Home / Browse projects / Thane, Maharashtra / FENNEL G

Registered No litigation declared Residential / Group Housing project

FENNEL G

By ROYALE URBANSPACE LLP

RG-MH-09945 · RERA P51700013833 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 85%
12 of 136Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

FENNEL G is a Residential / Group Housing project by ROYALE URBANSPACE LLP in Thane, Maharashtra, registered with MahaRERA as P51700013833 on 27 Oct 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 124 of the 136 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameFENNEL G
  • TypeResidential / Group Housing
  • Location
    • SHAHAPUR
    • Kalambhe
    • Thane
    • 421601
  • Pincode421601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700013833
  • ReraGenie IDRG-MH-09945

Builder

  • NameROYALE URBANSPACE LLP
  • Entity typeOthers
  • Named personsVELGREEN LAND DEVELOPER LLP, BIMAL M.SELARKA, KOMAX BUILDCON LLP, DREAM LIFESPACE LLP, LIFESPACE BUILDCON LLP
  • Other registrations3 more →
  • Completed3 of 4

Key dates

this monthRegisteredOct 2017First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Oct 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed76 files

Current status

91%124 of 136 units booked
76.2%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
FENNEL GNA881360136

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

FENNEL G: 62% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes35%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes30%
Energy managemcntYes20%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area554 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityAssistant Director, Town Planning, Thane
Permissible FSI4259.23
Proposed, not sanctioned4,259 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIDYAVIHAR STATION ROAD
Estimated costRs 12.15 cr
Cost incurredRs 9.26 cr
Work done76.16%
BuildingWingEstimatedIncurred
FENNEL GNARs 7.44 crRs 6.70 cr
-NARs 4.72 crRs 2.56 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRIARCH DESIGN STUDIO
EngineerVINAYAK CHOPDEKAR AND ASSOCIATES
Chartered AccountantMamta Bhanushali & Associates
PartnerRole in project
ROYALE URBANSPACE LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025970Dec 2024 → Dec 2025

Reason as filed by the promoterWe humbly submit this application seeking an extension of the completion timeline for the Below is a synopsis of the challenges encountered and the reasons project named FENNEL G necessitating this request Cash Flow Challenges: Despite completing RCC work and starting finishing work, the inflow of funds from both existing and new bookings dwindled. Many customers in the Shahapur vicinity were declared NPAs, leading major banks to hait home loans for buyers reasons such as inadequate road maintenance and connectivity issues, further delaying or denying loans. Banks also in the area. Ba cited Co

EA20122518874Dec 2024 → Dec 2026

Reason as filed by the promoterThe Project land requires a proper approach road for movement of construction material, labour, machinery, equipment, and for other related access. The said approach road passes through adjoining land bearing Ghat No. 294 (part). To ensure lawful access, we executed a Right of Way Agreement on 20/01/2012 with the concerned adjoining landholders at an early stage. Pursuant to the said agreement, we had already started using and developing the access road peacefully and without obstruction for construction-related activities till or around February 2025. Intervention by Authorities and Temporary

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12605190Sachin Bandu PatilROYALE URBANSPACE LLP14/08/2026
CC12605196Bharatkumar Y AdhikariROYALE URBANSPACE LLP14/08/2026
CC12605197Anita Parveen ShettyROYALE URBANSPACE LLP14/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FOMR1 Q3 FENNEL G- 2025.pdf23 Jun 2026
Withdrawal Update Form 1File: FORM 1 Q4 March 2026.pdf23 Jun 2026
Withdrawal Update Form 1File: FORM 1 Q4 March 2026.pdf23 Jun 2026
Withdrawal Update Form 2File: FORM 2 Q3 FENNEL G-2025.pdf23 Jun 2026
Withdrawal Update Form 2File: FORM 2 Q4 March 2026.pdf23 Jun 2026
Withdrawal Update Form 2File: FORM 2 Q4 March 2026.pdf23 Jun 2026
Withdrawal Update Form 3File: FORM -3 Q3 FENNEL G-2025.pdf23 Jun 2026
Withdrawal Update Form 3File: FORM -3 Q4 MARCH 2026.pdf23 Jun 2026
Withdrawal Update Form 3File: FORM -3 Q4 MARCH 2026.pdf23 Jun 2026
Form 1File: Form 1_June 2025.pdf20 Dec 2025
Form 2File: Form 2_June 2025.pdf20 Dec 2025
Form 3File: Form 3_June 2025.pdf20 Dec 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf20 Dec 2025
Form 1File: Form 1_Sep 25.pdf20 Dec 2025
Form 2File: Form 2_Sep 25.pdf20 Dec 2025
Form 3File: Form 3_Sep 25.pdf20 Dec 2025
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf20 Dec 2025
Layout approvalFile: LAYOUT AND G BUILDING PLAN_compressed (1).pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: LAYOUT AND G BUILDING PLAN_compressed (1).pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf5 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 20-21.pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A(20-21).pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold inventory for rera wing G (1) (1).pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22.pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A(20-21).pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A(21-22).pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A( 22-23).pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (22-23).pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A(23-24).pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (23-24).pdf3 Mar 2025
Certificates of CA (Form 3)File: CA Form 3.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold inventory for rera wing G (1).pdf28 Feb 2025
Declaration in FORM BFile: FORM B (2) (2).pdf18 Feb 2025
Certificates of CA (Form 3)File: CA Certificate Form 3 Wing G(2024) (2).pdf14 Feb 2025
Declaration about Commencement CertificateFile: Declartion of CC.pdf14 Feb 2025
CERSAI detailsFile: Cersai declaration.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold inventory for rera wing G.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf17 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITE CERTIFI BLD- G (18-19).pdf26 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITE CERTIFI BLD- G (20-21).pdf26 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITE CERTIFI BLD- G (21-2022).pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIF BLD-G (18-19)_compressed.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIF BLD-G (19-20)_compressed.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIF BLD-G (20-21)_compressed.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIF BLD-G (21-22)_compressed.pdf26 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ARCHITE CERTIFI BLD- G (19-20).pdf26 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER CERTIF BLD-G (19-20)_compressed.pdf26 Jun 2023
Certificates of CA (Form 3)File: FORM 3 G 2018-2019.pdf26 Jun 2023
Certificates of CA (Form 3)File: FROM 3 G (19-20).pdf26 Jun 2023
Certificates of CA (Form 3)File: FROM 3 G (20-21).pdf26 Jun 2023
Certificates of CA (Form 3)File: FROM 3 G (22).pdf26 Jun 2023
Certificates of CA (Form 5)File: FROM 3 G (21).pdf26 Jun 2023
Certificates of CA (Form 5)File: FORM 5 G 2018-2019.pdf26 Jun 2023
Certificates of CA (Form 5)File: FORM 5 G (19-20).pdf26 Jun 2023
Certificates of CA (Form 5)File: FORM 5 G (20-21).pdf26 Jun 2023
Certificates of CA (Form 5)File: FORM 5 G (21-22).pdf26 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 G 2018-2019.pdf26 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 G (19-20).pdf26 Jun 2023
OtherFile: G RERA.pdf20 Apr 2019
OtherFile: G RERA WEBSITE.pdf20 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Fennel G Architects.pdf17 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Fennel G compressed.pdf17 Apr 2019
Certificates of CA (Form 3)File: FENNEL G FORM 3 MARCH 2018.pdf17 Apr 2019
Certificates of CA (Form 5)File: CA chanchal Bhandari Form 5 for Fennel G.pdf17 Apr 2019
Declaration in FORM BFile: Form - B (G Bldg) new.pdf23 Oct 2017
Certificates of CA (Form 3)File: CA CERTIFICATE (G-TYPE) new.pdf23 Oct 2017
Proforma of Allotment letterFile: Royal City (G) final freeze.pdf23 Oct 2017
Copy of the legal title reportFile: TITLE REPORT.pdf1 Aug 2017
Building plan approvalFile: SEC II.pdf29 Jul 2017
Details of encumbrancesFile: INDEX 2 (FOR SECTOR 2).pdf29 Jul 2017
Building Plan Approval (IOD)File: SEC II.pdf29 Jul 2017
Layout approvalFile: LAYOUT PLAN.PDF21 Jul 2017
PAN CardFile: pan card of Royale Urbanspace LLP 001.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.PDF21 Jul 2017

How this compares with Thane

91%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep FENNEL G on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHAHAPUR7,600+ in Thane

2 kmFENNEL GCompleted 12Lapsed / revoked 9Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: ROYALE URBANSPACE LLP

ROYALE URBANSPACE LLP has 4 registrations on MahaRERA, including ORCHID and FENNEL H. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if FENNEL G is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of FENNEL G?

The registered promoter entity is ROYALE URBANSPACE LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in FENNEL G?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against FENNEL G?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for FENNEL G?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at FENNEL G?

The professionals named in the filing: Architect: TRIARCH DESIGN STUDIO; Engineer: VINAYAK CHOPDEKAR AND ASSOCIATES; Chartered Accountant: Mamta Bhanushali & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FENNEL G?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FENNEL G. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FENNEL G to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.