RG-MH-26544 · RERA P52100014266 · Last updated on MahaRERA portal: 31 Dec 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 98%
4 of 44Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

EXCEL CELESTIA RESIDENCY is a Residential / Group Housing project by EXCEL HOUSING in Pune, Maharashtra, registered with MahaRERA as P52100014266 on 17 Nov 2017. The registration is recorded completed; possession was promised by 30 Dec 2023. The completion date has moved by 24 months from the original filing. 40 of the 44 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameEXCEL CELESTIA RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • PUNE
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014266
  • ReraGenie IDRG-MH-26544

Builder

  • NameEXCEL HOUSING
  • Entity typePartnership
  • PartnersRAJU HIRAMAN SASTE, DEEPAK HIRAMAN SASTE
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredNov 2017First promiseDec 2021Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Nov 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed51 files

Current status

91%40 of 44 units booked
98.3%Work done, per cost certificate

Figures as on 31 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CORONA RESIDENCY D WINGNA151444044

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.

CORONA RESIDENCY D WING: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 31 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes20%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,847 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Sep 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI3069.0
Proposed, not sanctioned3,069 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAAROH DWELLING SHOP 7 8 9 DATTANGAR AMBEGAON PUNE 411046
Estimated costRs 6.90 cr
Cost incurredRs 6.79 cr
Work done98.3%
BuildingWingEstimatedIncurred
CORONA RESIDENCY D WINGNARs 6.61 crRs 6.61 cr
-NARs 29.25 lakhRs 17.55 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMRS USHA RANGRAJAN
EngineerPravin B More
Chartered AccountantVishank Chaudhari
PartnerRole in project
EXCEL HOUSING-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011251Dec 2021 → Mar 2022

Reason as filed by the promoterdue to lock down and lack of material we couldn't complete the project within time, we have already completed 90% construction work of the excel celestia Residency project

EXT52100012175Dec 2021 → Sep 2022

Reason as filed by the promoterDear sir , As per Rera Authority Guideline we are apply for Project completion date extend upto 31/03/2023 as per Extension under section 7(3) ,Project delay due to Covid-19 Lockdown effect shortage of labour and material till date project building work upto 90 % completed as per section 7(3) we have taken 51% consent of Sold unit pls consider my request and extend proposed completion date . Thank you

EXT52100015128Dec 2021 → Dec 2023

Reason as filed by the promoterDue To completion certificate not Received from Corporation

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 30 06 2023.pdf31 Dec 2025
Form 2File: Form 2 30 06 2023.pdf31 Dec 2025
Form 3File: Form 3 30 06 2023.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 30 06 2023 (1).pdf31 Dec 2025
Form 2A (FY 2019-2020)File: Form -2A D wing 2019-20.pdf20 Nov 2025
Form 2A (FY 2020-2021)File: Form -2A D wing 2020-21.pdf20 Nov 2025
Form 2A (FY 2021-2022)File: Form -2A D wing 2021-22.pdf20 Nov 2025
Form 2A (FY 2022-2023)File: Form -2A D wing -2022-23.pdf20 Nov 2025
Form 2A (FY 2023-2024)File: Form -2A D wing 2023-24.pdf20 Nov 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: EXCELL 2A.pdf14 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 EXCELL.pdf14 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (1).pdf12 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Excel D F2 June 23.pdf9 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan 12-Jul-2023.pdf3 Aug 2023
Certificates of CA (Form 3)File: FORM - 3 EXCEL HOUSING.pdf3 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate D Building.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC CERTIFICATE 31-May-2023 10-59 am (1).pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan 12-Jul-2023.pdf29 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Wing D.pdf29 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of SoldUnsold Inventory Wing D.pdf29 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD31-May-2023 10-58 am.pdf29 Jul 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 WING D_compressed.pdf29 Jul 2023
Certificates of CA (Form 3)File: FORM - 3 EXCEL HOUSING_compressed.pdf29 Jul 2023
Declaration in FORM BFile: Form B.pdf6 Jun 2023
Certificates of CA (Form 3)File: FROM-3_compressed.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter For Rera D wing Excel Housing.pdf1 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate 27june22_compressed.pdf1 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 19-20.pdf1 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclousre of Sold_Booked Inventory Final 27June22_compressed.pdf1 Jul 2022
CERSAI detailsFile: D wing CERSAI_Search_Report_.pdf2 Feb 2022
Declaration about Commencement CertificateFile: D Declration.pdf23 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: D Engg 2A_compressed.pdf23 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: D 18-19_compressed.pdf16 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: D 19-20_compressed.pdf16 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: D 20-21_compressed.pdf16 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate D Wing-2019_compressed.pdf12 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate D wing for RERA (1).pdf12 Nov 2021
Building plan approvalFile: pLAN _compressed.pdf8 Sep 2021
Building Plan Approval (IOD)File: pLAN _compressed.pdf8 Sep 2021
Disclosure of sold/ booked inventoryFile: Disclousre of Sold_Booked Inventory.pdf8 Sep 2021
Certificates of CA (Form 3)File: C A Certificate.PDF14 Nov 2017
Proforma of Allotment letterFile: Flat AGREEMENT and allotment letter.pdf14 Nov 2017
Building plan approvalFile: D Wing Plan.pdf13 Nov 2017
Layout approvalFile: Layout.pdf13 Nov 2017
PAN CardFile: excel pancard.pdf13 Nov 2017
Copy of the legal title reportFile: collective Search.pdf13 Nov 2017
Details of encumbrancesFile: encumbrances letter.pdf13 Nov 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf13 Nov 2017
Building Plan Approval (IOD)File: D Wing Plan.pdf13 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf13 Nov 2017
Declaration in FORM BFile: form b.pdf13 Nov 2017

How this compares with Pune

91%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EXCEL CELESTIA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

2 kmEXCEL CELESTIA RESIDENCYCompleted 44Lapsed / revoked 22Other 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: EXCEL HOUSING

EXCEL HOUSING has 3 registrations on MahaRERA, including EXCEL CELESTIA RESIDENCY and EXCEL CELESTIA RESIDENCY WING B AND C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if EXCEL CELESTIA RESIDENCY is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EXCEL CELESTIA RESIDENCY?

The registered promoter entity is EXCEL HOUSING, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EXCEL CELESTIA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EXCEL CELESTIA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EXCEL CELESTIA RESIDENCY?

The professionals named in the filing: Architect: MRS USHA RANGRAJAN; Engineer: Pravin B More; Chartered Accountant: Vishank Chaudhari. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EXCEL CELESTIA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EXCEL CELESTIA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EXCEL CELESTIA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.