ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / EXCELLANZAA

Completed No litigation declared Residential / Group Housing project

EXCELLANZAA

By SHANTANU REALTORS

RG-MH-27260 · RERA P52000008939 · Last updated on MahaRERA portal: 14 Dec 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

EXCELLANZAA is a Residential / Group Housing project by SHANTANU REALTORS in Raigarh, Maharashtra, registered with MahaRERA as P52000008939 on 19 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 27 months from the original filing.

At a glance

Project

  • NameEXCELLANZAA
  • TypeResidential / Group Housing
  • Location
    • SECTOR - 6
    • Karanjade
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000008939
  • ReraGenie IDRG-MH-27260

Builder

  • NameSHANTANU REALTORS
  • Entity typeOthers
  • Named personSHANTANU REALTORS

Key dates

this monthRegisteredAug 2017First promiseMar 2021Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Mar 2021)
  • Buildings1 building record
  • Documents filed68 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EXCELLANZAANA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

EXCELLANZAA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed57

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots57
Closed/Covered52
Open Space5

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,450 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3674.0
Proposed, not sanctioned3,674 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchplot no 13 central facility building no 2 APMC Market sector 19 vashi navi mumbai 400705

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectD G SHAH AND ASSOCIATES
EngineerCSE CONSULTANTS
PartnerRole in project
SHANTANU REALTORS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000012099Mar 2021 → Dec 2022

Reason as filed by the promoterThe Percentage of work Completed is 100% & awaiting for occupation certificate, which is pending due to non-availability of the officials. I request the authority to grant extension pursuant to section 7(3) for SIX Months till 31-12-2022 under power of athorise official.

EXT52000013086Mar 2021 → Jun 2023

Reason as filed by the promoterAwaiting for Occupancy Certificate

EXT52000009912Mar 2021 → Dec 2021

Reason as filed by the promoterAll the Paper Work & submission done.. Now Waiting for Occupancy Certificate..

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Nov 2023

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECT.pdf14 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FROM -2A 2021-22.pdf29 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FROM -2A 2022-23.pdf29 Nov 2023
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD - BOOKED INVENTORY.pdf29 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 ANNUAL REPORT F Y 22 23.pdf29 Nov 2023
Proforma of Agreement for saleFile: AGREEMENT TO SELL - DRAFT.pdf29 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE.pdf29 Nov 2023
CERSAI detailsFile: CERSAI REPORT.pdf21 Jun 2023
CERSAI detailsFile: CERSAI REPORT.pdf13 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL REPORT.pdf13 Dec 2022
CERSAI detailsFile: CERSAI.pdf24 Jun 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration.pdf17 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ANNUAL REPORT.pdf9 May 2022
Declaration about Commencement CertificateFile: FORMAT D.pdf15 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 19-20.pdf15 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5.pdf15 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5.pdf15 Jul 2021
OtherFile: FORMAT B.pdf15 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Eng cert.pdf8 Jul 2021
Disclosure of sold/ booked inventoryFile: Corrigandum.pdf8 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 18-19.pdf8 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 19-20.pdf8 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf15 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE -2.pdf15 Jun 2021
OtherFile: FORMAT D.pdf15 Jun 2021
Copy of the legal title reportFile: TITLE - CUM SEARCH REPORT-(1).pdf6 Apr 2018
Declaration in FORM BFile: FORM B.pdf27 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf27 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE.pdf27 Jan 2018
Certificates of CA (Form 3)File: CA CERTIFICATE FORM 3.pdf27 Jan 2018
Proforma of Allotment letterFile: AGREEMENT TO SELL - DRAFT - Revised.pdf27 Jan 2018
Building plan approvalFile: PLAN1213.pdf30 Jul 2017
Building plan approvalFile: PLAN11.pdf30 Jul 2017
Building plan approvalFile: GROUND FLOOR.pdf30 Jul 2017
Building plan approvalFile: PLAN8.pdf30 Jul 2017
Building plan approvalFile: SECTION PLAN.pdf30 Jul 2017
Building plan approvalFile: PLAN10.pdf30 Jul 2017
Building plan approvalFile: PLAN3579.pdf30 Jul 2017
Building plan approvalFile: PLAN46.pdf30 Jul 2017
Building plan approvalFile: ELEVATION PLAN.pdf30 Jul 2017
Building plan approvalFile: PLAN1.pdf30 Jul 2017
Building plan approvalFile: PLAN2.pdf30 Jul 2017
Building plan approvalFile: PLAN2.pdf30 Jul 2017
Layout approvalFile: GROUND FLOOR.pdf30 Jul 2017
PAN CardFile: KAMLESH SHAH PAN CARD.pdf30 Jul 2017
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf30 Jul 2017
Details of encumbrancesFile: DECLARATION FOR ENCUMBRANCES.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: GROUND FLOOR.pdf30 Jul 2017
Building Plan Approval (IOD)File: GROUND FLOOR.pdf30 Jul 2017
Building Plan Approval (IOD)File: SECTION PLAN.pdf30 Jul 2017
Building Plan Approval (IOD)File: ELEVATION PLAN.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN1.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN2.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN2.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN3579.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN46.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN8.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN10.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN11.pdf30 Jul 2017
Building Plan Approval (IOD)File: PLAN1213.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERIFICATE.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: DECLARATION FOR REV CC.pdf30 Jul 2017
Declaration in FORM BFile: FORM B AFFIDAVIT CUM DECLARATION.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf30 Jul 2017
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.pdf30 Jul 2017
Proforma of Allotment letterFile: AGREEMENT TO SELL - DRAFT (1).pdf30 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER - DRAFT.pdf30 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 27 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EXCELLANZAA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karanjade5,900+ in Raigarh

2 kmEXCELLANZAACompleted 207Lapsed / revoked 54Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 356 registered projects within 2 km.

Builder: SHANTANU REALTORS

SHANTANU REALTORS has 1 registration on MahaRERA, including EXCELLANZAA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if EXCELLANZAA is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EXCELLANZAA?

The registered promoter entity is SHANTANU REALTORS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EXCELLANZAA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EXCELLANZAA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EXCELLANZAA?

The professionals named in the filing: Architect: D G SHAH AND ASSOCIATES; Engineer: CSE CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EXCELLANZAA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EXCELLANZAA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EXCELLANZAA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.