Ekta Parksville Phase IV
By EKTA PARKSVILLE HOMES PVT. LTD.
RG-MH-80144 · RERA P99000015239 · Last updated on MahaRERA portal: 6 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 78 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Ekta Parksville Phase IV is a Residential / Group Housing project by EKTA PARKSVILLE HOMES PVT. LTD. in Palghar, Maharashtra, registered with MahaRERA as P99000015239 on 8 Feb 2018. Possession is promised by 31 Dec 2028. The completion date has moved by 78 months from the original filing. 54 of the 318 units on this registration are recorded sold or booked, and 12 of 44 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameEkta Parksville Phase IV
- TypeResidential / Group Housing
- Location
- Narangi Bypass Road
- Virar
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401303
- Pincode401303
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000015239
- ReraGenie IDRG-MH-80144
Builder
- NameEKTA PARKSVILLE HOMES PVT. LTD.
- Entity typeCompany
- CINU70102MH1988PTC050060
- GSTIN27AAACW4316N1Z2
- DirectorsDILIP LAXMAN BORHADE, PRAKASH TRIBHUVANDAS TANNA, DILIP LAXMAN BORHADE, PRAKASH TRIBHUVANDAS TANNA
- Other registrations6 more →
- Completed5 of 7
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Feb 2018
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Jun 2022)
- Buildings4 building records
- Documents filed105 files
Current status
Figures as on 6 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 17 | 15 | 58 | 8 | 66 |
| Wing B | NA | 17 | 15 | 73 | 12 | 85 |
| Wing C | NA | 17 | 15 | 58 | 0 | 58 |
| Wing D | NA | 17 | 15 | 103 | 6 | 109 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
Wing A27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing B27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing C27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing D27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 1 | 1 |
| Wing B | 1 | 1 |
| Wing C | 1 | 1 |
| Wing D | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE & ASSOCIATES |
| Architect | Samir Desai |
| Engineer | UMESH JOSHI , Designated Partner JW CONSULTANTS LLP STR/J/26 |
| Engineer | Amit Parshuram Kamble |
| Engineer | SACHIN S KARAWADE |
| Chartered Accountant | Vikas Mangal |
| Chartered Accountant | Manoj Chaturvedi |
| Partner | Role in project |
|---|---|
| EKTA PARKSVILLE HOMES PVT. LTD. | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to scarcity of the resources & also some technical reasons.
Reason as filed by the promoterDelay in grant of CC by VVCMC and non compliance on part of HDIL
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000197508 | Manish Singh | Ekta Parksville Homes Private Limited | 29/07/2021 |
| CC006000000429063 | DEEPAK GOVIND SURVE | M/S EKTA PARSVILLE HOMES PRIVATE LIMITED | 02/02/2024 |
| CC12603084 | Adv Yash KASHINATH Dabhole | EKTA PARKSVILLE HOMES PVT. LTD. | 24/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jan 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jan 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Feb 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed105
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: SIGNED REGENT PARK FORM 1 31_03_26.pdf | 6 May 2026 |
| Form 2File: SIGNED ekta parksville phase 4 form 2 31_03_26.pdf | 6 May 2026 |
| Form 3File: Signed FORM 3 EPV P IV 31_03_2026.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: PHASE IV PARKSVILLE sold and unsold inventory as on 31_03_2026.pdf | 6 May 2026 |
| Form 1File: REGENT PARK FORM.pdf | 18 Jan 2026 |
| Form 2File: ekta parksville phase 4 form 2.pdf | 18 Jan 2026 |
| Form 3File: Signed FORM 3 EPV P IV.pdf | 18 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: EKTA PARKSVILLE PHASE IV SOLD UNSOLD.pdf | 18 Jan 2026 |
| Form 1File: REGENT PARK FORM 1 30-9-2025.pdf | 17 Oct 2025 |
| Form 2File: ekta parksville phase 4 form 2 Sep 2025.pdf | 17 Oct 2025 |
| Form 3File: Signed FORM 3 EPV P IV.pdf | 17 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: EKTA PARKSVILLE PHASE IV SOLD UNSOLD.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 EKTA PARKSVILLE PHASE 4 31_03_25.pdf | 27 Sep 2025 |
| Form 1File: FORM 1 EKTA PARKSVILLE PHASE 4 30-6-2025.pdf | 17 Jul 2025 |
| Form 2File: FORM 2 EKTA PARKSVILLE PHASE 4.pdf | 17 Jul 2025 |
| Form 3File: Signed FORM 3 EPV P IV 30 06 2025.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold & Unsold PV phase 4.pdf | 17 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PV P IV REGENT PARK FORM 1 31_03_2025.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: parksville phase 4 sold unsold march 2025.pdf | 18 Apr 2025 |
| Other - TechnicalFile: Consent To Operate 07-05-2018 (1).pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: REGENT PARK FORM 1 31_12_2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: EP P IV_compressed.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EP PHASE IV.PDF | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PV V IV REGENT PARK FORM 1 30-09-2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EW PARKSVIILE PHASE IV Form 2 ENG CERT 30_09_24.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: PV P IV SOLD UNSOLD.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta parksville phase IV.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EW PARKSVIILE PHASE IV Form 2 ENG CERT 30_06_24.pdf | 8 Aug 2024 |
| Certificates of CA (Form 3)File: June 2024 FINAL FORM 3 EPV P IV_compressed.pdf | 8 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: REGENT PARK P IV_compressed.pdf | 17 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PARKSVILLE PHASE IV WING ABCD FORM 2A Quality Assurance 31-3-2024.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 01042024.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 P P IV 01042024.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold quaterly updates.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: SIGNED FORM 3 P P IV.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EW PARKSVIILE PHASE IV Form 2 ENG CERT 31012024.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: RP P P IV.pdf | 17 Jan 2024 |
| Proforma of Agreement for saleFile: AFS Ekta Parksville Phase IV.pdf | 8 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: PV P IV.pdf | 9 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Regant Park.pdf | 17 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: P P IV QUALITY ASSURANCE 22-23.pdf | 3 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: EKTA PARKSVILLE PHASE IV.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: REGANT PARK-PH-IV.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: EP P IV.pdf | 6 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Parksville II.pdf | 15 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: EW PARKSVILLE PHASE IV FORM 2A Quality Assurance Certificate 31-12-2021.pdf | 15 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: Ekta Parksville Phase IV.pdf | 27 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Ekta Parksville Phase IV.pdf | 27 Feb 2023 |
| Declaration about Commencement CertificateFile: EKTA PARKSVILLE PHASE IV CC DECLARATION 20-02-2023.pdf | 27 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EW PARKSVILLE PHASE IV WING A TO D ARCH CERT FORM 1 20-2-2023.pdf | 27 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: EW pARKSVILLE WING A TO D PHASE IV QUALITY ASSURANCE 31-12-2020.pdf | 27 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EW PARKSVILLE PHASE IV FORM 2A Quality Assurance Certificate 31-12-2022.pdf | 27 Feb 2023 |
| CERSAI detailsFile: Parksville.pdf | 20 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Virar C P GOYAL.pdf | 20 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: fORM 2 pHASE 4, pARKSVILLE.pdf | 17 Feb 2023 |
| Proforma of Agreement for saleFile: REGENT PARK_RERA- parkville phase 4.pdf | 15 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: EP PHASE IV.pdf | 15 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: parksville Phase IV.pdf | 29 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Parksville Phase IV.pdf | 9 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Ekta Parksville IV.pdf | 14 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Parksville IV.pdf | 5 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: PARKSVILLE PHASE IV.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PARKSVILLE PHASE IV.pdf | 30 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: ekta parksville phase IV.pdf | 19 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold InventoryEkta Parks ville phase 4.pdf | 3 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Parksville Phase IV.pdf | 10 Feb 2021 |
| Details of encumbrancesFile: Index-2 Jm 20 Crs.pdf | 3 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Parksville Phase IV.pdf | 16 Nov 2019 |
| Details of encumbrancesFile: INdex 2 tata finance.pdf | 4 Nov 2019 |
| Certificates of CA (Form 5)File: Parksville Phase IV.pdf | 11 Oct 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencment certificate from VVCMC.pdf | 1 Jul 2019 |
| Certificates of CA (Form 5)File: Parksville Phase IV 04102018105936.pdf | 9 Oct 2018 |
| Proforma of Allotment letterFile: REGENT PARK_RERA sale agreement.pdf | 5 Jul 2018 |
| Declaration in FORM BFile: Form B Declaration Revised.pdf | 24 Apr 2018 |
| Details of encumbrancesFile: Parksville.pdf | 11 Apr 2018 |
| Details of encumbrancesFile: JMF-Indenture of Mortgage-2423-2018-303-303.pdf | 11 Apr 2018 |
| Building plan approvalFile: WING-A 1-ilovepdf.pdf | 5 Feb 2018 |
| Building plan approvalFile: WING-A 1-ilovepdf.pdf | 5 Feb 2018 |
| Building plan approvalFile: WING-A 2-ilovepdf.pdf | 5 Feb 2018 |
| Building plan approvalFile: WING-B 1-ilovepdf.pdf | 5 Feb 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 105 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Ekta Parksville Phase IV on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Virar3,200+ in Palghar
Filed coordinates, straight-line distance. 152 registered projects within 2 km.
Mayfair Virar Gardens Cluster-VI
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS CLUSTER IV
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19,
MAYFAIR HOUSING
Agarwal Infinity
Laxminarayan Prabhudayal Agarwal
GOKUL HARI ANANTA
Mehta Ventures
GOKUL NAKSHATRA II
JSB HOMEMAKERS PRIVATE LIMITED
See every Palghar project, with the district possession charts
Builder: EKTA PARKSVILLE HOMES PVT. LTD.
EKTA PARKSVILLE HOMES PVT. LTD. has 7 registrations on MahaRERA, including EKTA PARKSVILLE PHASE I and EKTA PARKSVILLE PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Ekta Parksville Phase IV is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Ekta Parksville Phase IV?
The registered promoter entity is EKTA PARKSVILLE HOMES PVT. LTD., a company as per the filing. Its CIN U70102MH1988PTC050060 and GSTIN 27AAACW4316N1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Ekta Parksville Phase IV?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Ekta Parksville Phase IV?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Ekta Parksville Phase IV?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Ekta Parksville Phase IV?
The professionals named in the filing: Architect: AJAY WADE & ASSOCIATES; Architect: Samir Desai; Engineer: UMESH JOSHI , Designated Partner JW CONSULTANTS LLP STR/J/26; Engineer: Amit Parshuram Kamble; Engineer: SACHIN S KARAWADE; Chartered Accountant: Vikas Mangal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Ekta Parksville Phase IV?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback