RG-KA-66670 · RERA PRM/KA/RERA/1268/378/PR/200811/003542 · Last updated on RERA Karnataka portal: 1 Aug 2020
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Foundation Dhiya is a Residential/Group Housing project by FOUNDATIONS DHIYA in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/200811/003542 on 11 Aug 2020. Possession is promised by 31 Dec 2022.
At a glance
Project
- NameFoundation Dhiya
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/200811/003542
- ReraGenie IDRG-KA-66670
Builder
- NameFOUNDATIONS DHIYA
- Entity typePartnership Firm
- Authorized SignatoryMURALIDHARA N S
- DirectorsGURUSHANTHAPPA U M, SWAMY S R, RAVINDRA BHAT A R, SRIDHAR A V
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on11 Aug 2020
- Promised completion31 Dec 2022
- Revised completionNone
- Buildings1 building record
- Documents filed84 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| FOUNDATIONS DHIYA | - | - | - | 20 | 0 | 20 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 1 Aug 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 1 Aug 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Namrutha H Shenoy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V M ASSOCIATES |
| Engineer | H S DEEPAK |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed84
As listed on the registration, under the names the promoter filed them with; the newest 80 of 84 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/200811/003542 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CHANGE OF BANK ACCOUNT NAME AS PER BANK ACCOUNT RERA CIRCULARFile: Foundations RERA Dhiya Account for sheet.jpg | 1 Aug 2020 |
| AUDITED BALANCE SHEET 18-19 WITH UDIN NUMBERFile: Foundations Balance sheet 18-19.PDF | 27 Jul 2020 |
| AUDITED P & L 18-19 WITH UDIN NUMBERFile: Foundations P & L account 18-19.PDF | 27 Jul 2020 |
| EC AS ON 22 JULY 2020File: Dhiya EC RERA NO1.PDF | 27 Jul 2020 |
| BANK REQUEST LETTER TO CHANGE NAME AT BANKFile: RESOLUTION -BANK ACCOUNT CHANGE.pdf | 27 Jul 2020 |
| FORM BFile: Form-B-Affidavit Cum Declaration.PDF | 23 Jul 2020 |
| Plan LIcence Letter Upload with Seal and SignFile: Sanction Plan with sign and Seal.pdf | 23 Jul 2020 |
| Sanction plan with seal and signature of Plan Sanction AuthorityFile: Sanction Plan with sign and Seal.pdf | 23 Jul 2020 |
| CertificateFile: Foundation Regestration Certific.PDF | - |
| Commencement Certificate 2 | - |
| Single Layout Plan | - |
| Namrath Shenoy Final Corportion Send Sanction Drawing - Copy-Model_page-0001 | - |
| Sale Deed | - |
| Agreement for sale | - |
| Sale Deed Namrata H SHenoy0001 | - |
| Single Layout Plan | - |
| Namrath Shenoy Final Corportion Send Sanction Drawing | - |
| Allotment Letter | - |
| Broucher 1 | - |
| DHIYA structural details | - |
| Dhiya EC | - |
| Affidavit Notarized - Dhiya | - |
| Joint Affidavit Cum Declaration | - |
| Dhiya Khatha | - |
| JDA Dhiya | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Pollution Control Board_page-0001 | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Single Layout Plan | - |
| Namrath Shenoy Final Corportion Send Sanction Drawing | - |
| Land Coversion Certificate-Dhiya | - |
| Unnamed document | - |
| Balance Sheet 2018 - 2019File: Foundations 2018-19 Balance sheet.PDF | - |
| Balance Sheet 2017 - 2018File: Foundation 2017-18 Balance Sheet.PDF | - |
| Balance Sheet 2016 - 2017File: Foundation 2016-17 Balance Sheet.PDF | - |
| Audited Profit and Loss Statement 2018 - 2019File: Foundation 2018-19 P & L Account.PDF | - |
| Audited Profit and Loss Statement 2017 - 2018File: Foundation 2016-17 P & L Account.PDF | - |
| Audited Profit and Loss Statement 2016 - 2017File: Foundation 2016-17 Balance Sheet.PDF | - |
| Auditor's Report 2018 - 2019File: Foundation 2018-19 Auditors Rep.PDF | - |
| Auditor's Report 2017 - 2018File: Foundation 2017-18 Auditor Repor.PDF | - |
| Auditor's Report 2016 - 2017File: Foundation 2016-17 Auditor Repor.PDF | - |
| Income Tax Return Acknowledgement 2018 - 2019File: Foundations 2018-19 ITR Return.PDF | - |
| Income Tax Return Acknowledgement 2017 - 2018File: Foundation 2017-18 IT Return.PDF | - |
| Income Tax Return Acknowledgement 2016 - 2017File: Foundation 2016-17 IT Return.PDF | - |
| Form B | - |
| Prospectus/BrochureFile: Foundations Dhiya E-Brochure 19-Nov-2020.pdf | - |
| Advertisement Copy 1File: Advertisment copy.jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_200811_003542 - UNIT DETAILS.xlsx | - |
| Loan raised documentFile: Loan Sanction Letter - Dhiya.pdf | - |
| Stability CertificateFile: Stability Report-DHIYA.pdf | - |
| Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Dhiya Plan.pdf | - |
| Consent for operation issued by KSPCBFile: Pollution Control Board.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift NOC-Dhiya.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Dhiya CHESCOM.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Water and UGD.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Declaration to association of allotees Dhiya.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Dhiya Architect Certificate Closure upl.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC for RERA Dhiya upl.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Dhiya Affidavit Closure.pdf | - |
| DHIYA PLANFile: Dhiya Plan.pdf | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| FOUNDATIONS SILVER SPRINGS | - | Completed | - | No date filed |
| FOUNDATIONS PEARL | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep Foundation Dhiya on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Filed coordinates, straight-line distance. 8 registered projects within 2 km.
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: FOUNDATIONS DHIYA
FOUNDATIONS DHIYA has 1 registration on RERA Karnataka, including Foundation Dhiya. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if Foundation Dhiya is delayed beyond 31 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Foundation Dhiya?
The registered promoter entity is FOUNDATIONS DHIYA, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Foundation Dhiya?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Foundation Dhiya?
The professionals named in the filing: Architect: V M ASSOCIATES; Engineer: H S DEEPAK. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Foundation Dhiya?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback