EKTA PARKSVILLE PHASE II
By EKTA PARKSVILLE HOMES PVT. LTD.
RG-MH-08362 · RERA P99000000115 · Last updated on MahaRERA portal: 6 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- 44 complaints at MahaRERA
- Completion date moved by 66 months
- 3 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EKTA PARKSVILLE PHASE II is a Residential / Group Housing project by EKTA PARKSVILLE HOMES PVT. LTD. in Palghar, Maharashtra, registered with MahaRERA as P99000000115 on 4 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 66 months from the original filing. 44 complaints are on record with the regulator.
At a glance
Project
- NameEKTA PARKSVILLE PHASE II
- TypeResidential / Group Housing
- Location
- Narangi Bypass Rd
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401103
- Pincode401103
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000000115
- ReraGenie IDRG-MH-08362
Builder
- NameEKTA PARKSVILLE HOMES PVT. LTD.
- Entity typeCompany
- CINU70102MH1988PTC050060
- GSTIN27AAACW4316N1Z2
- DirectorsDILIP LAXMAN BORHADE, PRAKASH TRIBHUVANDAS TANNA, DILIP LAXMAN BORHADE, PRAKASH TRIBHUVANDAS TANNA
- Other registrations6 more →
- Completed5 of 7
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Jul 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2021)
- Buildings8 building records
- Documents filed167 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LINCOLN PARK A WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK B WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK C WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK D WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK E WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK F WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK G WING | NA | 17 | 16 | 0 | 0 | 0 |
| LINCOLN PARK H WING | NA | 17 | 16 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building8
As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
74 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Installation of Lifts, at 90%.
LINCOLN PARK A WING99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LINCOLN PARK B WING98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 83% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LINCOLN PARK C WING45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 75% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LINCOLN PARK D WING99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
LINCOLN PARK E WING98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 81% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LINCOLN PARK F WING99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 86% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LINCOLN PARK G WING98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 79% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LINCOLN PARK H WING98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 82% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities23
As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 88% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 85% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
| MULTI PURPOSE COURT | Yes | 100% |
| OPEN GYMNASIUM | Yes | 100% |
| OPEN LAWN | Yes | 100% |
| OUTDOOR CHESS BOARD | Yes | 100% |
| OUTDOOR PLAYING AREA WITH PLAY EQUIPMENTS | Yes | 100% |
| SHRUB BED | Yes | 100% |
| Jogging Track | Yes | 100% |
| GAZEBO | Yes | 100% |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| LINCOLN PARK A WING | 1 | 1 |
| LINCOLN PARK B WING | 1 | 1 |
| LINCOLN PARK C WING | 1 | 1 |
| LINCOLN PARK D WING | 1 | 1 |
| LINCOLN PARK E WING | 1 | 1 |
| LINCOLN PARK F WING | 1 | 1 |
| LINCOLN PARK G WING | 1 | 1 |
| LINCOLN PARK H WING | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Samir Desai |
| Architect | AJAY WADE AND ASSOCIATES |
| Engineer | SACHIN S KARAWADE |
| Engineer | Amit Parshuram Kamble |
| Engineer | J W CONSULTANTS |
| Chartered Accountant | SHIVANANDAN N KATDARE |
| Chartered Accountant | Manoj Chaturvedi |
| Chartered Accountant | Vikas Mangal |
| Partner | Role in project |
|---|---|
| EKTA PARKSVILLE HOMES PVT. LTD. | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterdue to scarcity of availability of the resources and also some technical reasons.
Reason as filed by the promoterWe hereby apply for extension u/s 7(3) for the wings [ A to H ] of the registered project Ekta Parksville Phase III bearing MahaRERA registration No. P99000000115. Wings A,B, E TO H of the said project have already received OC on 15th May, 2019. The structure of the Wings D is already completed and construction of the Wing C structure is ongoing. Further, Consent to Operate has been delayed for a long time for the entire larger HDIL Layout. Therefore, application for Occupation Certificate, will be applied shortly. Although, procurement of all the permissions including Consent to Operate in re
Reason as filed by the promoterNon compliance on the part of HDIL
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 887/2016 | BOMBAY CITY CIVIL COURT | Withdrawal |
| 889/2016 | BOMBAY CITY CIVIL COURT | WITHDRAWAL |
| 890/2016 | BOMBAY CITY CIVIL COURT | Withdrawal |
| 12390/2023 | HIGH COURT | Closed |
Complaints filed with MahaRERA44
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000461 | Prasenjit Halder | Ekta Parksville Homes Pvt Ltd | 18/12/2017 |
| CC006000000079020 | Prasenjit Halder | Ekta World Pvt Ltd and Ekta Parksville Homes Pvt Ltd | 09/05/2019 |
| CC006000000198221 | Prasenjit Halder | Ekta World | 03/09/2021 |
| CC006000000000637 | Praful Prakash Pawar | Ekta Parksville homes Pvt Ltd | 15/09/2017 |
| CC006000000292738 | Praful Prakash Pawar | EKTA PARKSVILLE HOMES PVT. LTD | 26/09/2022 |
| CC006000000078954 | NAIM SHAIKH | Ekta Parksville Home Pvt Ltd | 18/04/2019 |
| CC006000000055800 | RAJKUMAR TIWARI | EKTA PARKSVILLE HOMES PVT LTD | 22/09/2018 |
| CC006000000055848 | PAWAN UMESHCHANDRA TIWARI | EKTA PARKSVILLE HOMES PVT LTD | 22/09/2018 |
| CC006000000022958 | NAIM SHAIKH | Ekta Parksville Homes Private Limited | 17/01/2018 |
| CC006000000181962 | Tejas Patel | EKTA PARKSVILLE-ASHOK MOHANANI | 24/12/2019 |
| CC006000000023194 | Sandeep L Dalvi | Ekta Parksville Homes Pvt Ltd | 02/02/2018 |
| CC006000000023360 | Suresh Tehilramani | Ekta Parksville Homes Pvt Ltd Phase II | 22/02/2018 |
| CC006000000023737 | Maria Abbas Jamali | Ekta Parksville Homes Pvt.Ltd. | 14/03/2018 |
| CC006000000044006 | ROHIT ARORA | EKTA PARKSVILLE HOMES PVT LTD | 05/04/2018 |
| CC006000000054811 | Harsha B Bulchand and Bholaram I Bulchand | Ekta Parksville Homes Pvt. Ltd. | 11/06/2018 |
| CC006000000054835 | Bholaram I Bulchand and Harsha B Bulchand | Ekta Parksville Homes Pvt. Ltd. | 11/06/2018 |
| CC006000000056635 | Reshma Vishal Parkala | Ekta Parksville Homes Private Limited | 19/10/2018 |
| CC006000000056638 | Deepak Mehra | Ekta Parks Ville | 01/11/2018 |
| CC006000000057176 | POONAM BATHIJA | Vivek Mohanani | 05/12/2018 |
| CC006000000079300 | Ashfaque A Halde | Ashafaque Halde | 16/05/2019 |
| CC006000000100195 | Amita Soni | Ekta Parksville Homes Pvt Ltd | 17/07/2019 |
| CC006000000110792 | praveen kumar | EKTA PARKVILLA HOME PVT LTD- PH-II ( LINKON PARK) | 04/09/2019 |
| CC006000000171614 | Regimol Jose & Jose Thomas | Ekta Parksville Pvt Ltd | 27/11/2019 |
| CC006000000171742 | Hillari Dsouza | Ekta Parksville Homes Private Limited | 11/12/2019 |
| CC006000000192580 | SUNIR WADHWA and NEHA WADHWA | EKTA PARKSVILLE HOMES PVT. LTD. | 12/02/2020 |
| CC006000000192588 | RENUKA WADHWA and SULBHA WADHWA | EKTA PARKSVILLE HOMES PVT. LTD. | 12/02/2020 |
| CC006000000194339 | Surendra Poojar | Ekta Parkville Homes | 12/10/2020 |
| CC006000000194919 | Nitin koli | Ekta World | 16/12/2020 |
| CC006000000197935 | Sanjay Shivram Bansode | M/S EKTA PARKSVILLE HOMES PVT LTD | 10/08/2021 |
| CC006000000375011 | Mr Vinod D Ferreira and Mrs Felina V Ferreira | Ekta Parksville Homes Pvt Ltd | 29/03/2023 |
| CC006000000396096 | Susan Krishnarajan Nedungadi | Ekta Parksville Homes Pvt Ltd | 07/06/2023 |
| CC006000000408321 | Zicharious Miranda | M/s. Ekta Parksville Homes Private Limited | 19/12/2023 |
| CC006000000408200 | Maulik Kanchanlal PATEL | EKTA PARKSVILLE HOMES PVT. LTD. | 16/12/2023 |
| CC006000000408325 | DINESH KUMAR BHAGAT | EKTA PARKSVILLE HOMES PVT LTD | 02/12/2023 |
| CC006000000429391 | Ramesh Chapshi Mota | M/s Ekta Parksville Homes Pvt. Ltd. | 23/02/2024 |
| CC006000000439675 | Sagar Modi | M/s Ekta Parksville Homes Pvt. Ltd. | 05/04/2024 |
| CC006000000591588 | Abbasi Ujjainwala | EKTA WORLD | 18/08/2024 |
| CC12400336 | Sanjay Chandmal Shah | EKTA PARKSVILLE HOMES PVT. LTD. | 04/10/2024 |
| CC12401135 | Pawan Umeshchandra Tiwari | EKTA PARKSVILLE HOMES PVT. LTD. | 15/12/2024 |
| CC12401134 | Rajkumar Tiwari | EKTA PARKSVILLE HOMES PVT. LTD. | 15/12/2024 |
| CC12501501 | Suraj Vishwakarma | EKTA PARKSVILLE HOMES PVT. LTD. | 06/05/2025 |
| CC12500795 | Manish Mukund Prabhughate | EKTA PARKSVILLE HOMES PVT. LTD. | 08/03/2025 |
| CC12501289 | Santosh Tejbahadur Thakur | Santosh Tejbahadur Thakur | 17/04/2025 |
| CC12504058 | Saurabh Mittal | EKTA PARKSVILLE HOMES PVT. LTD. | 18/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jun 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jun 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Jul 2023
Documents filed167
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 167 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: SIGNED PARKVILLE PHASE II FORM 1 31_03_2026.pdf | 6 May 2026 |
| Form 2File: SIGNED ekta parksville phase 2 form 2 MARCH 2026.pdf | 6 May 2026 |
| Form 3File: Signed Form 3 PV P II 31_03_2026_compress.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: PHASE II PARKSVILLE sold and unsold inventory as on 31_03_26.pdf | 6 May 2026 |
| Form 1File: EW PARKSVILLE PHASE II WING C FORM 1.pdf | 18 Jan 2026 |
| Form 2File: ekta parksville phase 2 form 2.pdf | 18 Jan 2026 |
| Form 3File: Form 3 PV P II 30_06_2025_compressed (1).pdf | 18 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: EKTA PARKSVILLE PHASE II SOLD UNSOLD.pdf | 18 Jan 2026 |
| Form 1File: EW PARKSVILLE PHASE II WING C FORM 1 R1 30-9-2025.pdf | 17 Oct 2025 |
| Form 2File: ekta parksville phase 2 form 2 Sep 2025.pdf | 17 Oct 2025 |
| Form 3File: FORM 3 EKTA PARKSVILLE PHASE II.pdf | 17 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: EKTA PARKSVILLE PHASE II SOLD UNSOLD.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 EKTA PARKSVILLE PHASE 2 31_03_25.pdf | 27 Sep 2025 |
| Form 1File: FORM 1 EKTA PARKSVILLE PHASE II 30-6-2025.pdf | 17 Jul 2025 |
| Form 2File: FORM 2 EKTA PARKSVILLE PHASE 2.pdf | 17 Jul 2025 |
| Form 3File: Form 3 PV P II 30_06_2025_compressed (1).pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: ekta parksvillle phase 2 sold unsold 30-06-2025.pdf | 17 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: parksville phase 2 sold unsold march 2025.pdf | 18 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PARKSVILLE PHASE II WING C R1 31_03_2025.pdf | 9 Apr 2025 |
| Certificates of CA (Form 3)File: SIGNED March 2025_ FORM 3 CA Certificate EKTA PARKSVILLE PHASE II.pdf | 9 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 EP PHASE II 31_03_2025.pdf | 9 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW PARKSVILLE PHASE II WING C FORM 1 31_12_2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: EP P II_compressed.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EP PHASE II.PDF | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW PARKSVILLE PHASE II WING C FORM 1 30-09-2024 .pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW PARKSVIILE PHASE II Form 2 ENG CERT 30_09_2024.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: PV P II SOLD UNSOLD.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta parksville phase II.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW PARKSVIILE PHASE II Form 2 ENG CERT 30_06_2024.pdf | 26 Jul 2024 |
| Certificates of CA (Form 3)File: signed JUNE 2024_ FORM 3 CA Certificate EKTA PARKSVILLE PHASE II.pdf | 26 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: PV P II_COMPRESS.pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SIGNED EW PARKSVILLE PHASE II WING C FORM 1 31-03-2024.pdf | 3 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SIGNED EW PARKSVIILE PHASE II Form 2 ENG CERT 31032024.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PARKSVILLE PHASE II WING C FORM 2A Quality Assurance 31-3-2024.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: SIGNED Final Form 3 PP II 31 MARCH 2024.pdf | 3 May 2024 |
| Disclosure of sold/ booked inventoryFile: Lincon Park Inventory.pdf | 16 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW PARKSVILLE PHASE II WING C FORM 1 31-12-2023.pdf | 26 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW PARKSVIILE PHASE II Form 2 ENG CERT 31012024.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: LP.pdf | 17 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: PV P II.pdf | 9 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: parksville phase2.pdf | 17 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A P P II.pdf | 13 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: EKTA P P II.pdf | 3 Aug 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: virar OC 28072023.pdf | 30 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: EKTA PARKSVILLE-PH-II.pdf | 20 Jul 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: EKTA PARKSVILLE LINCON A TO H PHASE II.pdf | 12 Jun 2023 |
| OtherFile: Lincoln Park C Wing.pdf | 2 May 2023 |
| Disclosure of sold/ booked inventoryFile: EP P II.pdf | 6 Apr 2023 |
| Certificates of CA (Form 3)File: FORM 3 EKTA PARKSVILLE PHASE II.pdf | 11 Feb 2023 |
| OtherFile: EP Phase II.pdf | 11 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 EKTA PARKSVILLE PHASE II.pdf | 10 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH PARKSVILLE PHASE II EXTENTION 31-01-2023.pdf | 8 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW PARKSVILLE PHASE II Form 2 ENGINEER CERTIFICATE 31-12-22.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Parksville Phase II.pdf | 4 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Parksville Phase II.pdf | 4 Feb 2023 |
| Declaration about Commencement CertificateFile: EKTA PARKSVILLE PHASE II CC DECLARATION 31-01-2023.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A QUALITY ASSURANCE PARKSVILLE PHASE II 1-01-2022.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A QUALITY ASSURANCE PARKSVILLE PHASE II 1-01-2022.pdf | 4 Feb 2023 |
| CERSAI detailsFile: Parksville.pdf | 4 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Parksville.pdf | 4 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Virar C P GOYAL.pdf | 4 Feb 2023 |
| Proforma of Agreement for saleFile: Allottment Letter and Agreement for Sale Parksville Ph II.pdf | 4 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: EP PHASE II.pdf | 15 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: PARKSVILLE PHASE II.pdf | 31 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Parksville Phase II.pdf | 9 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Ekta Parksville II.pdf | 14 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: parksville II.pdf | 5 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: PARKSVILLE PHASE II.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PARKSVILLE PHASE II.pdf | 30 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: parksville phase II.pdf | 19 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21 PARKSVILLE PHASE II.pdf | 6 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Parksville Phase 2-1-6.pdf | 3 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Parksville Phase 2-7-12.pdf | 3 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Parksville Phase II.pdf | 10 Feb 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Parksville.pdf | 6 Feb 2021 |
| Details of encumbrancesFile: Index-2 Jm 20 Crs.pdf | 3 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Virar phase II.pdf | 16 Nov 2019 |
| Certificates of CA (Form 5)File: Virar phase II.pdf | 11 Oct 2019 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: PHASE II Lincon park AtoH Society Formation application.pdf | 16 Sep 2019 |
| OtherFile: Virar OC.pdf | 17 May 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 167 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep EKTA PARKSVILLE PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar
Filed coordinates, straight-line distance. 150 registered projects within 2 km.
GALAXY RESIDENCY
MAHASHAKTI ENTERPRISES
TANISHQ TYPE G-5,E-5,F-5 WING P,Q,R
RAJVAN LIFESPACES LLP
TANISHQ-TYPE G-4,E-4,F-4 WING M,N,O
RAJVAN LIFESPACES LLP
IVORY HOMES
YASHRON DEVELOPERS LLP
PRIME ONE
PRIMEVILLE DEVELOPERS LLP
SAMYA ONE
PRIMEVILLE DEVELOPERS LLP
See every Palghar project, with the district possession charts
Builder: EKTA PARKSVILLE HOMES PVT. LTD.
EKTA PARKSVILLE HOMES PVT. LTD. has 7 registrations on MahaRERA, including EKTA PARKSVILLE PHASE I and EKTA PARKSVILLE PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if EKTA PARKSVILLE PHASE II is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EKTA PARKSVILLE PHASE II?
The registered promoter entity is EKTA PARKSVILLE HOMES PVT. LTD., a company as per the filing. Its CIN U70102MH1988PTC050060 and GSTIN 27AAACW4316N1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EKTA PARKSVILLE PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EKTA PARKSVILLE PHASE II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EKTA PARKSVILLE PHASE II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EKTA PARKSVILLE PHASE II?
The professionals named in the filing: Architect: Samir Desai; Architect: AJAY WADE AND ASSOCIATES; Engineer: SACHIN S KARAWADE; Engineer: Amit Parshuram Kamble; Engineer: J W CONSULTANTS; Chartered Accountant: SHIVANANDAN N KATDARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EKTA PARKSVILLE PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback