Home / Browse projects / Raigarh, Maharashtra / EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1

Registration lapsed No litigation declared Others project

EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1

By Xrbia Developers Ltd

RG-MH-57099 · RERA P52000007138 · Last updated on MahaRERA portal: 15 Aug 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • 11 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
12 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 70%
11Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 is a Others project by Xrbia Developers Ltd in Raigarh, Maharashtra, registered with MahaRERA as P52000007138 on 17 Aug 2017. Possession was promised by 30 Mar 2023 and is now 43 months past that date. 11 complaints are on record with the regulator.

At a glance

Project

  • NameEXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1
  • TypeOthers
  • Location
    • Madap
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000007138
  • ReraGenie IDRG-MH-57099

Builder

  • NameXrbia Developers Ltd
  • Entity typeCompany
  • Other registrations9 more →
  • No longer live10 lapsed, de-registered or revoked

Key dates

43 months past promisethis monthRegisteredAug 2017PromisedMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion30 Mar 2023
  • Revised completionNone
  • Buildings4 building records
  • Documents filed41 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PP3NA80000
QQ12NA80000
QQ16NA80000
QQ21NA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 15 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 70%.

PP330%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure31%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
QQ1241%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises18%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
QQ1634%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure53%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks17%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
QQ2141%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises19%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities18

As on 15 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Basket Ball CourtYes0%
Cricket PitchYes0%
Tennis CourtYes0%

Parking filed61

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots61
Open Space61
BuildingOpen SpaceTotal
PP31515
QQ121515
QQ161515
QQ211616

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,493 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI26278.0
Proposed, not sanctioned15,840 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1,2,Platinum Shree Chintamani CHS,Sector 14,Plot No 18,Sanpada ,Mumbai

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Gade
PartnerRole in project
Xrbia Developers Ltd-

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC006000000198866sarvesh guptaRahul Nahar12/11/2021
CC006000000089535SAGAR HAVALKARAN RAJIVKUMAR KARNAWAT31/05/2019
CC006000000194778Pradip Hanumant PawarXrbia Builders Limited04/11/2020
CC006000000196635Anil Kumar GuptaXrbia Developers Ltd05/04/2021
CC006000000209656MEHERNOSH B MISTRYXRBIA DEVELOPERS LTD11/01/2022
CC006000000354490BHALCHANDRA VASANT GOKHALEXRBIA DEVELOPERS LIMITED12/04/2023
CC006000000395965DIAGO FRANCIS MARTINSXRBIA DEVELOPERD LTD.14/06/2023
CC006000000397317Daylan DsouazXrbia Developers Limited07/09/2023
CC006000000397885Vinay NairXrbia Developers Limited18/10/2023
CC006000000397921ISMAIL IBRAHIM NAIKXRBIA DEVELOPERS PVT. LTD.20/10/2023
CC12400875Yogesh Pratap SinghXrbia Developers Ltd23/11/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: EKW_CC_Declaration.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: EKW_Ph1_Sold Unit Declaration_090821.pdf15 Aug 2021
Proforma of Allotment letterFile: EKW Ph 1_Draft_.pdf5 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Express City_Form 5_Ph 1_31032020.pdf28 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Express City_Ph 1_Form 5.pdf2 Jan 2020
Details of encumbrancesFile: EXPRESS-PH 1.pdf2 Nov 2018
Certificates of CA (Form 5)File: Express City_Form 5_Ph 1.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: NA_CC.pdf26 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ph_1_Engineers Certificate.pdf7 Aug 2017
Certificates of CA (Form 3)File: Ph_1_CA Certificate.pdf7 Aug 2017
Layout approvalFile: Sanction Plan.pdf6 Aug 2017
Building plan approvalFile: NA_CC.pdf6 Aug 2017
Building plan approvalFile: 2BHK_Sanctioned.pdf6 Aug 2017
Building plan approvalFile: 3BHK_Sanctioned.pdf6 Aug 2017
Copy of the legal title reportFile: TSR_Part_1.pdf6 Aug 2017
Copy of the legal title reportFile: TSR_Part_2.pdf6 Aug 2017
Copy of the legal title reportFile: TSR_Part_3.pdf6 Aug 2017
Copy of the legal title reportFile: TSR_Part_4.pdf6 Aug 2017
Details of encumbrancesFile: Ph_1_Encumbarances.pdf6 Aug 2017
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf6 Aug 2017
Building Plan Approval (IOD)File: NA_CC.pdf6 Aug 2017
Building Plan Approval (IOD)File: 2BHK_Sanctioned.pdf6 Aug 2017
Building Plan Approval (IOD)File: 3BHK_Sanctioned.pdf6 Aug 2017
Declaration in FORM BFile: Ph_1_Form B.pdf6 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ph_1_Architect Certificate.pdf6 Aug 2017
Proforma of Allotment letterFile: Ph_1_Declaration for Agreement as per Rera.pdf6 Aug 2017
OtherFile: Ph_1_Future Buildings etc.pdf6 Aug 2017
OtherFile: Proposed Plan.pdf6 Aug 2017
OtherFile: Proposed Larger Layout.pdf6 Aug 2017
OtherFile: 1Rera_2 BHK - 1_Proposed Unit Plan_12.pdf6 Aug 2017
OtherFile: 2Rera_2 BHK - 1_Proposed Unit Plan_14.pdf6 Aug 2017
OtherFile: 3Rera_2 BHK - 2_Proposed Unit Plan_12.pdf6 Aug 2017
OtherFile: 4Rera_2 BHK - 2_Proposed Unit Plan_14.pdf6 Aug 2017
OtherFile: 5Rera_2 BHK - 2A_Proposed Unit Plan_12.pdf6 Aug 2017
OtherFile: 6Rera_2 BHK - 2A_Proposed Unit Plan_14_.pdf6 Aug 2017
OtherFile: 1_3_BHK_Proposed_Lower Floor Plan_.pdf6 Aug 2017
OtherFile: 2_3_BHK_Proposed_Upper Floor Plan_.pdf6 Aug 2017
OtherFile: 3_Rera_3 BHK - 1_Proposed Unit Plan_.pdf6 Aug 2017
OtherFile: 4_Rera_3 BHK - 2_Proposed Unit Plan_.pdf6 Aug 2017
OtherFile: 5_Rera_3 BHK - 3_Proposed Unit Plan_.pdf6 Aug 2017
OtherFile: 6_Rera_3 BHK - 4_Proposed Unit Plan.pdf6 Aug 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Madap5,900+ in Raigarh

2 kmEXPRESS CITY/KHOPOLI WOOCompleted 37Lapsed / revoked 27Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: Xrbia Developers Ltd

Xrbia Developers Ltd has 10 registrations on MahaRERA, including First City and Xrbia Vangani Ph 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1?

The registered promoter entity is Xrbia Developers Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1?

The professionals named in the filing: Architect: Ajay Gade. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EXPRESS CITY/KHOPOLI WOODS/NEW LONAVALA-PH-1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.