Home / Browse projects / Pune, Maharashtra / DURGA VIHAR

Registration lapsed No litigation declared Residential / Group Housing project

DURGA VIHAR

By Satkar Reality

RG-MH-82074 · RERA P52100048316 · Last updated on MahaRERA portal: 22 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 8 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
15 of 20Construction stages doneacross 2 buildings; furthest along: Staircases, 85%
22 of 40Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

DURGA VIHAR is a Residential / Group Housing project by Satkar Reality in Pune, Maharashtra, registered with MahaRERA as P52100048316 on 26 Dec 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 8 months from the original filing. 18 of the 40 units on this registration are recorded sold or booked, and 15 of 20 construction stages are filed complete.

At a glance

Project

  • NameDURGA VIHAR
  • TypeResidential / Group Housing
  • Location
    • Dhankawadi
    • Haveli
    • Pune
    • 411043
  • Pincode411043
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048316
  • ReraGenie IDRG-MH-82074

Builder

  • NameSatkar Reality
  • Entity typePartnership
  • PartnerRashmi Rajendra Varma

Key dates

4 months past promisethis monthRegisteredDec 2022First promiseOct 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Dec 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 28 Oct 2025)
  • Buildings2 building records
  • Documents filed125 files

Current status

45%18 of 40 units booked
70.0%Work done, per cost certificate

Figures as on 22 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Durga Vihar Wing BNA8618018
Durga Vihar Wing ANA8522022

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 20 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 85%.

Durga Vihar Wing B100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Durga Vihar Wing A72%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes90%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed135

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots135
Closed/Covered130
Open Space5
BuildingClosed/CoveredOpen SpaceTotal
Durga Vihar Wing B88593
Durga Vihar Wing A42042

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,080 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jul 2025
LandownerVillageDistrict
Mr Mahesh Eknath WaniParvatiPune
Smt Suman Eknath WaniParvatiPune

Approvals and building plan

Sanctioning authorityPune Municipal Corpoaration
Permissible FSI3004.54
Proposed, not sanctioned3,005 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhandarkar Road
Estimated costRs 14.29 cr
Cost incurredRs 10.01 cr
Work done70.0%
BuildingWingEstimatedIncurred
Durga Vihar Wing BNARs 7.09 crRs 3.71 cr
Durga Vihar Wing ANARs 4.70 crRs 4.61 cr
-NARs 2.50 crRs 1.69 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShailesh Salehittal Architect
ArchitectRAJENDRA H THITE
EngineerAnand Shindekar
Chartered AccountantBogati & Co
Chartered AccountantS P A K & Co.
PartnerRole in project
Satkar Reality-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24102518163Oct 2025 → Jun 2026

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow. But now we have completed our 95 % Project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 _durga vihar_mar 26.pdf22 Apr 2026
Withdrawal Update Form 2File: FORM2 _durga vihar _mar 26.pdf22 Apr 2026
Withdrawal Update Form 3File: Form 3 _durga vihar_mar 26.pdf22 Apr 2026
Withdrawal Update Form 1File: Durga Vihar Architect s certificate.pdf20 Jan 2026
Withdrawal Update Form 2File: Durga Vihar Engineers Certificate.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Durga Final Dec 25.pdf20 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf27 Oct 2025
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf24 Oct 2025
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf24 Oct 2025
Withdrawal Update Form 1File: FORM 1_Satkar Realty_SEPT 25.pdf18 Oct 2025
Withdrawal Update Form 1File: FORM 1_Satkar Realty_JUNE 25.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2_Satkar Realty_Sep 25.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2_Satkar Reality_June 25_.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3_Satkar Realty_Sep 25_compressed.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3_Satkar Realty_June 25_.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: Satkar Form 5_FY 2024-25.pdf29 Sep 2025
Form 1File: Durga Vihar F1 Jun 2023.pdf30 May 2025
Form 1File: Durga Vihar F1 Sep 2023.pdf30 May 2025
Form 1File: Durga Vihar F1 Dec 2023.pdf30 May 2025
Form 1File: Durga Vihar F1 Mar 2024.pdf30 May 2025
Form 1File: Form 1_Satkar Realty_June 24.pdf30 May 2025
Form 1File: Form 1_Satkar Realty_Sep 24.pdf30 May 2025
Form 1File: Form 1_Satkar Realty_DEC 24.pdf30 May 2025
Form 1File: Satkar Reality Form 1_March 2025.pdf30 May 2025
Form 1File: form 1 dec 2022.pdf27 May 2025
Form 2File: form 2 dec 22.pdf27 May 2025
Form 3File: form 3 dec 22.pdf27 May 2025
Form 1File: form 1 march 2023.pdf27 May 2025
Form 2File: form 2 mar 23.pdf27 May 2025
Form 3File: form 3 march 23.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Sold disclouser mar 23.pdf27 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 March 25.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera Form 3 Final.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 March 25.pdf13 May 2025
Disclosure of sold/ booked inventoryFile: Sold disclouser.pdf13 May 2025
Disclosure of sold/ booked inventoryFile: GetUserDocumentFileContent (10).pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satkar reality form 3.pdf9 Apr 2025
Layout approvalFile: HPSC0803-1_compressed.pdf5 Mar 2025
Building plan approvalFile: HPSC0804-2_compressed.pdf5 Mar 2025
Building plan approvalFile: HPSC0805-3_compressed.pdf5 Mar 2025
Building plan approvalFile: HPSC0807-4_compressed.pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: HPSC0803-1_compressed.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: HPSC0804-2_compressed.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: HPSC0805-3_compressed.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: HPSC0807-4_compressed.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Satkar Realty_June 24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Satkar Realty_Sep 24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Satkar Realty_DEC 24.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A March 23.pdf15 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A March 24.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satkar Reality F3 Dec 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satkar Reality F3 Sep 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satkar Reality F3 Jun 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satkar Reality F3 Mar 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Satkar Reality F3 Sep 2023.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Durga Vihar F1 Dec 2022.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Durga Vihar F1 Mar 2023.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Durga Vihar F1 Jun 2023.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Durga Vihar F1 Sep 2023.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Durga Vihar F1 Dec 2023.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Durga Vihar F1 Mar 2024.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3) Form 3_ Satkar Reality_June 23_11zon.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5) Form 3_ Satkar Reality_December 23_11zon.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4) Form 3_ Satkar Reality_SEP 23_11zon.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2) Form 3_ Satkar Reality_March 23_11zon.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1) Form 3_ Satkar Reality_December 22_11zon.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3) Form 2_Satkar Reality_June 23.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9) Form 2_Satkar Reality_DEC 24_11zon.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8) Form 2_Satkar Reality_Sep 24_11zon.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7) Form 2_Satkar Reality_June 24_11zon.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6) Form 2_Satkar Reality_March 24_11zon.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4) Form 2_Satkar Reality_SEP 23.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2) Form 2_Satkar Reality_March 23.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1) Form 2_Satkar Reality_DEC 22.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5) Form 2_Satkar Reality_DEC 23.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: 3) Sold Disclosure SEP 23.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: 8) Sold Disclosure DEC 24.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: 7) Sold Disclosure SEP 24.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: 6) Sold Disclosure June 24.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: 5) Sold Disclosure March 24.pdf13 Feb 2025

How this compares with Pune

45%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 8 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DURGA VIHAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhankawadi13,700+ in Pune

2 kmDURGA VIHARCompleted 35Lapsed / revoked 18Other 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 104 registered projects within 2 km.

Builder: Satkar Reality

Satkar Reality has 1 registration on MahaRERA, including DURGA VIHAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DURGA VIHAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DURGA VIHAR is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DURGA VIHAR?

The registered promoter entity is Satkar Reality, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DURGA VIHAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DURGA VIHAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DURGA VIHAR?

The professionals named in the filing: Architect: Shailesh Salehittal Architect; Architect: RAJENDRA H THITE; Engineer: Anand Shindekar; Chartered Accountant: Bogati & Co; Chartered Accountant: S P A K & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DURGA VIHAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DURGA VIHAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DURGA VIHAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.