ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / EKTA CO-OP HSG SOCIETY

Registration lapsed No litigation declared Residential / Group Housing project

EKTA CO-OP HSG SOCIETY

By SURJIT BHOJSINGH AILSINGHANI

RG-MH-11979 · RERA P51800004327 · Last updated on MahaRERA portal: 9 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 98%
22 of 141Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 159 documents Report an error

EKTA CO-OP HSG SOCIETY is a Residential / Group Housing project by SURJIT BHOJSINGH AILSINGHANI in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004327 on 9 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 119 of the 141 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameEKTA CO-OP HSG SOCIETY
  • TypeResidential / Group Housing
  • Location
    • S. G. Barve Marg
    • Nehru Nagar
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004327
  • ReraGenie IDRG-MH-11979

Builder

  • NameSURJIT BHOJSINGH AILSINGHANI
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed159 files

Current status

84%119 of 141 units booked
65.2%Work done, per cost certificate

Figures as on 9 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EKTA CO-OP HSG SOCIETYNA16168358141

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

EKTA CO-OP HSG SOCIETY: 62% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks93%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 9 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered46

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,547 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI8750.93
Proposed, not sanctioned8,751 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPalm Beach Road, Sector 17, Vashi, Navi Mumbai
Estimated costRs 35.40 cr
Cost incurredRs 23.10 cr
Work done65.25%
BuildingWingEstimatedIncurred
EKTA CO-OP HSG SOCIETYNARs 33.00 crRs 23.10 cr
-NARs 2.40 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAYANT RATILAL KATIRA
ArchitectSameer Kulkarni
EngineerJAYANT RATILAL KATIRA
Chartered AccountantE A PATIL & ASSOCIATES LLP
Chartered AccountantR J PHADKE & CO
PartnerRole in project
SURJIT BHOJSINGH AILSINGHANI-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018458Dec 2023 → Dec 2024

Reason as filed by the promoterOur Project is almost 85% complete and part occupancy certificate has also been received. Due to very congested site the material storage problem and traffic problem, local problems and also a Covid-19 and labour shortage it took time to complete our project on time as mentioned. Required additional extension for the period of 12-month time to complete the project.

EXT51800027158Dec 2023 → Dec 2025

Reason as filed by the promoterWe hereby state that our project has been delayed due to ongoing work involving the fire system work, car tower parking work, and lift installation work. We kindly request you to grant an extension of 1 year for the completion of the project.

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000500494Rahul Rohidas DivateSurjit Bhojsingh Alisighani16/05/2024
CC006000000500496Mahadeo Maruti JagadaleSurjit Bhojsingh Alisighani16/05/2024
CC006000000500489Vikas Valiba AvhadSurjit Bhojsingh Alisighani16/05/2024
CC006000000591435Vikas Valiba AvhadShri Surjit Bhojsingh Ailsinghani06/08/2024
CC12502903Abdul Halim Nadir ShaikhSURJIT BHOJSINGH AILSINGHANI19/08/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Jan 2024

Documents filed159

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 159 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC-Revalidation.pdf9 Mar 2026
Commencement certificateFile: CC-Revalidation.pdf9 Mar 2026
Withdrawal Update Form 1File: Form-1 Dec 25.pdf9 Mar 2026
Withdrawal Update Form 2File: Form-2 Dec 25.pdf9 Mar 2026
Withdrawal Update Form 3File: Form-3 Dec 25.pdf9 Mar 2026
Withdrawal Update Form 1File: Oct-25.pdf7 Mar 2026
Withdrawal Update Form 2File: Form-2 Oct 25.pdf7 Mar 2026
Withdrawal Update Form 3File: Form-3 oct 25.pdf7 Mar 2026
Withdrawal Update Form 1File: Jul-25.pdf6 Mar 2026
Withdrawal Update Form 2File: Form-2 Jul 25.pdf6 Mar 2026
Withdrawal Update Form 3File: Form-3 July 25.pdf6 Mar 2026
Details of encumbrances concerned to FinanceFile: Encumbrances Certificate.pdf7 Mar 2025
Declaration in FORM BFile: Form-B.pdf7 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 24.pdf7 Mar 2025
Certificates of CA (Form 3)File: Form-3.pdf7 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec 24.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Declaration About Unit-apartment.pdf7 Mar 2025
Details of encumbrances concerned to LegalFile: Encumbrances Certificate.pdf7 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation.pdf16 Jan 2025
Other - LegalFile: Format B Consent.pdf13 Jan 2025
Details of encumbrancesFile: No Encumbrances.pdf8 Jan 2025
Declaration in FORM BFile: Form B.pdf8 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf8 Jan 2025
Certificates of CA (Form 3)File: April 24.pdf8 Jan 2025
Certificates of CA (Form 3)File: Jul 24.pdf8 Jan 2025
Certificates of CA (Form 3)File: Oct 24.pdf8 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: April 24.pdf8 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jul 24.pdf8 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct 24.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf8 Jan 2025
Declaration about Commencement CertificateFile: Form B.pdf8 Jan 2025
Declaration about Commencement CertificateFile: Declaration about CC.pdf8 Jan 2025
CERSAI detailsFile: Security Interest.pdf8 Jan 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of Bank.pdf8 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other than real estate.pdf8 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5.pdf8 Jan 2025
Declaration about Commencement CertificateFile: Revalidation of CC.pdf16 Feb 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - sep 2018.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - sep 2018.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - sep 2019.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - sep 2020.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - sep 2021.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - sep 2022.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Jan 2023.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - april 2023.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - July 2023.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Oct 2023.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 Jan 23.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 Apr 23.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 July 23.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 Oct 23.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 Dec 23.pdf3 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2021-22.pdf3 Feb 2024
Other - LegalFile: Self Declaration.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 31 Jan 2023.pdf31 Jan 2024
Certificates of CA (Form 3)File: Form 3 30 April 2023.pdf31 Jan 2024
Certificates of CA (Form 3)File: Form 3 31 July 2023.pdf31 Jan 2024
Certificates of CA (Form 3)File: Form 3 31 Oct 2023.pdf31 Jan 2024
Certificates of CA (Form 3)File: Form 3 31 Dec 2023.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf31 Jan 2024
Other - LegalFile: Consent-Form C.pdf31 Jan 2024
Other - LegalFile: Self Declaration.pdf31 Jan 2024
Certificates of CA (Form 3)File: Form Dec 23.pdf27 Jan 2024
Building plan approvalFile: IOD 2014.pdf25 Jan 2024
Building plan approvalFile: IOD Amended.pdf25 Jan 2024
Building Plan Approval (IOD)File: IOD 2014.pdf25 Jan 2024
Building Plan Approval (IOD)File: IOD Amended.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf25 Jan 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
BABA PEARL HEIGHTPlot No. 17 Sector 20 kamothe Navi Mumbai26CompletedDec 2012Dec 2012

How this compares with Mumbai Suburban

84%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EKTA CO-OP HSG SOCIETY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nehru Nagar6,700+ in Mumbai Suburban

2 kmEKTA CO-OP HSG SOCIETYCompleted 112Lapsed / revoked 96Other 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 352 registered projects within 2 km.

Builder: SURJIT BHOJSINGH AILSINGHANI

SURJIT BHOJSINGH AILSINGHANI has 3 registrations on MahaRERA, including EKTA CO-OP HSG SOCIETY and Satguru SRA Co-op Hsg. Society. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that EKTA CO-OP HSG SOCIETY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if EKTA CO-OP HSG SOCIETY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EKTA CO-OP HSG SOCIETY?

The registered promoter entity is SURJIT BHOJSINGH AILSINGHANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EKTA CO-OP HSG SOCIETY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EKTA CO-OP HSG SOCIETY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EKTA CO-OP HSG SOCIETY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EKTA CO-OP HSG SOCIETY?

The professionals named in the filing: Architect: JAYANT RATILAL KATIRA; Architect: Sameer Kulkarni; Engineer: JAYANT RATILAL KATIRA; Chartered Accountant: E A PATIL & ASSOCIATES LLP; Chartered Accountant: R J PHADKE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EKTA CO-OP HSG SOCIETY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EKTA CO-OP HSG SOCIETY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EKTA CO-OP HSG SOCIETY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.