Home / Browse projects / Mysore, Karnataka / FOUNDATIONS SILICON
FOUNDATIONS SILICON
By FOUNDATIONS DEVELOPERS & PROMOTERS
RG-KA-81727 · RERA PRM/KA/RERA/1268/378/PR/190913/002855
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
FOUNDATIONS SILICON is a Residential/Group Housing project by FOUNDATIONS DEVELOPERS & PROMOTERS in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/190913/002855 on 13 Sep 2019. Possession is promised by 30 Jan 2022. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameFOUNDATIONS SILICON
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- RERA no.PRM/KA/RERA/1268/378/PR/190913/002855
- ReraGenie IDRG-KA-81727
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on13 Sep 2019
- Promised completion30 Jan 2022
- Revised completionRevised to 30 Jan 2022 (originally 30 Apr 2021)
- Buildings1 building record
- Documents filed76 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Foundations Silicon | - | - | - | 22 | 0 | 22 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJGOPAL GOPINATH |
| Engineer | DEEPAK H S |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed76
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/190913/002855 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Foundations Firm Registration.PDF | - |
| Already registered project ongoing detailsFile: RERA Project List.pdf | - |
| Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Sanctied Plan1.pdf | - |
| Elevation, Sections, Specifications ( If changes are there )File: Elevations.pdf | - |
| List Of AllotteesFile: List Of Allottees b.pdf | - |
| List Of ComplaintsFile: complain declarations.pdf | - |
| Consent LetterFile: Conset Letter.pdf | - |
| List Of Pending LitigationsFile: litigations declarations.pdf | - |
| Chartered Accountant CertificateFile: Form 4.PDF | - |
| Notarized AffidavitFile: Affidavit.PDF | - |
| Engineer CertificateFile: Engineer certificate -for modified.pdf | - |
| Architect CertificateFile: Architect certificate - Modified.pdf | - |
| Structural Engineer Certificate for stability of structureFile: Certificate from H S Deepak.pdf | - |
| Modification of Plan DetailsFile: Sanction Plan (Approved Building Plotting Plan).JPG | - |
| Modification of Plan DetailsFile: Modified Sanction Plan.pdf | - |
| Modification of Plan DetailsFile: CC.pdf | - |
| Modification of Plan DetailsFile: commencement certificate_.pdf | - |
| Modification of Plan DetailsFile: Previous units.xlsx | - |
| Modification of Plan DetailsFile: New units.xlsx | - |
| Document 1File: Pollution Control board Silicon.PDF | - |
| Document 2File: Electricity.PDF | - |
| Commencement certificate | - |
| Approved Layout Plan | - |
| Sale Deed -Silicon | - |
| SA-Foundation Silicon | - |
| Sale Deed of S Ragahavendra_compressed | - |
| Approved Section of Building | - |
| Area Development of Plan | - |
| Preforma Allotment Letter | - |
| pg1 and pg 4 ---11-mar-2019 | - |
| consent for establishment | - |
| pg2 and pg 3 ---11-mar-2019 | - |
| EC from Jan 2018 to Mar 2019 | - |
| Section 3(1) Affidavit | - |
| Joint Declaration cum Affidavit | - |
| MUDA KHATHA TRANSFER LTR | - |
| Silicon JDA | - |
| consent for establishment | - |
| Approved Layout Plan | - |
| Section Plan | - |
| MUDA Order Copy of Conversion | - |
| Balance Sheet 2017 - 2018File: ITR Return FY 2017-18_2_Balance sheet FY 2017-18.pdf | - |
| Balance Sheet 2016 - 2017File: Balancesheet FY 2016-17.pdf | - |
| Balance Sheet 2015 - 2016File: 6.jpg | - |
| Audited Profit and Loss Statement 2017 - 2018File: P & L Account FY 2017-18.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L Account FY 2016-17.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 7.jpg | - |
| Director's Report 2017 - 2018File: NOT APPILCABLE BLANK DOCUMENT.pdf | - |
| Director's Report 2016 - 2017File: NOT APPILCABLE BLANK DOCUMENT.pdf | - |
| Director's Report 2015 - 2016File: NOT APPILCABLE BLANK DOCUMENT.pdf | - |
| Cash Flow Statement 2017 - 2018File: NOT APPILCABLE BLANK DOCUMENT.pdf | - |
| Cash Flow Statement 2016 - 2017File: NOT APPILCABLE BLANK DOCUMENT.pdf | - |
| Auditor's Report 2017 - 2018File: 3CB FY 2017-18.pdf | - |
| Auditor's Report 2016 - 2017File: 3CB FY 2016-17.pdf | - |
| Auditor's Report 2015 - 2016File: 18.jpg | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR Return FY 2017-18.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR Ack FY 2016-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 1.jpg | - |
| Form B | - |
| Tower Excel SheetFile: PRMKARERA1268378PR190913002855.xlsx | - |
| Loan raised documentFile: Silicon Canara Bank discharge deed.pdf | - |
| Stability CertificateFile: Stability Certificate.pdf | - |
| Occupancy CertificateFile: KEB & Occupancy Certificate.pdf | - |
| Consent for operation issued by KSPCBFile: Pollution Control board Silicon.PDF | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift Certificate.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electricity NOC Silicon.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Completion Report - SILICON.pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Silicon Archiect Certificate_Closure.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Silicon Declaration_Association of Allotees.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Silicon Archiect Certificate_Closure.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Silicon CA Certificate_Closure Form CCqq.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Silicon Engineer Certificate_Closure.pdf | - |
| Electricity ApprovalFile: Electricity approval.PDF | - |
| AffidavitFile: Silicon Affidavit Closure.pdf | - |
| sale deedFile: Sale agreement Silicon_Prashanth 1.pdf | - |
| completion ReportFile: Completion Report - SILICON.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep FOUNDATIONS SILICON on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: FOUNDATIONS DEVELOPERS & PROMOTERS
FOUNDATIONS DEVELOPERS & PROMOTERS has 5 registrations on RERA Karnataka, including FOUNDATIONS SIRII and Foundations Pearl. Its filings declare 9 earlier projects, 7 of them declared completed. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if FOUNDATIONS SILICON is delayed beyond 30 Jan 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of FOUNDATIONS SILICON?
The registered promoter entity is FOUNDATIONS DEVELOPERS & PROMOTERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in FOUNDATIONS SILICON?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at FOUNDATIONS SILICON?
The professionals named in the filing: Architect: RAJGOPAL GOPINATH; Engineer: DEEPAK H S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in FOUNDATIONS SILICON?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback