Home / Browse projects / Raigarh, Maharashtra / ENKAY GARDEN - LOTUS C

Registration lapsed No litigation declared Residential / Group Housing project

ENKAY GARDEN - LOTUS C

By BHUPESHBABU KARAPPAN NILLIPARAMBIL

RG-MH-75849 · RERA P52000009049 · Last updated on MahaRERA portal: 27 Feb 2020

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 18 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 80%
18Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

ENKAY GARDEN - LOTUS C is a Residential / Group Housing project by BHUPESHBABU KARAPPAN NILLIPARAMBIL in Raigarh, Maharashtra, registered with MahaRERA as P52000009049 on 19 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 18 complaints are on record with the regulator.

At a glance

Project

  • NameENKAY GARDEN - LOTUS C
  • TypeResidential / Group Housing
  • Location
    • WAVANJE VILLAGE ROAD
    • Vavanje
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000009049
  • ReraGenie IDRG-MH-75849

Builder

  • NameBHUPESHBABU KARAPPAN NILLIPARAMBIL
  • Entity typeIndividual
  • Other registrations9 more →
  • No longer live10 lapsed, de-registered or revoked

Key dates

34 months past promisethis monthRegisteredAug 2017PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1 - LOTUS 1NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

BUILDING 1 - LOTUS 1: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes30%
Street LightingYes60%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,085 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO- NAINA
Permissible FSI6871.5
Proposed, not sanctioned4,064 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASHI NAVI MUMBAI

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Abhijit Shashikant Mohite
ArchitectSWAPNIL KALYANKAR
EngineerMr. Sunil Kagade
EngineerMOHD. ATHESHAM ANSARI
Chartered AccountantANIL DUTTA
Chartered AccountantARPIT BOHRA

Litigation declared1

CaseCourtStatus
67/2015/2015JMFC PANVELAwaiting some a report

Complaints filed with MahaRERA18

Case no.ComplainantRespondentFiled
CC006000000001933PUSHPARAJAN S. NAIRN.K.BHUPESHBABU, PROPRIETOR, M/S.ENKAY CASTLE,22/12/2017
CC006000000012525Prabir S LahiriN K Bhupesh Babu16/02/2018
CC006000000023518MR. SUNIL NAMDEO BAGADEMR.N.K.BHUPESHBABU26/03/2018
CC006000000023359AJAY SONIMR.N.K.BHUPESHBABU26/02/2018
CC006000000054792savio rosa thomasbhupeshbabu karappan nilliparambil06/06/2018
CC006000000055205MR.RAHUL KUMARMR.N.K.BHUPESH BABU14/09/2018
CC006000000055869GANESH A KUMBHARM/S.ENKAY GARDEN-LOTUS C26/08/2018
CC006000000056866GAJANAN TRIMBAK NADEM/S.ENKAY GARDEN LOTUS C17/11/2018
CC006000000251725SUNIL NAMDEO BAGADEN.K.BHUPESHBABU, PROPRIETOR OF M/s.ENKAY CASTLE05/07/2022
CC006000000251926RAMESH BAJIRAO SABLEN.K.BHUPESHBABU, PROPRIETOR OF M/s.ENKAY CASTLE14/07/2022
CC006000000251898AJAY SONIN.K.BHUPESHBABU, PROPRIETOR OF M/s.ENKAY CASTLE13/07/2022
CC006000000375218Srikanta Kumar PanigrahySrikanta Kumar Panigrahy11/04/2023
CC006000000396447DILIP SADANAND PARABN.K.BHUPESHBABU, Proprietor ENKAY CASTLE27/06/2023
CC006000000396538UTTAM DASN.K.BHUPESHBABU PROPRIETOR, M/S. ENKAY CASTLE04/07/2023
CC006000000396588VARUGHESE CHERIANN.K.BHUPESHBABU, Proprietor ENKAY CASTLE06/07/2023
CC006000000397437Mohamed Farooque DeshmukhM/s. Enkay Garden through its proprietor Mr. Bhupeshbabu Karappan Nilliparambil09/09/2023
CC006000000428997Vijay Kumar1. MIS Enkay Castle, 2.Mr. N.K.Bhupeshbabu, 3.Mrs.Preeta Bhupeshbabu17/03/2024
CC12400886LEENA PRAFUL PATELBHUPESHBABU KARAPPAN NILLIPARAMBIL25/11/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: LOTUS C.pdf27 Feb 2020
Certificates of CA (Form 5)File: Lotus-C.pdf15 Oct 2018
Certificates of CA (Form 3)File: Phase-2 Lotus-C-ilovepdf-compressed.pdf30 Mar 2018
Building plan approvalFile: Plan_Lotus_C.pdf31 Jul 2017
Layout approvalFile: Ph-II Approved Layout.pdf31 Jul 2017
PAN CardFile: PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: Ph-II Title Certificate.pdf31 Jul 2017
Details of encumbrancesFile: NEC_Lotus_C.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Ph-II Approved Layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: Plan_Lotus_C.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Ph-II CC.pdf31 Jul 2017
Declaration in FORM BFile: Form B_Lotus_C.PDF31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EG-Ph-II_Arch Certificate_Lotus_C.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EG-Ph-II_Eng Certificate_Lotus_C.pdf31 Jul 2017
Certificates of CA (Form 3)File: EG-Ph_II_CA Certificate_LOTUS_C.pdf31 Jul 2017
Proforma of Allotment letterFile: AL_Lotus_C.pdf31 Jul 2017
Proforma of Allotment letterFile: Ph-II_AFS.pdf31 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ENKAY GARDEN - LOTUS C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vavanje5,900+ in Raigarh

2 kmENKAY GARDEN - LOTUS CCompleted 3Lapsed / revoked 9Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: BHUPESHBABU KARAPPAN NILLIPARAMBIL

BHUPESHBABU KARAPPAN NILLIPARAMBIL has 10 registrations on MahaRERA, including Enkay Garden - ROSE and ENKAY GARDEN - ZENIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that ENKAY GARDEN - LOTUS C shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ENKAY GARDEN - LOTUS C is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ENKAY GARDEN - LOTUS C?

The registered promoter entity is BHUPESHBABU KARAPPAN NILLIPARAMBIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ENKAY GARDEN - LOTUS C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ENKAY GARDEN - LOTUS C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ENKAY GARDEN - LOTUS C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ENKAY GARDEN - LOTUS C?

The professionals named in the filing: Architect: Mr. Abhijit Shashikant Mohite; Architect: SWAPNIL KALYANKAR; Engineer: Mr. Sunil Kagade; Engineer: MOHD. ATHESHAM ANSARI; Chartered Accountant: ANIL DUTTA; Chartered Accountant: ARPIT BOHRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ENKAY GARDEN - LOTUS C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ENKAY GARDEN - LOTUS C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ENKAY GARDEN - LOTUS C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.