Registration lapsed No litigation declared Others project

EARTH ANAND

By M/s. Earth Graphics

RG-MH-93097 · RERA P51900021985 · Last updated on MahaRERA portal: 2 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 17 months past the filed date
  • Completion date moved by 17 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
May 2025Possession promised17 months past this date
4 of 11Construction stages donefurthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

EARTH ANAND is a Others project by M/s. Earth Graphics in Chinch Bunder, 400009, registered with MahaRERA as P51900021985 on 25 Aug 2019. Possession was promised by 31 May 2025 and is now 17 months past that date. The completion date has moved by 17 months from the original filing.

At a glance

Project

  • NameEARTH ANAND
  • TypeOthers
  • Location
    • Keshavji Naik Road
    • Chinch Bunder
    • 400009
  • Pincode400009
  • RERA no.P51900021985
  • ReraGenie IDRG-MH-93097

Builder

  • NameM/s. Earth Graphics
  • Entity typeOthers
  • PartnersBhupesh Babulal Jain, Bharat Babulal Jain
  • Named personsBhupesh Babulal Jain, Bharat Babulal Jain, Earth Corporation Limited
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

17 months past promisethis monthRegisteredAug 2019First promiseDec 2023Revised toMay 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Aug 2019
  • Promised completion31 May 2025
  • Revised completionRevised to 31 May 2025 (originally 22 Dec 2023)
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Earth AnandNA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

Earth Anand: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities16

As on 2 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes20%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Fitness centerYes20%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,044 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5259.83
Proposed, not sanctioned5,260 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSandoz House, Dr Annie Besant Road, Worli, Mumbai - 18

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Nandkishore Madhav Udas
EngineerStruct Bombay Consultants
Chartered AccountantSanket R Shah
PartnerRole in project
M/s. Earth Graphics-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900018236Dec 2023 → Dec 2024

Reason as filed by the promoterWe have received approval of additional floor in this project and therefore we require extension for one year to complete the project with receive occupancy certificate and Form 4.

EXT51900027139Dec 2023 → May 2025

Reason as filed by the promoterWE HAVE APPLIED FOR RERA EXTENSION BECAUSE THE FORMALITY IS PENDING FOR OC APPLICATION AND THEREFORE AS PER RULES AND REGULATION WE APPLIED LESS THAN 1 YEAR. PLEASE APPROVE THE EXTENSTION

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Earth Anand.pdf2 Jul 2025
Declaration in FORM BFile: Form B - Earth Anand.pdf1 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NAND KISHORE UDAS CERTIFICATE APRIL 2025.pdf1 Jul 2025
Other - TechnicalFile: Annexure A.pdf1 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NAND KISHORE UDAS CERTIFICATE APRIL 2025.pdf30 Jun 2025
Declaration about Commencement CertificateFile: EARTH ANAND FULL CC JUNE2025.pdf30 Jun 2025
Form 3File: Form_III_Dec24_Anand_compressed.pdf13 Jun 2025
Form 2File: Form_II_Anand.pdf13 Jun 2025
Form 1File: Form_I_Architect_Anand.pdf13 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec24 - Earth Anand.pdf13 Jun 2025
Declaration in FORM BFile: 6.pdf4 Mar 2025
Declaration in FORM BFile: Form B.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_I_Architect_Anand.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form_III_Dec24_Anand_compressed.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_II_Anand.pdf21 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec24 - Earth Anand.pdf21 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance FY23-24.pdf21 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (Mar 24) - Earth Anand.pdf21 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Earth Anand.pdf21 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclousure of loan - Earth Anand.pdf21 Jan 2025
Declaration about Commencement CertificateFile: Latest CC revalidation issue letter (1).pdf20 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Work Comp Cert dt 1-12-23_231201_154344.pdf1 Dec 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Legal - Earth Anand.pdf3 Nov 2023
Details of encumbrances concerned to LegalFile: Encumbrances Legal - Earth Anand.pdf3 Nov 2023
CERSAI detailsFile: Cersai Declaration - Earth Anand.pdf3 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (Mar 23) - Earth Anand.pdf3 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: E-ANAND SEPRATE BANK AC.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 20 - Earth Anand.pdf30 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March 21 - Earth Anand.pdf30 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 22 - Earth Anand.pdf30 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM V (F Y 21-22) - Earth Anand.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form V March 20 - Earth Anand.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form V March 21 - Earth Anand.pdf23 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed upto 15th Floor.pdf15 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed upto 15th Floor Revalidated.pdf15 Mar 2022
Declaration about Commencement CertificateFile: FurtherCC_signed upto 15th Floor.pdf15 Mar 2022
Declaration about Commencement CertificateFile: FurtherCC_signed upto 15th Floor Revalidated.pdf15 Mar 2022
Proforma of Allotment letterFile: Allotment Letter.pdf4 Jul 2019
Layout approvalFile: Layout of Earth Anand.pdf25 May 2019
Layout approvalFile: Layout of Earth Anand.pdf25 May 2019
Copy of Layout Approval (in case of layout)File: Layout of Earth Anand.pdf25 May 2019
Copy of Layout Approval (in case of layout)File: Layout of Earth Anand.pdf25 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf25 May 2019
Building plan approvalFile: Amended Approval Letter 07082018.pdf22 May 2019
Copy of the legal title reportFile: Title Certificate from Advocate_compressed.pdf22 May 2019
Building Plan Approval (IOD)File: Amended Approval Letter 07082018.pdf22 May 2019
Commencement Certificates / NA Order for plotted developmentFile: First CC Earth Anand.pdf22 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng CERTIFICATE EARTH ANAND.pdf22 May 2019
Certificates of CA (Form 3)File: rera cer.pdf22 May 2019
PAN CardFile: Earth Graphics Pan Card.pdf14 May 2019
Details of encumbrancesFile: Encumbrances.pdf14 May 2019
Declaration in FORM BFile: Undertaking.pdf14 May 2019

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Earth Galaxy163 A Dr BA Road Dadar Mumbai 40001421CompletedApr 2014Apr 2014
Earth Pillar22 24B Junction of khadilkar road and sadashiv cross road girgaum mumbai 40000454CompletedNov 2012Late, Apr 2015
Earth View12th Khetwadi Back Road Girgaon Mumbai 40000445CompletedAug 2012Aug 2012

Keep EARTH ANAND on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chinch Bunder

Builder: M/s. Earth Graphics

M/s. Earth Graphics has 3 registrations on MahaRERA, including Earth Darshan and Earth Terrace. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record.

Frequently asked questions

What does it mean that EARTH ANAND shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if EARTH ANAND is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EARTH ANAND?

The registered promoter entity is M/s. Earth Graphics, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EARTH ANAND?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EARTH ANAND?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EARTH ANAND?

The professionals named in the filing: Architect: Mr Nandkishore Madhav Udas; Engineer: Struct Bombay Consultants; Chartered Accountant: Sanket R Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EARTH ANAND?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EARTH ANAND. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EARTH ANAND to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.