ESSAR APEX
By ARSIWALA CONSTRUCTIONS PRIVATE LIMITED
RG-MH-73707 · RERA P99000010587 · Last updated on MahaRERA portal: 8 Aug 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 54 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ESSAR APEX is a Others project by ARSIWALA CONSTRUCTIONS PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000010587 on 31 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameESSAR APEX
- TypeOthers
- Location
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401303
- Pincode401303
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000010587
- ReraGenie IDRG-MH-73707
Builder
- NameARSIWALA CONSTRUCTIONS PRIVATE LIMITED
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed66 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ESSAR APEX | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
ESSAR APEX: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 8 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADA & ASSOCIATES |
| Engineer | SHAH GATTANI CONSULTANT |
| Partner | Role in project |
|---|---|
| ARSIWALA CONSTRUCTIONS PRIVATE LIMITED | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn this regards we like to state that our construction work at site is completed 100% and we have also given possession to few flat holders, but due to Covid-19 pandemic and Lockdown situation, we are awaiting clearance documents from Environment and other competent authorities, which is required for getting Occupancy certificate from Vasai Virar City Municipal Corporation.
Reason as filed by the promoterDate: 25th August, 2023. To, The Maharashtra Real Estate Regulatory Authority (RERA) Mumbai Dear Sir/Madam, Sub: Application for Extension of Project Ref: ARSIWALA CONSTRUCTIONS (P) LTD REG No: P99000010587 We herby apply for extension of the Project Name Essar Apex registered with the regulatory authority vide project registration certificate bearing No. P99000010587 which expires on 30th June, 2023. In this regards we like to state that our Majority of our construction work completed and only minor finishing works and some of the amenity’s work, Premises Land PCC and tree plantation work is
Reason as filed by the promoterDate: 02th August, 2024 To, The Maharashtra Real Estate Regulatory Authority (RERA) Mumbai Dear Sir/Madam, Sub: Application for Extension of Project Ref: ARSIWALA CONSTRUCTIONS (P) LTD REG No: P99000010587 We herby apply for extension of the Project Name Essar Apex registered with the regulatory authority vide project registration certificate bearing No. P99000010587 which expired on 31st May, 2024. In this regards we like to state that our Majority of our construction work completed and only minor finishing works and some of the amenity’s work, Premises Land PCC and tree plantation work is pe
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000089711 | Abhishek Kumar Srivastava | Fakruddin Arsiwala | 12/06/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Affidavit for Extn.pdf | 8 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate_31_03_2024.pdf | 8 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate_30_06_2024.pdf | 8 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_31_03_2024.pdf | 8 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_30_06_2024.pdf | 8 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Engineer_2023_24.pdf | 8 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_ Booked Inventory.pdf | 8 Aug 2024 |
| Certificates of CA (Form 3)File: From No-3_23_24.pdf | 8 Aug 2024 |
| Certificates of CA (Form 3)File: Form No-3_30_06_24.pdf | 8 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form No 5 FY 2023_24.pdf | 8 Aug 2024 |
| Declaration in FORM BFile: Affidavit Fakhruddin Arsiwala.pdf | 3 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate_compressed.pdf | 3 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf | 3 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Site Engineers certificate_compressed.pdf | 3 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate (22-23).pdf | 30 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (2022-23).pdf | 30 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Site Engineer Certificate (22-23).pdf | 30 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD (1).pdf | 30 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 - Essar Apex.pdf | 30 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No-5 (22-23)_compressed.pdf | 30 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: Declaration for Encrubance.pdf | 24 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Declaration for Encrubance.pdf | 24 Feb 2023 |
| CERSAI detailsFile: CERSAI.pdf | 24 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouse for Interest other Co.pdf | 24 Feb 2023 |
| Proforma of Agreement for saleFile: 2 Proforma of Allotment letter.pdf | 24 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Deviation.pdf | 24 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Seperate account.pdf | 24 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: Declaration for Deviation.pdf | 24 Feb 2023 |
| Deviation Report with respect to model copy of AgreementFile: Declaration for Deviation.pdf | 24 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate (21-22)_compressed.pdf | 21 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (2021-22).pdf | 21 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Site Engineer Cetificate (21-22)_compressed.pdf | 21 Feb 2023 |
| Certificates of CA (Form 3)File: Form-3 Arsiwala Constructions (2021-22)_compressed.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form No-5 (2021-22).pdf | 21 Feb 2023 |
| Declaration about Commencement CertificateFile: Commencement Certificate NEW1.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 27 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaraion for CC.pdf | 23 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 18-19.pdf | 23 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 19-20.pdf | 23 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 20-21.pdf | 23 Sep 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 18-19.pdf | 23 Sep 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 19-20.pdf | 23 Sep 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 20-21.pdf | 23 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Site Engineer Certificate 19-20.pdf | 23 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Site Engineer Certificate 20-21.pdf | 23 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: Inventry Details.pdf | 23 Sep 2021 |
| Certificates of CA (Form 3)File: from 3 31-03-2019_compressed.pdf | 23 Sep 2021 |
| Certificates of CA (Form 3)File: form 3 31-03-2020_compressed.pdf | 23 Sep 2021 |
| Certificates of CA (Form 3)File: form 3 31-03-2021_compressed.pdf | 23 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: From No-5 (18-19).pdf | 23 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form No-5 (19-20).pdf | 23 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form No-5 (20-21).pdf | 23 Sep 2021 |
| Certificates of CA (Form 5)File: Form No 5.pdf | 13 Oct 2018 |
| Certificates of CA (Form 3)File: CA Cert001.pdf | 16 Aug 2017 |
| Layout approvalFile: Flor Plan 1.pdf | 14 Aug 2017 |
| Building plan approvalFile: Flor Plan 2.pdf | 14 Aug 2017 |
| PAN CardFile: Pan.pdf | 14 Aug 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 14 Aug 2017 |
| Details of encumbrancesFile: No Encrumbrance.pdf | 14 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Flor Plan 1.pdf | 14 Aug 2017 |
| Building Plan Approval (IOD)File: Flor Plan 2.pdf | 14 Aug 2017 |
| Declaration in FORM BFile: Form B (Self Declaration).pdf | 14 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf | 14 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 14 Aug 2017 |
| Proforma of Allotment letterFile: Allotement Letter.pdf | 14 Aug 2017 |
| Proforma of Allotment letterFile: Model Agreement.pdf | 14 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ESSAR APEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar
Filed coordinates, straight-line distance. 155 registered projects within 2 km.
Mayfair Virar Gardens Cluster-VI
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS CLUSTER IV
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19,
MAYFAIR HOUSING
Agarwal Infinity
Laxminarayan Prabhudayal Agarwal
GOKUL HARI ANANTA
Mehta Ventures
GOKUL NAKSHATRA II
JSB HOMEMAKERS PRIVATE LIMITED
See every Palghar project, with the district possession charts
Builder: ARSIWALA CONSTRUCTIONS PRIVATE LIMITED
ARSIWALA CONSTRUCTIONS PRIVATE LIMITED has 1 registration on MahaRERA, including ESSAR APEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that ESSAR APEX shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ESSAR APEX is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ESSAR APEX?
The registered promoter entity is ARSIWALA CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ESSAR APEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ESSAR APEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ESSAR APEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ESSAR APEX?
The professionals named in the filing: Architect: AJAY WADA & ASSOCIATES; Engineer: SHAH GATTANI CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ESSAR APEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback