ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Forest Trails Athashri - B2

Completed No litigation declared Residential / Group Housing project

Forest Trails Athashri - B2

By PARANJAPE SCHEMES (CONSTRUCTION) LIMITED

RG-MH-01282 · RERA P52100000029 · Last updated on MahaRERA portal: 24 Jan 2025

Source: official MahaRERA filing

Red flags

  • 13 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2024Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
13Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

Forest Trails Athashri - B2 is a Residential / Group Housing project by PARANJAPE SCHEMES (CONSTRUCTION) LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100000029 on 13 Jun 2017. The registration is recorded completed; possession was promised by 31 Jul 2024. The completion date has moved by 24 months from the original filing. 13 complaints are on record with the regulator.

At a glance

Project

  • NameForest Trails Athashri - B2
  • TypeResidential / Group Housing
  • Location
    • paud road
    • Bhugaon
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000029
  • ReraGenie IDRG-MH-01282

Builder

  • NamePARANJAPE SCHEMES (CONSTRUCTION) LIMITED
  • Entity typeCompany
  • DirectorsSHRIKANT PARANJAPE, SHRIKANT PARANJAPE
  • Other registrations2 more →
  • Completed3 of 3
  • Declared earlier projects5 →

Key dates

this monthRegisteredJun 2017First promiseJul 2022Revised toJul 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on13 Jun 2017
  • Promised completion31 Jul 2024
  • Revised completionRevised to 31 Jul 2024 (originally 31 Jul 2022)
  • Buildings1 building record
  • Documents filed95 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Athashri - B2NA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Athashri - B2: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities23

As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
PHYSIO THERAPY ROOMYes0%
RESIDENT MANAGER OFFICEYes0%
SPACE OF DOCTORYes0%
MULTI PURPOSE HALLYes0%
LIBRARYYes0%
GUEST ROOMSYes20%
DININGNoNot applicable
CARD AND CARROMNoNot applicable

Parking filed334

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots334
Closed/Covered263
Open Space71

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,913 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI21157.25
Proposed, not sanctioned21,157 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
PARANJAPE SCHEMES (CONSTRUCTION) LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011849Jul 2022 → Jul 2023

Reason as filed by the promoterInvoking force majeure due to outbreak of pandemic and consequent periodic nationwide lock downs from March 2020 have caused disruption of supply chains for obtaining construction material ,labour work force migration and has impacted the pace of the construction activity adversely. Rising input costs, limited support from Banks have impacted the cash flow resulting into significant slowdown of construction .The aforementioned impediments have affected regular development of the real estate project.hence Promoter is seeking for extension

EXT52100016709Jul 2022 → Jul 2024

Reason as filed by the promoterIn accordance with Oder no 40 dated 27/12/2022 we are applying for Extension without majority consents of the allotees The aforementioned project has received adequate funding from “IDBI Trusteeship Services Limited as Debenture Trustee” (Wherein SWAMIH Investment fund is an investor which is private trust registered under SEBI acting through its trustee SBICAP trustee company limited and is a special window in the form of AIF to provide priority debt financing for completion of RERA Registered Residential projects), as substantiated by the relevant financial documentation. However, the disbur

Litigation declared3

CaseCourtStatus
186/2018/2018Civil Judge Senior Division PuneOrder below Exh Five is rejected Matter kept for issues
593/2018/2018Civil Judge Junior Division PuneApplicant has taken steps for issue of summons Report awaited
1480/2011/2011Civil Judge Senior Division PuneThe matter is kept for submitting amended plaint on Eighteen January Two Thousand Twenty Two for iss

Complaints filed with MahaRERA13

Case no.ComplainantRespondentFiled
CC005000000208295Dr.Anita Surendra ZendeParanjape Schemes Construction Limited25/02/2023
CC005000000258888Guruprasad Shivram PanditParanjpe Schemes Construction Ltd27/11/2023
CC005000000290036VINAYAK PRABHAKAR WALUJKARM/s. Paranjape Schemes Constructins Ltd.07/06/2024
CC005000000290255ASHOK MORESHWAR WAGHMAREPARANAJPE SCHEMES (CONSTRUCTION) LIMITED FORMERLY MATRIX DEVELOPERS PRIVATE LIMITED05/02/2024
CC005000000320612Dileep Gururao KulkarniParanjape Schemes Construction Limited14/03/2024
CC005000000340654Vikram Gururao KulkarniParanjape Schemes Construction Limited23/03/2024
CC005000000421093Milind Vasudeo BembalkarParanjape Schemes Consturction Limited10/06/2024
CC005000000471329Neela Vasant DeshmukhParanjape Schemes Construction Limited17/07/2024
CC005000000471507Pradeep Vitthalrao LakheParanjape Schemes (Construction) Limited)10/08/2024
CC12400207Shilpa Praktan BhandarkarPARANJAPE SCHEMES (CONSTRUCTION) LIMITED24/09/2024
CC12400985Vijay Narayan MadimanPARANJAPE SCHEMES (CONSTRUCTION) LIMITED03/12/2024
CC12503253Milind Madhusudan BhagwatPARANJAPE SCHEMES (CONSTRUCTION) LIMITED13/09/2025
CC12601016Sandhya Purushottam ShiralkarPARANJAPE SCHEMES (CONSTRUCTION) LIMITED25/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 May 2024

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4-Athashri B2-uploaded.pdf24 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4-Athashri B2-uploaded.pdf12 Nov 2024
Certificates of CA (Form 3)File: Form 3- 31Mar24-FT B2-compressed.pdf18 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Athashri B2-Sept'24-UPLOADED.pdf17 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Athashri B2-Sept'24-uploaded.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Athashri B2-FY '23-24-uploaded.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure-Sold-unsold-FT Athashri B2-June'24-uploaded.pdf20 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 28 Athashri B2-FORM 1-June'24-Uploaded.pdf9 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 21 FORM 2-Athashri B2-June'24-uploaded.pdf8 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 FT Athashri B2-FORM 2A-June'24-uploaded.pdf4 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC Athashri B2-compressed.pdf24 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Sector R26-Athashri B2-08-05-2024-Bhugaon.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: Inventory Report-Athashri B2-Mar'24-uploaded.pdf17 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Athashree B2 -Mar'24-uploaded.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-FTATHASHRI B2-Mar'24-uploaded.pdf4 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-Athashri B2-Mar'24-uploaded.pdf1 Apr 2024
Disclosure of sold/ booked inventoryFile: 6 FT B2 Athashri-Inventory disclosure-Dec'23.pdf11 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Athashree B2 A B wing-Dec'23-uplaoded.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-FTAthashri B2-Dec'23-uploaded.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A DEC 2023 ATH B2-uplaoded.pdf10 Jan 2024
Certificates of CA (Form 3)File: FORM3-Athashri B2-Sept ended-uploaded on 10Jan'24.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Athashree B2 - Form 5.pdf12 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Forest Trails Athashri B2-Sept'23-uploaded.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory Data-Forest Trails Athashri B2-Sept'23-uploaded.pdf10 Oct 2023
Certificates of CA (Form 3)File: FORM 3-CA Certificate -Forest Trails Athashri B2.pdf7 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- FT Athashree B2-Sept'23.pdf5 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 A SEPT 23 ATH B2.pdf3 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Athashree B2-June 23-uploaded.pdf11 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Athashri B2-June'23.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FT Ath B2 June 23.pdf7 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Athashree B2 A.pdf3 Jun 2023
Details of encumbrancesFile: Forest Trails Athashri -B2-Encumbrances Letter-Financial dues.pdf26 May 2023
Declaration about Commencement CertificateFile: Forest Trails Athashri- B2-Commencement Declaration.pdf26 May 2023
Declaration in FORM BFile: Forest Trails Athashri B2-FORM B.pdf26 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A-FT Athasri B2.pdf26 May 2023
Disclosure of sold/ booked inventoryFile: Forest Trails Athashri -B2-Inventory.pdf26 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 FORM 2-Forest Trails Athashri B2-Mar 23.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Athashri-B2-RERA Form-1-Mar 2023-uploaded.pdf8 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 B2 -Athashri -Form 1 -2017-Dec 2021-uploaded.pdf3 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Athashri B2-FORM 5-F Y 21-22 uploded 03Feb2023.pdf3 Feb 2023
Declaration about Commencement CertificateFile: 2 Ft B2 Compressed June 18 to Mar 19-merged compressed.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FT Athashri B2-merged -Dec 17 and Mar 18 merged compressed.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 FT B2 june 19 Dec 19 merged -compressed.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210422 FT-ATHASHRI - B2 FORM 1-Mar2021.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FT ATHASHRI - B2 RERA Form-1-june 2021.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ATHASHRI - B2_RERA FORM-1-Mar 2022 update.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FT Athashri-B2_RERA Form-1-Sept 2022.pdf25 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 FORM2-athashri b2- Sep 2017.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FT Athashri B2-June 18 to Mar 19 merged and compressed FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 FT Athashri B2 June 19 to mar 20-FORM 2-merged and compressed.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 FT Athshri B2-June 20 to March 21-FORM 2-merged and compressed.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 F T Athashri B2 June 21 to Dec21 FORM 2-merged and compressed.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 FORM2 -Athashri B2- Mar 22.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 FORM2 -Athashri B2- Sep 22.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 FORM2 -Athashri B2- Dec22.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Forest Trails Athashri B2-Form 5-Fy 18-19.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Athashree B2 2 nd Quarter ending Sept 2022.pdf28 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Mar 2019.pdf6 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Mar 2020.pdf6 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ma 2022.pdf6 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mar 2021.pdf6 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FT B2-min_compressed.pdf25 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 9 RERA Forest Trials Athashri B 2 compressed.pdf1 Apr 2021
Certificates of CA (Form 5)File: Forest Trails Athashri B2_Form 5_18-19.pdf19 Oct 2019
Copy of the legal title reportFile: Title Certificate Athashri B2 Post Merger uploded 18 oct 2019.pdf18 Oct 2019
Proforma of Allotment letterFile: AGREEMENT TO SELL Athashri B2 Post Merger Final uploaded 18 oct2019.pdf18 Oct 2019
Certificates of CA (Form 5)File: Athashri B2.pdf18 Dec 2018
Layout approvalFile: Revised Copy of Layout Approval.pdf7 Apr 2018
Building plan approvalFile: Revised Builidng Plan Approval.pdf7 Apr 2018
Copy of Layout Approval (in case of layout)File: Revised Copy of Layout Approval.pdf7 Apr 2018
Building Plan Approval (IOD)File: Revised Builidng Plan Approval.pdf7 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: Plan Permission Revised Sector B2.pdf7 Apr 2018
Declaration in FORM BFile: Athashri B2_Corrected Form B of Promoter.pdf4 Oct 2017
Proforma of Allotment letterFile: Athashri B2 - Proforma of Allotment Letter and Agreement to sell.pdf28 Sep 2017
Building plan approvalFile: SANCTION LAYOUT PAGE 1.pdf12 Jun 2017
Building plan approvalFile: SANCTION LAYOUT PAGE 2.pdf12 Jun 2017
Building plan approvalFile: Athashri B2 CC.PDF12 Jun 2017
Layout approvalFile: SANCTION LAYOUT PAGE 1.pdf12 Jun 2017
Layout approvalFile: SANCTION LAYOUT PAGE 2.pdf12 Jun 2017
Layout approvalFile: Athashri B2 CC.PDF12 Jun 2017

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Athashri - B1 R18S NO 16 AND OTHERS OPP MANAS LAKE BEHIND NIXIA LOGISTIC BHUGAON PUNE 412 115275CompletedMar 2017Mar 2016
T1-T6S NO 16 AND OTHERS OPP MANAS LAKE BEHIND NIXIA LOGISTIC BHUGAON PUNE 412 115528CompletedMar 2016Feb 2016
Servants QuartersS NO 16 AND OTHERS OPP MANAS LAKE BEHIND NIXIA LOGISTIC BHUGAON PUNE 412 11536CompletedMar 2016Late, May 2016
PebblesS NO 16 AND OTHERS OPP MANAS LAKE BEHIND NIXIA LOGISTIC BHUGAON PUNE 412 115315CompletedNov 2015Late, Aug 2016
Shopping MallS NO 16 AND OTHERS OPP MANAS LAKE BEHIND NIXIA LOGISTIC BHUGAON PUNE 412 11521CompletedMar 2015Late, Sep 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Forest Trails Athashri - B2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhugaon13,700+ in Pune

2 kmForest Trails Athashri -Completed 13Lapsed / revoked 3Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: PARANJAPE SCHEMES (CONSTRUCTION) LIMITED

PARANJAPE SCHEMES (CONSTRUCTION) LIMITED has 3 registrations on MahaRERA, including Forest Trails Athashri - B2 and Forest Trails Highland Tower 7 and 8. Its filings disclose 5 earlier MahaRERA projects: declares 2 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Forest Trails Athashri - B2 is delayed beyond 31 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Forest Trails Athashri - B2?

The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Forest Trails Athashri - B2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Forest Trails Athashri - B2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Forest Trails Athashri - B2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Forest Trails Athashri - B2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Forest Trails Athashri - B2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Forest Trails Athashri - B2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.