Home / Browse projects / Pune, Maharashtra / EMINENCE PROJECT 1

Completed No litigation declared Residential / Group Housing project

EMINENCE PROJECT 1

By NAIKNAVARE DEVELOPERS PVT LTD

RG-MH-10495 · RERA P52100001061 · Last updated on MahaRERA portal: 6 Nov 2024

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
17 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
4Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

EMINENCE PROJECT 1 is a Residential / Group Housing project by NAIKNAVARE DEVELOPERS PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100001061 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2022. The completion date has moved by 36 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameEMINENCE PROJECT 1
  • TypeResidential / Group Housing
  • Location
    • VIMAN NAGAR
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001061
  • ReraGenie IDRG-MH-10495

Builder

  • NameNAIKNAVARE DEVELOPERS PVT LTD
  • Entity typeCompany
  • Managing DirectorHEMANT DATTAJI NAIKNAVARE
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects5 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Jul 2017
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed106 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLDG ANA90000
CLUB HOUSENA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

BLDG A98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
CLUB HOUSE91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes95%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes95%

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered78
Open Space6

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,427 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5500.0
Proposed, not sanctioned5,108 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch885 BHANDARKAR ROAD OPP SANE DAIRY PUNE 4

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGAURI NAIKNAVARE
EngineerKRUPALI KADAM
PartnerRole in project
NAIKNAVARE DEVELOPERS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005323Dec 2019 → Dec 2020

Reason as filed by the promoterOur project “Eminence” is registered with regulatory authority vide project registration certificate bearing No P52100001061. During the implementation of the project, the Pune Municipal Corporation required the NOC from for construction of building for a height of 36 M AGL or 606 M AMSL from the concern authority. Accordingly, the Promoter has applied to Survey of India on 16.04.2018 for its report on Aerial distance and AMSL heights of site for the purpose of Airport NOC. Upon receipt of report of Survey of India on 08.10.2018, the Promoter has applied to SATCO Airforce Station Lohagaon on 2

EXT52100009869Dec 2019 → Jun 2022

Reason as filed by the promoterWe have registered our Project EMINENCE No. P521000001061 under RERA. The completion date for the project is 30 TH JUNE 2021. But considering the COVID-19 situation, we are unable to complete our Project due to various reasons mentioned as under. As you are aware, due to lockdown announced by the Government of Maharashtra, the labours moved from site to their native places. Mostly the labours are from other States like UP, Bihar Orissa, Assam, Rajasthan etc. The labour strength on site reduced drastically. Here we have attached the previous labour strength and the labours available as of now f

Litigation declared1

CaseCourtStatus
583/2013CIVIL JUDGE JUNIOR DIVISION PUNEPENDING

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000023015Virendra Paul NaronhaNaiknavare Developers Pvt. Ltd11/05/2019
CC005000000033556Mrs Saramma GeorgeNaik Navare Developer Pvt Ltd16/01/2020
CC005000000177935Naiknavare Developers Pvt Ltd Thr its Authorized Signatory Anand Hemant NaiknavareMr. Madhav Samarth Gawai19/12/2022
CC005000000279730Naiknavare GroupMs. Kaushalyadevi Omprakash Agrawal27/11/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Jan 2023

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: Certificate EM1.pdf6 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Eminence Project-1-Form-5.pdf20 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eminence.pdf4 Oct 2023
Disclosure of sold/ booked inventoryFile: Eminence-A.pdf13 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 EMINENCE A BLDG.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eminence Pro 1 - Form 2 Jan To March 2023.pdf12 Apr 2023
Disclosure of sold/ booked inventoryFile: Eminence A_compressed.pdf10 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: 4 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for7 Apr 2023
Certificates of CA (Form 3)File: Eminence 1 rera form 3 Oct Dec 22 (2).pdf8 Mar 2023
Disclosure of sold/ booked inventoryFile: EMINENCE PRO 1 SOLD UNSOLD DEC 22.pdf9 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eminence.pdf19 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: EMINENCE RERA PART COMPLITION BALANC FLATS.pdf13 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: EMINENCE A Form 4 RERA.pdf13 Jan 2023
Certificates of CA (Form 3)File: Form 3 Eminence Sept 22.pdf27 Dec 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECT CERTIFICATE EMC BLDG A.pdf7 Dec 2022
Certificates of CA (Form 5)File: Eminance Pro1 Form 5.pdf6 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: EMINENCE PRO 1 PART COMPLETION OC.pdf7 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMINENCE PRO 1 FORM 2 JUN SEPT 22.pdf14 Oct 2022
Disclosure of sold/ booked inventoryFile: Eminence A building Sold Unsold.pdf10 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EMINENCE A RERA PRO 1 JULY SEPTEMBER 061022.pdf7 Oct 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Emience PRO 1 PART COMPLETION Bldg A.pdf7 Oct 2022
OtherFile: RERA EMINENCE BUILDING A _ FINAL AREA STATEMENT (1).pdf29 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMINENCE PRO 2 FORM 2 JUN 22.pdf6 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMINENCE A FORM 2 JUN 22.pdf6 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EMINENCE A RERA ARCH CERTI APR TO JUN.pdf1 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Eminence P1 Arch Certi.pdf4 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMINENCE P1 ENGR CERT.pdf19 Apr 2022
Certificates of CA (Form 5)File: 6 Certificates of CA (Form 5).pdf9 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH EMINENCE.pdf7 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGR EMINENCE.pdf7 Jan 2022
OtherFile: QUALITY CERTIFICATE A BLDG.pdf8 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT A BLDG 30 9 21.pdf4 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR CERT A BLDG 30 9 21.pdf4 Oct 2021
Certificates of CA (Form 3)File: Form 3 eminence PROJECT 1 A BUILDING 30 6 21.pdf16 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EMINENCE A ARCH CERT 27 07 2021.pdf31 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMINENCE A ENGR CERT 27 07 2021.pdf31 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Eminence Project 1 2018 TO 2019.pdf5 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Eminence Project 1 2019 TO 2020.pdf5 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: NDPL Rera Certificate.pdf5 Jul 2021
Declaration about Commencement CertificateFile: cc declration emience a bldg.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: inventory book 2362021.pdf23 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality letter eminence 1.pdf22 Jun 2021
Certificates of CA (Form 5)File: Eminence Project 1.pdf22 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A ARCH CERT 27 04 21.pdf27 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A ENGR CERT 27 04 21.pdf27 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EMINENCE ARCH CERT 19 01 21.pdf20 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMINENCE ENGR CERT 19 01 21.pdf20 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH A BLDG 28 09 2020.pdf7 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR A BLDG 28 09 2020.pdf7 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH CERT 20 06 2020.pdf22 Jun 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERT 20 6 20.pdf22 Jun 2020
Certificates of CA (Form 5)File: Form 5 Eminence P1.pdf22 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH A BLDG 20 01 2020.pdf20 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR A BLDG 20 01 2020.pdf20 Jan 2020
Certificates of CA (Form 5)File: NDPL - Project Eminence.pdf2 Jan 2020
Certificates of CA (Form 5)File: Form 5 Eminence P1.pdf14 Nov 2019
OtherFile: CREDAINDPL MEM CERT 2020.pdf4 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH A BLDG 21 10 19.pdf21 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR A BLDG 21 10 19.pdf21 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH CERT 22 7 2019.pdf22 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGR CERT 22 7 2019.pdf22 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch certificate A 24 4 2019.pdf26 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR CERTIFICATE 24042019.pdf25 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE 24 01 2019.pdf24 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR CERTIFICATE 24 01 2019.pdf24 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch cert 25 10 18.pdf25 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engr cert 25 10 18.pdf25 Oct 2018
Certificates of CA (Form 5)File: NDPL - Project Eminence.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT 25072018.pdf25 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGRCERT25072018.pdf25 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT.pdf25 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGR CERT.pdf25 Apr 2018
Details of encumbrancesFile: Altico Mortgage deed Index II.pdf20 Mar 2018
Proforma of Allotment letterFile: ALLOTTMENT LETTER.pdf20 Mar 2018
Proforma of Allotment letterFile: Agreement to sell2032018.pdf20 Mar 2018
Status of ConveyanceFile: Deed of Conveyance.pdf20 Mar 2018
OtherFile: EMINENCE_ALL FLOOR PLANS WITH LAYOUT (ANNEXURE C2).pdf20 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 arch cert 25-1-18.pdf25 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 engr cert 25-1-18.pdf25 Jan 2018
OtherFile: Eminence CA certificate251017.PDF25 Oct 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MYSTQUE MOOD B BLDGS NO 230A -3- 1 AND 231 -1 -1 LOHGAON PUNE32CompletedMar 2015Late, Apr 2015
SYLVAN HEIGHTS E BLDGAUNDH PUNE37CompletedSep 2013Sep 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EMINENCE PROJECT 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIMAN NAGAR13,700+ in Pune

2 kmEMINENCE PROJECT 1Completed 13Lapsed / revoked 8Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: NAIKNAVARE DEVELOPERS PVT LTD

NAIKNAVARE DEVELOPERS PVT LTD has 3 registrations on MahaRERA, including EMINENCE PROJECT 1 and SHIVATMAN. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if EMINENCE PROJECT 1 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EMINENCE PROJECT 1?

The registered promoter entity is NAIKNAVARE DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EMINENCE PROJECT 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EMINENCE PROJECT 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EMINENCE PROJECT 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EMINENCE PROJECT 1?

The professionals named in the filing: Architect: GAURI NAIKNAVARE; Engineer: KRUPALI KADAM. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EMINENCE PROJECT 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EMINENCE PROJECT 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EMINENCE PROJECT 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.