aug 2019. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameFour Seasons Private Residences Phase - 2
  • TypeResidential / Group Housing
  • Location
    • Dr. E Moses Road
    • Worli
    • 400018
  • Pincode400018
  • RERA no.P51900022056
  • ReraGenie IDRG-MH-04502

Builder

  • NameProvenance Land Private Limited
  • Entity typeCompany
  • Managing DirectorAdarsh Rajkumar Jatia
  • ChairpersonRajkumar Subhkaran Jatia
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredAug 2019First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Aug 2019
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed152 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Four Seasons Private ResidencesNA630000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 60%.

Four Seasons Private Residences: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 3 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed153

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots153
Closed/Covered153

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,069 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3685.89
Proposed, not sanctioned3,686 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor , Industry House Opposite Ramon House 159 HT Parekh Marg Churchgate Mumbai 400020

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Provenance Land Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900018506Dec 2023 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EXT51900027603Dec 2023 → Dec 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen procurement issues, site conditions, coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regula

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Mar 2024

Documents filed152

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 152 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Four Seasons Private Residences Phase 2 as on June 2025.pdf3 Jan 2026
Form 2File: Form 2 - Four Seasons Private Residences Phase 2 as on June 2025.pdf3 Jan 2026
Form 3File: Form 3 Four Seasons Private Residency Phase II as on 30-06-2025.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Four Seasons June 2025.pdf3 Jan 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Four Seasons Private Residences Phase 2 as on Sep 2024.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Four Seasons Private Residences Phase 2 as on Dec 2024.pdf6 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Seasons Private Residences Phase 2 as on Sep 2024.pdf6 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Seasons Private Residences Phase 2 as on Dec 2024.pdf6 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Four Seasons Private Residences Phase 2 as on June 2024.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Four Seasons Private Residences Phase 2 as on Sep 2024.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Four Seasons Private Residences Phase 2 as on Sep 2024.pdf24 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Four Seasons Private Residences Phase 2 FY 2023-24.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Four Seasons Private Residences Phase 2 FY 2023-24.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Four Seasons Private Residency Phase II 31-03-2024 (REVISED).pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 23 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Four Seasons Private Residency Phase II 31-03-2024.pdf14 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Four Seasons Private Residency Phase 2 as on June 2024.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Season Private Residences Phase 2 as on March 2024.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Season Private Residences Phase 2 as on June 2024.pdf14 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A mar 23.pdf18 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 23.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Dec 20.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March 21.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 22.pdf15 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 23.pdf15 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: RERA Annexure 1.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FOrm 5 Mar 20.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Mar 21.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Mar 22.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 mar 23.pdf15 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Rera Format A.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1_2_merged_merged.pdf11 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC - Four Seasons Private Residences Phase - 2.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20240208101628_compressed.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Season Private Residences Phase 2 as on Dec 2023.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Four Seasons Private Residency Phase II 31-12-2023.pdf19 Jan 2024
Declaration about Commencement CertificateFile: Rera Format D Celaration of CC.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: RERA Circlular 29.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Season Private Residences Phase 2 as on Sept 2023.pdf5 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Four Seasons Private Residency Phase II Sept 2023.pdf5 Jan 2024
Declaration in FORM BFile: Affidavit_11zon.pdf28 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Four Season Private Residences Phase 2 as on June 2023.pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Four Seasons Private Residency Phase II as on 30-06-2023.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- as on 31-12-2022.pdf22 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - as on 31-03-2023.pdf22 Jun 2023
Building plan approvalFile: Latest Layout-1.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-2_11zon.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-3.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-4.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-5_11zon.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-6.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-7.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-8.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-9.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-10.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-11.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-12.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-13.pdf14 Jun 2023
Building plan approvalFile: Latest Layout-14_11zon.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-1.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-2_11zon.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-3.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-4.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-5_11zon.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-6.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-7.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-8.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-9.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-10.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-11.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-12.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-13.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Latest Layout-14_11zon.pdf14 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Four Seasons Private Residence Phase II as on March 2023.pdf14 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Four Seasons Private Residency Phase II as on March 2023.pdf14 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA FORM 5 PH 2 March 22 (1).pdf3 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Four Season Private Residence Phase 2 Dec 22 - Form 2.pdf14 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Four Seasons Private Residency Phase II as on December 2022.pdf14 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Four Seasons as on March 2022.pdf14 Dec 2022

Keep Four Seasons Private Residences Phase - 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Worli

Builder: Provenance Land Private Limited

Provenance Land Private Limited has 2 registrations on MahaRERA, including Four Seasons Private Residences Phase - 1 and Four Seasons Private Residences Phase - 2. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that Four Seasons Private Residences Phase - 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Four Seasons Private Residences Phase - 2 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Four Seasons Private Residences Phase - 2?

The registered promoter entity is Provenance Land Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Four Seasons Private Residences Phase - 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Four Seasons Private Residences Phase - 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Four Seasons Private Residences Phase - 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Four Seasons Private Residences Phase - 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Four Seasons Private Residences Phase - 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.