Home / Browse projects / Nagpur, Maharashtra / DREAM HOME III

Registration lapsed No litigation declared Residential / Group Housing project

DREAM HOME III

By ANUP RAMAKANT DWIVEDI

RG-MH-13380 · RERA P50500048074 · Last updated on MahaRERA portal: 2 Dec 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 29 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
May 2024Possession promised29 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

DREAM HOME III is a Residential / Group Housing project by ANUP RAMAKANT DWIVEDI in Nagpur, Maharashtra, registered with MahaRERA as P50500048074 on 8 Dec 2022. Possession was promised by 19 May 2024 and is now 29 months past that date.

At a glance

Project

  • NameDREAM HOME III
  • TypeResidential / Group Housing
  • Location
    • PLOT NO 80 KH NO 87 GORAKHNATH CO OPERATIVE HOUSING SOCIETY LTD PH NO 11 CITY SURVEY NO 118 SHEET NO 35 HOUSE NO 604/A/80 MAUZA ZINGABAI TAKLI
    • ZINGABAI...
  • Pincode440030
  • RERA no.P50500048074
  • ReraGenie IDRG-MH-13380

Builder

  • NameANUP RAMAKANT DWIVEDI
  • Entity typeIndividual

Key dates

29 months past promisethis monthRegisteredDec 2022PromisedMay 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Dec 2022
  • Promised completion19 May 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DREAM HOME IIINA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

DREAM HOME III: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area373 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI948.43
Proposed, not sanctioned948 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFRIENDS COLONY KOTAL ROAD NAGPUR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSATISH PANDEY
EngineerSATISH PANDEY
Chartered AccountantHUZAIFA SANAWADWALA
PartnerRole in project
ANUP RAMAKANT DWIVEDI-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: COMPRESS.pdf2 Dec 2022
Details of encumbrances concerned to FinanceFile: non ecumbarance fianance.pdf29 Oct 2022
Details of encumbrances concerned to FinanceFile: LEGAL.pdf29 Oct 2022
Details of encumbrances concerned to LegalFile: non ecumbarance fianance.pdf29 Oct 2022
Details of encumbrances concerned to LegalFile: LEGAL.pdf29 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA1_CA2_merged.pdf29 Oct 2022
Proforma of Agreement for saleFile: letter of allotment.pdf29 Oct 2022
Deviation Report with respect to Allotment letterFile: no devation sheet.pdf29 Oct 2022
Other - LegalFile: ALLOTMENT LETTER.pdf6 Oct 2022
Details of encumbrances concerned to LegalFile: non encumbrance law.pdf4 Oct 2022
Proforma of Agreement for saleFile: AFS.pdf4 Oct 2022
Proforma of Allotment letterFile: AFS.pdf4 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK.pdf4 Oct 2022
Deviation Report with respect to model copy of AgreementFile: NO DEVATION AGREEMENT FOR SALES.pdf4 Oct 2022
Details of encumbrances concerned to FinanceFile: finance.pdf20 Sep 2022
Layout approvalFile: nit receipt.pdf18 Aug 2022
Copy of Layout Approval (in case of layout)File: nit receipt.pdf18 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: nit receipt.pdf18 Aug 2022
Other - TechnicalFile: nit receipt.pdf18 Aug 2022
Copy of the legal title reportFile: legal title report.pdf19 Jul 2022
CERSAI detailsFile: CRESAI RECO.pdf19 Jul 2022
Other - LegalFile: DECLERATION.pdf2 Jul 2022
Layout approvalFile: SCANTIONEDMAP1.pdf7 Jun 2022
Layout approvalFile: SCANTIONEDMAP.pdf7 Jun 2022
Copy of the legal title reportFile: legal title report.pdf7 Jun 2022
Copy of Layout Approval (in case of layout)File: SCANTIONEDMAP1.pdf7 Jun 2022
Copy of Layout Approval (in case of layout)File: SCANTIONEDMAP.pdf7 Jun 2022
Declaration about Commencement CertificateFile: COMMENCEMNT CERTIFICATE.pdf7 Jun 2022
Declaration in FORM BFile: 100.pdf7 Jun 2022
Building plan approvalFile: SCANTIONEDMAP.pdf27 May 2022
Building plan approvalFile: SCANTIONEDMAP1.pdf27 May 2022
PAN CardFile: PANCARD.pdf27 May 2022
Building Plan Approval / NA Order for plotted developmentFile: SCANTIONEDMAP.pdf27 May 2022
Building Plan Approval / NA Order for plotted developmentFile: SCANTIONEDMAP1.pdf27 May 2022
Commencement Certificates / NA Order for plotted developmentFile: bulding permit.pdf27 May 2022
CERSAI detailsFile: cercai.pdf27 May 2022

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DREAM HOME III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ZINGABAI TAKLI2,800+ in Nagpur

Builder: ANUP RAMAKANT DWIVEDI

ANUP RAMAKANT DWIVEDI has 1 registration on MahaRERA, including DREAM HOME III. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that DREAM HOME III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DREAM HOME III is delayed beyond 19 May 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DREAM HOME III?

The registered promoter entity is ANUP RAMAKANT DWIVEDI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DREAM HOME III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DREAM HOME III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DREAM HOME III?

The professionals named in the filing: Architect: SATISH PANDEY; Engineer: SATISH PANDEY; Chartered Accountant: HUZAIFA SANAWADWALA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DREAM HOME III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DREAM HOME III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DREAM HOME III to a free account